Differences between revisions 286 and 296 (spanning 10 versions)
Revision 286 as of 2018-05-24 21:46:08
Size: 2524
Editor: MarkBarton
Comment:
Revision 296 as of 2018-06-21 15:21:59
Size: 2970
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for weeks of 5/14, 5/21 ====
 * We weighted the IM/... section of the SR3.
 * We set up for the F0 blade prototype test.
 * Takahashi-san characterized the F0 prototype blades, and ordered final blades based on the BS and SR mass budgets.
 * Hirata-san characterized the LBB blades and identified three sets with blades of similar strength, plus two weaker ones. However he realized that M12x50 Bumax screws for the blade sets had not been ordered, so he got a new quote and ordered them for delivery 6/11.
 * Mirapro installed the mushroom section of the SRM tank.
 * We craned in the BF and cabled and tested the yaw pico, the FR stepper and the LVDT.
 * We hung the IM/... section from the BF, removed ≈200 g of trim mass and rearranged the rest to get the desired height, pitch and roll.
 * We added the sides of the IRM and the IM OSEMs, cabled the OSEMs, and adjusted everything to get good lateral and in/out alignment of the OSEMs.
 * Enzo did TFs using the IM OSEMs and the BF LVDT.
 * Hirata-san organized getting the LBB damper rings into the SR3 tank. He joined the halves of the Cu and magnet rings and got them ready for craning (which will happen later when we have rebuilt the SR3 IP and have somewhere to park the lid of the vacuum chamber). However he encountered a problem with the top ring: one of the screw holes in the top of the tank is not fully threaded, so one of the pillars supporting the top ring cannot be attached. He is considering various options.
 * Hirata-san and Kozu-kun made rod assemblies for the LBB damper rings.
 * Enzo made a batch of flipping and non-flipping feedthrough adapters.
 * Yamamoto-san connected up the SRM rack.
==== Report for week of 6/18 ====
 * Mark checked the health of the suspensions after an earthquake on Monday morning. The BS watchdog tripped and there was a few µrad change in the pointing, but otherwise it was fine. SR3 and SR2 were also fine.
 * Mark, Enzo and Terrence finalized the trim mass on the BF to set the SF keystone height and BF pitch/roll.
 * They weighed the SF/... section. With no internal trim mass in the SF but with the flying saucer and rod, but with 2 Promec masses for rough balance, it was 255.4 kg, so allowing 1 kg for cables and fine trim mass, we would like a PI load capacity of 256.4 kg.
 * Hirata-san and Kozu-kun struggled to tune the top filter for SR3 - see klogs 5310, 5324, 5337, xxxx. At first the results were somewhat unrepeatable, with high frequency and low load capacity. This was improved by using a torque wrench (set to 50 N.m) to tighten the blade base clamp screws, retightening the blade tip screws (which had worked loose) and tightening the collar on the end of the shaft of the magic wand. Eventually ...
 * Enzo and Terrence cabled and tested the SF fishing rod, and reversed the connections on the SF LVDT actuation to bring it to standard polarity.
 * Mark and Enzo made many improvements to the Type B MEDM screens.
 * Enzo and Mark measured the BF and SF bounce frequencies (with the other keystone locked).
 * Enzo replaced a HPCD that seemed to have failed during the bounce test (but had just had a watchdog trip), and then replaced the replacement, which really did fail. It turns out we need to avoid applying more than about 25000 counts of GAS actuation.
 * Enzo offloaded the BF LVDT actuator with the BF FR to remove the need for a 10000 ct offset.
 
==== Plan for week of 6/25 ====
 * Mark, Enzo, Hirata-san, Terrence at Kamioka Mon-Fri.
 * Kozu-kun at Kamioka except Thu.
 * --
 * Shutdown Type B controls (as far as possible) in preparation for risk of accidental power outage during electrical work on 6/26.
 * Add calculated ballast to SF.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
 * Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
 * Install PI.
 * Suspend SF/... section.
 * Lots of cable routing.
Line 21: Line 30:
==== Plan for week of 5/28 ====
 * Mark, Enzo at Kamioka Mon-Fri.
 * Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
 * Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
 
 * TBD.
==== Plan for week of 6/4 ====
 * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
 
 *
==== Plan for week of 7/2 ====
 * Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
 * Enzo at Kamioka Mon-Wed
 * Kozu-kun at Kamioka except Wed.
Line 33: Line 36:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 37: Line 38:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 40: Line 41:
 * Kozu-kun: 7/4 Tokyo.
 * Enzo: 7/5-6 NAOJ Party, Mitaka.
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/18 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 6/18

  • Mark checked the health of the suspensions after an earthquake on Monday morning. The BS watchdog tripped and there was a few µrad change in the pointing, but otherwise it was fine. SR3 and SR2 were also fine.
  • Mark, Enzo and Terrence finalized the trim mass on the BF to set the SF keystone height and BF pitch/roll.
  • They weighed the SF/... section. With no internal trim mass in the SF but with the flying saucer and rod, but with 2 Promec masses for rough balance, it was 255.4 kg, so allowing 1 kg for cables and fine trim mass, we would like a PI load capacity of 256.4 kg.
  • Hirata-san and Kozu-kun struggled to tune the top filter for SR3 - see klogs 5310, 5324, 5337, xxxx. At first the results were somewhat unrepeatable, with high frequency and low load capacity. This was improved by using a torque wrench (set to 50 N.m) to tighten the blade base clamp screws, retightening the blade tip screws (which had worked loose) and tightening the collar on the end of the shaft of the magic wand. Eventually ...
  • Enzo and Terrence cabled and tested the SF fishing rod, and reversed the connections on the SF LVDT actuation to bring it to standard polarity.
  • Mark and Enzo made many improvements to the Type B MEDM screens.
  • Enzo and Mark measured the BF and SF bounce frequencies (with the other keystone locked).
  • Enzo replaced a HPCD that seemed to have failed during the bounce test (but had just had a watchdog trip), and then replaced the replacement, which really did fail. It turns out we need to avoid applying more than about 25000 counts of GAS actuation.
  • Enzo offloaded the BF LVDT actuator with the BF FR to remove the need for a 10000 ct offset.

Plan for week of 6/25

  • Mark, Enzo, Hirata-san, Terrence at Kamioka Mon-Fri.
  • Kozu-kun at Kamioka except Thu.
  • --
  • Shutdown Type B controls (as far as possible) in preparation for risk of accidental power outage during electrical work on 6/26.
  • Add calculated ballast to SF.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.
  • Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
  • Install PI.
  • Suspend SF/... section.
  • Lots of cable routing.

Plan for week of 7/2

  • Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
  • Enzo at Kamioka Mon-Wed
  • Kozu-kun at Kamioka except Wed.

To-Do Lists, Schedule

Vacation Info

  • Kozu-kun: 7/4 Tokyo.
  • Enzo: 7/5-6 NAOJ Party, Mitaka.
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/18 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)