 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He is trying the cup that had been made for the PR2 on the actual PR2. It works to confine the acetone, and we will see shortly how much soaking is required to get a prism off. We will then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Hirata-san worked on the crane height problem with Saito-sensei. They concluded that craning in the suspension is possible but will require not just the vacuum tank lid but the ≈30 cm section of tank below it to be removed.
  * Hirata-san liaised with Nakamura-san of Mirapro. Mirapro could start assembling the frame in the first week of July.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and will be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark did a top level schedule.
  * Mark released a draft (about half-finished) of [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| JGW-E1504235 - BS Installation Procedure]].
  * Mark updated [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] with a better arrangement for the IM and BF pico motor cables, as well as various other minor fixes.
  * Mark organized a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - SOLVED
  * Installation stuff
   * Crane scale - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
 * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
 * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
 * We craned the PI. There was a minor safety incident - see below.
 * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
 * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
 * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
 * We set up the BS gluing jigs and applied the glue. We will check the results on Monday.

==== Plan for week of 7/24 ====
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
 * Check results of gluing.
 * Finish BF rebuild.
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.

==== Plan for week of 7/31 ====
Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).
 * Weigh/trim BS/RM/IM.
 * Bring in rebuilt BF.

Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):

  • We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
  • Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
  • We craned the PI. There was a minor safety incident - see below.
  • Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
  • Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
  • We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
  • We set up the BS gluing jigs and applied the glue. We will check the results on Monday.

Plan for week of 7/24

Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).

  • Check results of gluing.
  • Finish BF rebuild.
  • Recheck alignment of assembly frame and centering of optical table.
  • Install IM, suspend BS and RM.

Plan for week of 7/31

Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).

  • Weigh/trim BS/RM/IM.
  • Bring in rebuilt BF.

Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct