 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He is trying the cup that had been made for the PR2 on the actual PR2. It works to confine the acetone, and we will see shortly how much soaking is required to get a prism off. We will then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Hirata-san worked on the crane height problem with Saito-sensei. They concluded that craning in the suspension is possible but will require not just the vacuum tank lid but the ≈30 cm section of tank below it to be removed.
  * Hirata-san liaised with Nakamura-san of Mirapro. Mirapro could start assembling the frame in the first week of July.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and will be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark did a top level schedule.
  * Mark released a draft (about half-finished) of [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| JGW-E1504235 - BS Installation Procedure]].
  * Mark updated [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] with a better arrangement for the IM and BF pico motor cables, as well as various other minor fixes.
  * Mark organized a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - SOLVED
  * Installation stuff
   * Crane scale - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 10/29 ====
 * SRM
  * Enzo realized that he could cover the next round of needed cables with more cable soldering and did another batch. Because Yamamoto-san's lab was running low on isopropanol, Hirata-san washed them with ethanol at Mozumi.
  * Enzo worked out the optimum output resistance for the LPCDs to substitute for HPCDs with the horizontal IM OSEMs. The value was quite close to that already chosen for modified LPCDs by the cryogenic group, so we're going to standardize. The modified LPCDs will have to be operated with the internal watchdog disabled for now because it was hard-wired to 2 mA.
  * Fabian finished adding the TM OSEM cables out to the rack and tested them.
  * We ran DC power and network to the second SRM stepper driver. We still need to get one more DC power cable to replace one we borrowed from SR3. We added the remaining steppers to the Python driver and MEDM screen.
  * We reconfigured the top of the assembly frame in preparation for the PI (removing crossbars and moving jacks down).
  * Hirata-san put the magnets on the SF damper and we hooked it to the PI, craned the PI into the assembly frame and joined it to the security structure.
  * We installed the F0-SF rod and flying saucer and suspended the SF/... section. We had plenty of spare load capacity, so we changed the CuBe spring to a weaker one and put 2.3 kg of ballast on the SF cap. This leaves 1.2 kg reserve for cables and an F0 yaw stepper mechanism.
  * We reduced the trim mass on the BF to compensate for the mass of the TM OSEM cables.
  * We measured all the bounce frequencies.
  * Hirata-san put magnets on the LBB damper magnet ring, put the pieces into the tank and assembled them into a sandwich ready for craning.
 * SR2
  * Hirata-san unclamped the LBB damper rings and suspended the LBB. It still needs ballast mass and is currently sitting high, with the blades at their upper stops.

 
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 11/4 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence
  * Add magnets to SF damper.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.

==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.

==== Plan for week of 11/18 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Crane into tank.

==== Vacation Info ====
 * Hirata-san at Mitaka, Mon 11/19.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/29

  • SRM
    • Enzo realized that he could cover the next round of needed cables with more cable soldering and did another batch. Because Yamamoto-san's lab was running low on isopropanol, Hirata-san washed them with ethanol at Mozumi.
    • Enzo worked out the optimum output resistance for the LPCDs to substitute for HPCDs with the horizontal IM OSEMs. The value was quite close to that already chosen for modified LPCDs by the cryogenic group, so we're going to standardize. The modified LPCDs will have to be operated with the internal watchdog disabled for now because it was hard-wired to 2 mA.
    • Fabian finished adding the TM OSEM cables out to the rack and tested them.
    • We ran DC power and network to the second SRM stepper driver. We still need to get one more DC power cable to replace one we borrowed from SR3. We added the remaining steppers to the Python driver and MEDM screen.
    • We reconfigured the top of the assembly frame in preparation for the PI (removing crossbars and moving jacks down).
    • Hirata-san put the magnets on the SF damper and we hooked it to the PI, craned the PI into the assembly frame and joined it to the security structure.
    • We installed the F0-SF rod and flying saucer and suspended the SF/... section. We had plenty of spare load capacity, so we changed the CuBe spring to a weaker one and put 2.3 kg of ballast on the SF cap. This leaves 1.2 kg reserve for cables and an F0 yaw stepper mechanism.

    • We reduced the trim mass on the BF to compensate for the mass of the TM OSEM cables.
    • We measured all the bounce frequencies.
    • Hirata-san put magnets on the LBB damper magnet ring, put the pieces into the tank and assembled them into a sandwich ready for craning.
  • SR2
    • Hirata-san unclamped the LBB damper rings and suspended the LBB. It still needs ballast mass and is currently sitting high, with the blades at their upper stops.

To-Do Lists, Schedule

Plan for week of 11/4

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Main sequence
    • Add magnets to SF damper.
    • Install #353 poles
    • Move NB-03 jacks down.
    • Crane PI into AF.
    • Install F0-SF rod (#331) and flying saucer.
    • Route SF/... cables up to underside of F0.
    • Do vertical height budget.
    • Adjust SF trim mass for balance and keystone height.
    • Cable/test IP LVDTs.
    • Cable/test IP FRs.
  • LBB
    • Move KOACH filters
    • Put LBB damper rings in tank.
    • Set tank jacks to nominal height.

Plan for week of 11/11

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.

Plan for week of 11/18

  • Friday 11/23 is Labor Thanksgiving Day.
  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.
  • Crane into tank.