 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He is trying the cup that had been made for the PR2 on the actual PR2. It works to confine the acetone, and we will see shortly how much soaking is required to get a prism off. We will then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Hirata-san worked on the crane height problem with Saito-sensei. They concluded that craning in the suspension is possible but will require not just the vacuum tank lid but the ≈30 cm section of tank below it to be removed.
  * Hirata-san liaised with Nakamura-san of Mirapro. Mirapro could start assembling the frame in the first week of July.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and will be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark did a top level schedule.
  * Mark released a draft (about half-finished) of [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| JGW-E1504235 - BS Installation Procedure]].
  * Mark updated [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] with a better arrangement for the IM and BF pico motor cables, as well as various other minor fixes.
  * Mark organized a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - SOLVED
  * Installation stuff
   * Crane scale - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for weeks of 5/14, 5/21 ====
 * We set up for the F0 blade prototype test.
 * Takahashi-san characterized the F0 prototype blades, and ordered final blades based on the BS and SR mass budgets.
 * Hirata-san characterized the LBB blades and identified three sets with blades of similar strength, plus two weaker ones. However he realized that M12x50 Bumax screws for the blade sets had not been ordered, so he got a new quote and ordered them for delivery 6/11.
 * Mirapro installed the mushroom section of the SRM tank.
 * We added the budgeted amount of ballast to the IM/... section of the SR3.
 * We craned in the BF and cabled and tested the yaw pico, the FR stepper and the LVDT.
 * We hung the IM/... section from the BF, removed ≈200 g of trim mass and rearranged the rest to get the desired height, pitch and roll.
 * We added the sides of the IRM and the IM OSEMs, cabled the OSEMs, and adjusted everything to get good lateral and in/out alignment of the OSEMs.
 * Enzo did TFs using the IM OSEMs and the BF LVDT.
 * We added the BF cap and weighed the BF/... section. We will need to remove the cap again and add about 5 kg of ballast mass.
 * Hirata-san organized getting the LBB damper rings into the SR3 tank. He joined the halves of the Cu and magnet rings and got them ready for craning (which will happen later when we have rebuilt the SR3 IP and have somewhere to park the lid of the vacuum chamber). However he encountered a problem with the top ring: one of the screw holes in the top of the tank is not fully threaded, so one of the pillars supporting the top ring cannot be attached. He is considering various options.
 * Hirata-san and Kozu-kun made rod assemblies for the LBB damper rings.
 * Enzo made a batch of flipping and non-flipping feedthrough adapters.
 * Yamamoto-san connected up the SRM rack.
 * We installed a booth thermometer for the SR3.

==== Plan for week of 5/28 ====
 * Mark, Enzo at Kamioka Mon-Fri.
 * Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
 * Matteo at Kamioka from Tue. He may help Type B to get experience.
 * Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
 * --
 * Hirata-san will modify and clean some Promec masses at Mitaka (making threaded holes unthreaded to allow stacking).
 * Cable and test BF cap picos.
 * Install internal ballast masses.
 * Install cap ballast masses.
 * Build up security structure to SF level.
 * Crane in SF and remove cap.
 * Hook BF and adjust total ballast.
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Adjust BF trim mass.

==== Plan for week of 6/4 ====
 * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
 * --
 * Readjust payload.
 * Take TFs.
 * Add budgeted ballast mass to SF.
 * Cable, test SF LVDT and FR.
 * Characterize final F0 blades.
 * Finish four half-assembled geophones.

==== Plan for week of 6/11 ====
 * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
 * --
 * Rebuild F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
 * Make LBB blade sets (or at least 3 of 9).

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for weeks of 5/14, 5/21

  • We set up for the F0 blade prototype test.
  • Takahashi-san characterized the F0 prototype blades, and ordered final blades based on the BS and SR mass budgets.
  • Hirata-san characterized the LBB blades and identified three sets with blades of similar strength, plus two weaker ones. However he realized that M12x50 Bumax screws for the blade sets had not been ordered, so he got a new quote and ordered them for delivery 6/11.
  • Mirapro installed the mushroom section of the SRM tank.
  • We added the budgeted amount of ballast to the IM/... section of the SR3.
  • We craned in the BF and cabled and tested the yaw pico, the FR stepper and the LVDT.
  • We hung the IM/... section from the BF, removed ≈200 g of trim mass and rearranged the rest to get the desired height, pitch and roll.
  • We added the sides of the IRM and the IM OSEMs, cabled the OSEMs, and adjusted everything to get good lateral and in/out alignment of the OSEMs.
  • Enzo did TFs using the IM OSEMs and the BF LVDT.
  • We added the BF cap and weighed the BF/... section. We will need to remove the cap again and add about 5 kg of ballast mass.
  • Hirata-san organized getting the LBB damper rings into the SR3 tank. He joined the halves of the Cu and magnet rings and got them ready for craning (which will happen later when we have rebuilt the SR3 IP and have somewhere to park the lid of the vacuum chamber). However he encountered a problem with the top ring: one of the screw holes in the top of the tank is not fully threaded, so one of the pillars supporting the top ring cannot be attached. He is considering various options.
  • Hirata-san and Kozu-kun made rod assemblies for the LBB damper rings.
  • Enzo made a batch of flipping and non-flipping feedthrough adapters.
  • Yamamoto-san connected up the SRM rack.
  • We installed a booth thermometer for the SR3.

Plan for week of 5/28

  • Mark, Enzo at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
  • Matteo at Kamioka from Tue. He may help Type B to get experience.
  • Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
  • --
  • Hirata-san will modify and clean some Promec masses at Mitaka (making threaded holes unthreaded to allow stacking).
  • Cable and test BF cap picos.
  • Install internal ballast masses.
  • Install cap ballast masses.
  • Build up security structure to SF level.
  • Crane in SF and remove cap.
  • Hook BF and adjust total ballast.
  • Route cables through SF-BF flying saucer up to bottom of SF.
  • Adjust BF trim mass.

Plan for week of 6/4

  • Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
  • --
  • Readjust payload.
  • Take TFs.
  • Add budgeted ballast mass to SF.
  • Cable, test SF LVDT and FR.
  • Characterize final F0 blades.
  • Finish four half-assembled geophones.

Plan for week of 6/11

  • Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
  • --
  • Rebuild F0 #3 for SR3.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.
  • Make LBB blade sets (or at least 3 of 9).