Differences between revisions 29 and 399 (spanning 370 versions)
Revision 29 as of 2016-06-17 11:17:47
Size: 3027
Editor: MarkBarton
Comment:
Revision 399 as of 2019-03-08 13:41:52
Size: 1879
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
Line 5: Line 4:
 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He is trying the cup that had been made for the PR2 on the actual PR2. It works to confine the acetone, and we will see shortly how much soaking is required to get a prism off. We will then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Hirata-san worked on the crane height problem with Saito-sensei. They concluded that craning in the suspension is possible but will require not just the vacuum tank lid but the ≈30 cm section of tank below it to be removed.
  * Hirata-san liaised with Nakamura-san of Mirapro. Mirapro could start assembling the frame in the first week of July.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and will be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark did a top level schedule.
  * Mark released a draft (about half-finished) of [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| JGW-E1504235 - BS Installation Procedure]].
  * Mark updated [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] with a better arrangement for the IM and BF pico motor cables, as well as various other minor fixes.
  * Mark organized a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - SOLVED
  * Installation stuff
   * Crane scale - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for the week of 3/4 ====
 * On Monday, Mark helped Aso-san with PR3, and Monday, Tuesday and Wednesday, Fabian helped Fujii-kun with PRM.
 * Mark and Terrence attempted to offload some BS IM/IRM yaw adjustments that had been done by Enomoto-san last Friday. They rezeroed the OL and then opened the tank lid and did a compensating adjustment to the F0 yaw stepper, then undid the IM/IRM yaw with the pico. However this did not have the desired effect, probably because the buoyancy correction had not been cancelled when Enomoto-san was working and the BF keystone was very high, with the IM-V OSEMs way too far in and possibly touching. We did our best to back out all the adjustments but the roll TFs were still messy and there were signs that the IM was not free in yaw (the IM/IRM Y varied oppositely to IP Y, indicating that the IMR was free and the IM wasn't). We ended up deciding to have Mirapro remove the ducts on the ±X sides of the tank so we could go in and inspect.
 * Terrence tuned the SR3 LEN OL to be free of yaw cross-coupling.
 * Terrence and Enzo did a full set of filters and a Guardian for SR2 and SR3.
 * Terrence did health checks on SR2 and SR3.
 * Enzo measured mode Qs on SR2.

==== Plan for week of 3/11 ====
 * Mark at Kamioka full week.
 * Enzo at Kamioka Mon, Tue, then JPS.
 * Hirata-san at Kamioka from Monday lunchtime through Friday.
 * Fix BS.
 * Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
 * Install/test hardware watchdogs.
 * Continue monitoring SRM yaw drift.
 * More mode Q measurements.
 * Work on Type B paper.


==== Vacation/Travel Info ====
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/4

  • On Monday, Mark helped Aso-san with PR3, and Monday, Tuesday and Wednesday, Fabian helped Fujii-kun with PRM.
  • Mark and Terrence attempted to offload some BS IM/IRM yaw adjustments that had been done by Enomoto-san last Friday. They rezeroed the OL and then opened the tank lid and did a compensating adjustment to the F0 yaw stepper, then undid the IM/IRM yaw with the pico. However this did not have the desired effect, probably because the buoyancy correction had not been cancelled when Enomoto-san was working and the BF keystone was very high, with the IM-V OSEMs way too far in and possibly touching. We did our best to back out all the adjustments but the roll TFs were still messy and there were signs that the IM was not free in yaw (the IM/IRM Y varied oppositely to IP Y, indicating that the IMR was free and the IM wasn't). We ended up deciding to have Mirapro remove the ducts on the ±X sides of the tank so we could go in and inspect.
  • Terrence tuned the SR3 LEN OL to be free of yaw cross-coupling.
  • Terrence and Enzo did a full set of filters and a Guardian for SR2 and SR3.
  • Terrence did health checks on SR2 and SR3.
  • Enzo measured mode Qs on SR2.

Plan for week of 3/11

  • Mark at Kamioka full week.
  • Enzo at Kamioka Mon, Tue, then JPS.
  • Hirata-san at Kamioka from Monday lunchtime through Friday.
  • Fix BS.
  • Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
  • Install/test hardware watchdogs.
  • Continue monitoring SRM yaw drift.
  • More mode Q measurements.
  • Work on Type B paper.

Vacation/Travel Info

  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)