==== Report for week of 5/28 ==== * Enzo tested the LVDT driver repaired by Tanaka-san - it was fine. * Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data. * Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF. * Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings). * After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole. * Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2). * Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3). * Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades. * We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles. * We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap. * Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank. * Enzo installed damping filters for the IM OSEMs. ==== Plan for week of 5/28 ==== * Mark, Enzo at Kamioka Mon-Fri. * Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.) * Matteo at Kamioka from Tue. He may help Type B to get experience. * Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.) * -- ==== Plan for week of 6/4 ==== * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.) * -- * Cable and test BF cap picos. * Build up security structure to SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF and weigh SF/... section. * Cable, test SF LVDT and FR. * Characterize final F0 blades. ==== Plan for week of 6/11 ==== * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.) * -- * Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Make LBB blade sets (or at least 3 of 9). |
==== Report for week of 10/29 ==== * SRM * Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half. * Fabian and Hirata-san finished the in-vacuum cabling. * Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling. * We're now ready for final tests of the SF/... items and initial tests of the PI items. * Enzo and Fujii-kun built three geophones for SRM. * Mark worked on the height budget. * SR2 * Enzo experimented with [[http://www2.mpq.mpg.de/~ros/geo600_docu/soft/liso/manual.pdf|LISO]] (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.) |
Line 53: | Line 20: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] | * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] |
Line 55: | Line 22: |
==== Vacation Info ==== | ==== Plan for week of 11/11 ==== * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri. ===== SRM ===== * Main sequence ==== Plan for week of 11/19 ==== * Friday 11/23 is Labor Thanksgiving Day. * Mark, Enzo and Fabian at Kamioka Mon-Thu. * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting). ===== SRM ===== * Go/no-go test of all electronics items, especially SF/... section. * Finish vertical height check and adjust SF trim mass as required. * Unlock IP and center roughly. * Check/adjust alignment of SS. * Calibrate IP LVDTs. * Add arc weights and geophones. * Improve centering/tuning of IP and SS alignment. * Disconnect cables at feedthroughs, lock suspension. * Crane into tank. ===== SR2 ===== * Assist MIF team with pico cables and LBB breadboard ballast. * Install SR2 OL pillar and shelf (with AOL supervision)? ==== Plan for week of 11/26 ==== * Move SRM in-air cables over to tank. * Remove First Contact. * Unlock and align SRM. * Hook and roughly ballast LBB. ==== Plan for week of 12/3 ==== * f2f Meeting at NAOJ - no Kamioka work. ==== Vacation/Event Info ==== * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 10/29
- SRM
- Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
- Fabian and Hirata-san finished the in-vacuum cabling.
- Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
- We're now ready for final tests of the SF/... items and initial tests of the PI items.
- Enzo and Fujii-kun built three geophones for SRM.
- Mark worked on the height budget.
- SR2
Enzo experimented with LISO (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)
To-Do Lists, Schedule
Plan for week of 11/11
- Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
SRM
- Main sequence
Plan for week of 11/19
- Friday 11/23 is Labor Thanksgiving Day.
- Mark, Enzo and Fabian at Kamioka Mon-Thu.
- Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
SRM
- Go/no-go test of all electronics items, especially SF/... section.
- Finish vertical height check and adjust SF trim mass as required.
- Unlock IP and center roughly.
- Check/adjust alignment of SS.
- Calibrate IP LVDTs.
- Add arc weights and geophones.
- Improve centering/tuning of IP and SS alignment.
- Disconnect cables at feedthroughs, lock suspension.
- Crane into tank.
SR2
- Assist MIF team with pico cables and LBB breadboard ballast.
- Install SR2 OL pillar and shelf (with AOL supervision)?
Plan for week of 11/26
- Move SRM in-air cables over to tank.
- Remove First Contact.
- Unlock and align SRM.
- Hook and roughly ballast LBB.
Plan for week of 12/3
- f2f Meeting at NAOJ - no Kamioka work.
Vacation/Event Info
- Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).