Line 6: Line 6:
==== Report for week of 4/23 ====
 * We hung the optic and set its pitch. The winch system had a lot of slop in it but the technique of relaxing the wires by lifting the optic on the EQ stops was effective in getting consistent results.
 * We tightened the clamps using a torque wrench, using settings of 5 N.m for the primary clamps and 20 N.m for the secondary.
 * We hung the RM and set its pitch. The RM winches were a lot more consistent.
 * However when tightening the clamps, the wire on the +Y side broke at the bottom edge of primary clamp. The wire on the -Y held, so the RM dropped a few mm onto the trolley on the +Y side.
 * We raised the RM trolley to support the RM and left the optic hanging inside it overnight as a safety test.
 * We then reversed the usual installation procedure to remove the RM and get the mirror box around the optic. We used clamp pieces as spacers to bridge the gaps created by the fact that the optic had been raised 3 mm during hanging and could not safely be lowered. We then cut the wires, leaving the op
 * Shoda-san made SRM model (Dropbox/Largefiles/Subsystems/VIS/Design/SR/Model/SRM-MetalMass_180426)
 * Shoda-san made 2D drawings of LBB ballast masses
 * Hirata-san washed parts.
==== Control Issues ====
 * Resonant frequency table is ready for BS ([[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/BSdetail|BS suspension details]])
 * We found the inconsistency between local damping measurement and interferometer measurement. ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4811|klog4811]])
  The TF gains from IML to TML, and from TML to TML are different from the interferometer measurement.
==== Report for week of 9/17 ====
 * Monday 9/17 was holiday.
 * We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico.
 * We set the SF damper gap to 6 mm.
 * We set the SR2 pitch with the optic lever, aligned the IRM, and set all the OSEMs to have good clearance and midrange output.
 * We locked the SR2 suspension, craned it into the tank and hooked the LBB damper rings (but not the LBB yet).
 * With help from Ohishi-san, we removed the First Contact from SR2.
 * Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc.
 * Mark added some thin arc weights to the inventory and finalized the number of various types to order (8*38 mm + 9*10 mm).
 * Panwei copied control filters over from the SR3.
 
==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
===== SR2 =====
 * Move SR2 in-air cables.
 * Unlock and realign suspension.
===== SRM =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.
 * Suspend IM and tweak height/balance.
Line 21: Line 30:
  * I checked the TML gain, which are calculated from TMP and TMY measurements, and found EUL2COIL matrix was different from what I supposed.
   --> Fixed it and updated the state space model. Might be OK now for TF from TML to TML. (Komori-kun will check it.)
  * I checked the calibration gain of OSEMs and found that the measured values are not used. But it makes only small difference.
  * Compare the TFs from BFGAS to BFGAS and BFGAS to IMV, and they are inconsistent for BS and PR2. (No data found for PR3)([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4807|klog4807]])
  * Comparing TFs from IMP to TMP and from IMY to TMY also helps to check the OSEM calibration by comparing OSEM signals and Oplev signals.
   Found the matrix to convert OSEM signals (um) to pitch (urad) is different from what I calculated. To be checked.
   The measurement will be done after phase-I.
==== Plan for week of 10/1 ====
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.
Line 29: Line 37:
 * Constructing the tool to implement the current filterbank information to state space model.

==== Plan for week of 4/30 ====
 * Shoda-san at Mitaka.
 * Mark, Enzo at Kamioka Mon-Wed or TBD.
 * Others having fun doing Golden Week stuff.
 * --
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Do BF TFs.

==== Plan for week of 5/7 ====
 * Shoda-san at Mitaka.
 * Enzo at Kamioka from Tue.
 * Mark, Hirata-san at Kamioka full week.
 * Kozu-kun at Kamioka??
 * Tanioka-kun at Kamioka Mon, Tue.
 * --
 * Continue SR3 Hang
  * Inspect clamps and decide whether to reuse or swap in clamps from SRM IM.
  * Rehang optic.
  * Rehang RM.
  * Cable RM OSEMs.
 * Prepare for filter testing
  * Remove cracked blades from F0 #1 and #3.
  * Remove floor panel in SR3 area.
  * Set up filter building trolley with crossbars, jacks and F0 test masses.
 
 * Etc
  * Test prototype SR3 safety bar, and set up second safety bar.
  * Negotiate with Mirapro to get SRM mushroom installed, avoiding 5/15.
==== Plan for week of 10/8 ====
 * Monday 10/8 is Sports Day.
 * Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
 * Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.
===== SR2/SR3 =====
 * Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.
===== SRM =====
 * Continue installation.
Line 62: Line 47:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 66: Line 49:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 68: Line 51:
==== Vacation Info ====
 * Fabian vacation, 3/26-4/27 (then gone). 
==== Vacation/Visitor Info ====
 * Enzo: 9/15 through 10/8 vacation in Chile.
 * Terrence: 10/8-12
, 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 9/17

  • Monday 9/17 was holiday.
  • We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico.
  • We set the SF damper gap to 6 mm.
  • We set the SR2 pitch with the optic lever, aligned the IRM, and set all the OSEMs to have good clearance and midrange output.
  • We locked the SR2 suspension, craned it into the tank and hooked the LBB damper rings (but not the LBB yet).
  • With help from Ohishi-san, we removed the First Contact from SR2.
  • Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc.
  • Mark added some thin arc weights to the inventory and finalized the number of various types to order (8*38 mm + 9*10 mm).
  • Panwei copied control filters over from the SR3.

Plan for week of 9/24

  • Monday 9/24 is holiday (Autumn Equinox).
  • Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.

SR2
  • Move SR2 in-air cables.
  • Unlock and realign suspension.

SRM
  • Set pitch of SRM and RM, tighten clamps, remove winch system.
  • Weigh IM/... section.
  • Build up SS to BF level.
  • Add BF.
  • Suspend IM and tweak height/balance.

Plan for week of 10/1

  • Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.

SRM
  • Cable/test BF.
  • Install IRM.
  • Install/cable/test IM OSEMs.

Plan for week of 10/8

  • Monday 10/8 is Sports Day.
  • Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
  • Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.

SR2/SR3
  • Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.

SRM
  • Continue installation.

To-Do Lists, Schedule

Vacation/Visitor Info

  • Enzo: 9/15 through 10/8 vacation in Chile.
  • Terrence: 10/8-12, 10/29-11/2 at Kamioka.