Line 6: Line 6:
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
  * Mark and Hirata-san at Mitaka
   * Gathered parts for cable making.
  * Mark and Hirata-san at Kamioka:
   * Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame.
   * Installed two more LPCDs and the stepper motor driver in the PR2 rack.
   * Ran cables from the rack to the second and third sat amps (for the IRM OSEMs).
   * Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs.
   * Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement.
   * Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4).
   * Added extension to the IM pico cable for the BF yaw pico.
   * Made LVDT adapter cable.
  * Mark worked on schedule.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark and Hirata-san at Mitaka
      • Gathered parts for cable making.
    • Mark and Hirata-san at Kamioka:
      • Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame.
      • Installed two more LPCDs and the stepper motor driver in the PR2 rack.
      • Ran cables from the rack to the second and third sat amps (for the IRM OSEMs).
      • Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs.
      • Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement.
      • Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4).
      • Added extension to the IM pico cable for the BF yaw pico.
      • Made LVDT adapter cable.
    • Mark worked on schedule.