==== Report for weeks of 5/14, 5/21 ====
 * We weighted the IM/... section of the SR3.
 * We set up for the F0 blade prototype test.
 * Takahashi-san characterized the F0 prototype blades, and ordered final blades based on the BS and SR mass budgets.
 * Hirata-san characterized the LBB blades and identified three sets with blades of similar strength, plus two weaker ones. However he realized that M12x50 Bumax screws for the blade sets had not been ordered, so he got a new quote and ordered them for delivery 6/11.
 * Mirapro installed the mushroom section of the SRM tank.
 * We craned in the BF and cabled and tested the yaw pico, the FR stepper and the LVDT.
 * We hung the IM/... section from the BF, removed ≈200 g of trim mass and rearranged the rest to get the desired height, pitch and roll.
 * We added the sides of the IRM and the IM OSEMs, cabled the OSEMs, and adjusted everything to get good lateral and in/out alignment of the OSEMs.
 * Enzo did TFs using the IM OSEMs and the BF LVDT.
 * Hirata-san organized getting the LBB damper rings into the SR3 tank. He joined the halves of the Cu and magnet rings and got them ready for craning (which will happen later when we have rebuilt the SR3 IP and have somewhere to park the lid of the vacuum chamber). However he encountered a problem with the top ring: one of the screw holes in the top of the tank is not fully threaded, so one of the pillars supporting the top ring cannot be attached. He is considering various options.
 * Hirata-san and Kozu-kun made rod assemblies for the LBB damper rings.
 * Enzo made a batch of flipping and non-flipping feedthrough adapters.
 * Yamamoto-san connected up the SRM rack.
==== Report for week of 5/28 ====
 * Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
 * Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
 * Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
 * Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
 * After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
 * Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
 * Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
 * Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
 * We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
 * We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
 * Enzo did several rounds of TFs on the BF/... section of the suspension, and ins
Line 24: Line 22:
 * Matteo at Kamioka from Tue. He may help Type B to get experience.
Line 25: Line 24:
   * TBD.  * --
 * Hirata-san will modify and clean some Promec masses at Mitaka (making threaded holes unthreaded to allow stacking).
 * Cable and test BF cap picos.
 * Install internal ballast masses.
 * Install cap ballast masses.
 * Build up security structure to SF level.
 * Crane in SF and remove cap.
 * Hook BF and adjust total ballast.
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Adjust BF trim mass.
Line 29: Line 37:
   *  * --
 * Readjust payload.
 * Take TFs.
 * Add budgeted ballast mass to SF.
 * Cable, test SF LVDT and FR.
 * Characterize final F0 blades.
 * Finish four half-assembled geophones.

==== Plan for week of 6/11 ====
 * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
 * --
 * Rebuild F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
 * Make LBB blade sets (or at least 3 of 9).
Line 33: Line 54:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 5/28

  • Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
  • Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
  • Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
  • Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
  • After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
  • Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
  • Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
  • Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
  • We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
  • We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
  • Enzo did several rounds of TFs on the BF/... section of the suspension, and ins

Plan for week of 5/28

  • Mark, Enzo at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
  • Matteo at Kamioka from Tue. He may help Type B to get experience.
  • Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
  • --
  • Hirata-san will modify and clean some Promec masses at Mitaka (making threaded holes unthreaded to allow stacking).
  • Cable and test BF cap picos.
  • Install internal ballast masses.
  • Install cap ballast masses.
  • Build up security structure to SF level.
  • Crane in SF and remove cap.
  • Hook BF and adjust total ballast.
  • Route cables through SF-BF flying saucer up to bottom of SF.
  • Adjust BF trim mass.

Plan for week of 6/4

  • Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
  • --
  • Readjust payload.
  • Take TFs.
  • Add budgeted ballast mass to SF.
  • Cable, test SF LVDT and FR.
  • Characterize final F0 blades.
  • Finish four half-assembled geophones.

Plan for week of 6/11

  • Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
  • --
  • Rebuild F0 #3 for SR3.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.
  • Make LBB blade sets (or at least 3 of 9).