==== Report for week of 4/23 ====
 * We hung the optic and set its pitch. The winch system had a lot of slop in it but the technique of relaxing the wires by lifting the optic on the EQ stops was effective in getting consistent results.
 * We tightened the clamps using a torque wrench, using settings of 5 N.m for the primary clamps and 20 N.m for the secondary.
 * We hung the RM and set its pitch. The RM winches were a lot more consistent.
 * However when tightening the clamps, the wire on the +Y side broke at the bottom edge of primary clamp. The wire on the -Y held, so the RM dropped a few mm onto the trolley on the +Y side.
 * We raised the RM trolley to support the RM and left the optic hanging inside it overnight as a safety test.
 * We then reversed the usual installation procedure to remove the RM and get the mirror box around the optic. We used clamp pieces as spacers to bridge the gaps created by the fact that the optic had been raised 3 mm during hanging and could not safely be lowered. We then cut the wires, leaving the op

==== Plan for week of 4/30 ====
 * Shoda-san at Mitaka.
 * Mark, Enzo at Kamioka Mon-Wed or TBD.
 * Others having fun doing Golden Week stuff.
 * --
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Do BF TFs.
 * Continue SR3 hang.

==== Plan for week of 5/7 ====
 * Shoda-san at Mitaka.
 * Hirata-san at Kamioka Mon-Wed, then Mitaka.
 * Kozu-kun at Kamioka Wed-Fri (but may be working with PEM on Fri).
 * Others (Mark, Enzo, Tanioka-kun) at Kamioka full week
 * --
 * Continue SR3 Hang
  * Inspect clamps and decide whether to reuse or swap in clamps from SRM IM.
  * Rehang optic.
  * Rehang RM.
  * Cable RM OSEMs.
 * Prepare for filter testing
  * Remove cracked blades from F0 #1 and #3.
  * Remove floor panel in SR3 area.
  * Set up filter building trolley with crossbars, jacks and F0 test masses.
 
 * Etc
  * Test prototype SR3 safety bar, and set up second safety bar.
  * Negotiate with Mirapro to get SRM mushroom installed, avoiding 5/15.

==== Report for week of 10/29 ====
 * SRM
  * Enzo repaired some broken cables and made some long cables from shorter ones. We ultrasonically cleaned them at Toyama U, with help from Yamamoto-san. Enzo then reinforced the joins with EP30 (two cables) or heat shrink.
  * Hirata-san finished tuning the PI. It is now complete except for some PEEK cable clamp pieces which are expected next Monday.
  * Hirata-san wiped writing marks off the F0 and SF yoke magnets, and off the PI.
  * Hirata-san found we were running out of magnets and ordered more - we have almost enough (short by one) for the SF damper, but will need more for the LBB damper.
  * Fabian cabled and tested the BF cap picos.
  * Fabian routed all the cables up to the underside of the SF. He cabled and tested the SF LVDT and stepper.
  * We added the SF cap and weighed the SF/... section. We appear to have a good amount of load capacity margin.
 * SR2
  * We opened the SR2 tank, borrowed a geophone for Fujii-kun's geophone test, and left the IP locked.
  * We gathered parts for the SR2 OL. We believe we have all the pieces we need except for an LED (the one originally allocated to SR2 is currently being used for pitch setting on SRM and we may need to steal it back). Akutsu-san wants to supervise us setting up the LED and receiver supports, so that will happen next week.
 * SR3
  * Terrence visited for another week and made more measurements on the OL. A report is forthcoming.
 * BS
  * We searched for the dog clamps that we had borrowed from AOS to serve as ballast for the BS LBB and returned them to the AOS pallet.
 * Electronics
  * Enzo analyzed the LPCD and worked out the resistors we need to get the drive current recommended for the IM-V OSEMs by Shoda-san.
Line 45: Line 25:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 49: Line 27:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 51: Line 29:
==== Vacation Info ====
 * Fabian vacation, 3/26-4/27 (then gone).
==== Plan for week of 11/4 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence
  * Add magnets to SF damper.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.

==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.

==== Plan for week of 11/18 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Crane into tank.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/29

  • SRM
    • Enzo repaired some broken cables and made some long cables from shorter ones. We ultrasonically cleaned them at Toyama U, with help from Yamamoto-san. Enzo then reinforced the joins with EP30 (two cables) or heat shrink.
    • Hirata-san finished tuning the PI. It is now complete except for some PEEK cable clamp pieces which are expected next Monday.
    • Hirata-san wiped writing marks off the F0 and SF yoke magnets, and off the PI.
    • Hirata-san found we were running out of magnets and ordered more - we have almost enough (short by one) for the SF damper, but will need more for the LBB damper.
    • Fabian cabled and tested the BF cap picos.
    • Fabian routed all the cables up to the underside of the SF. He cabled and tested the SF LVDT and stepper.
    • We added the SF cap and weighed the SF/... section. We appear to have a good amount of load capacity margin.
  • SR2
    • We opened the SR2 tank, borrowed a geophone for Fujii-kun's geophone test, and left the IP locked.
    • We gathered parts for the SR2 OL. We believe we have all the pieces we need except for an LED (the one originally allocated to SR2 is currently being used for pitch setting on SRM and we may need to steal it back). Akutsu-san wants to supervise us setting up the LED and receiver supports, so that will happen next week.
  • SR3
    • Terrence visited for another week and made more measurements on the OL. A report is forthcoming.
  • BS
    • We searched for the dog clamps that we had borrowed from AOS to serve as ballast for the BS LBB and returned them to the AOS pallet.
  • Electronics
    • Enzo analyzed the LPCD and worked out the resistors we need to get the drive current recommended for the IM-V OSEMs by Shoda-san.

To-Do Lists, Schedule

Plan for week of 11/4

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Main sequence
    • Add magnets to SF damper.
    • Install #353 poles
    • Move NB-03 jacks down.
    • Crane PI into AF.
    • Install F0-SF rod (#331) and flying saucer.
    • Route SF/... cables up to underside of F0.
    • Do vertical height budget.
    • Adjust SF trim mass for balance and keystone height.
    • Cable/test IP LVDTs.
    • Cable/test IP FRs.
  • LBB
    • Move KOACH filters
    • Put LBB damper rings in tank.
    • Set tank jacks to nominal height.

Plan for week of 11/11

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.

Plan for week of 11/18

  • Friday 11/23 is Labor Thanksgiving Day.
  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.
  • Crane into tank.