Differences between revisions 29 and 409 (spanning 380 versions)
Revision 29 as of 2016-06-17 11:17:47
Size: 3027
Editor: MarkBarton
Comment:
Revision 409 as of 2019-04-05 13:30:01
Size: 2036
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
Line 5: Line 4:
 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He is trying the cup that had been made for the PR2 on the actual PR2. It works to confine the acetone, and we will see shortly how much soaking is required to get a prism off. We will then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Hirata-san worked on the crane height problem with Saito-sensei. They concluded that craning in the suspension is possible but will require not just the vacuum tank lid but the ≈30 cm section of tank below it to be removed.
  * Hirata-san liaised with Nakamura-san of Mirapro. Mirapro could start assembling the frame in the first week of July.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and will be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark did a top level schedule.
  * Mark released a draft (about half-finished) of [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| JGW-E1504235 - BS Installation Procedure]].
  * Mark updated [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] with a better arrangement for the IM and BF pico motor cables, as well as various other minor fixes.
  * Mark organized a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - SOLVED
  * Installation stuff
   * Crane scale - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for the week of 4/1 ====
 * Support of Type Bp
  * Hirata-san procured the jigs for PRs and Takahashi-san tested one at TAMA.
  * Hirata-san cleaned up the flags for PR2 and Mark did the one for PRM.
  * Fabian helped Fujii-kun and Takashashi-san to reglue the flags.
 * Mark did a lot of maintenance on the MEDM screens:
  * Made the name of the suspension more obvious (no yellow text!).
  * Added rack temperature indicators.
  * Fixed the labels in the ADC screen (to reflect the LEN OL moving from ADC#0 to #1).
  * Fixed broken links.
  * Committed files to the SVN.
 * Mark did maintenance on the Guardian to make it give more helpful messages in the TRIGGER state. Formerly it only checked the user model watchdog and the coil driver watchdog, not the DACKILL, and gave the same generic notification for both. Now it checks all three and tells the user which need attention.
 * Mark tidied up the cables in the SR2 rack and returned a large pile of no-longer-used cables to the tent.
 * Mark started a !HealthCheck page on the Operation Manual wiki.
Fabian and Mark
==== Plan for week of 4/8 ====
 * Mark, Fabian at Kamioka Mon-Fri.
 * Help with Type Bp.
 * Health checks on Type B.
 * Monitor pumpdown.
 * Work on Type B paper.
 * Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
 * Tidy up.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.

==== Plan for week of 4/15 ====
 * Mark at Mitaka 4/15, Kamioka 4/16-18, f2f 4/19.
 * Fabian at Kamioka 4/15-18, f2f 4/19.

==== Vacation/Travel Info ====
 * Mark at Mitaka 4/15.
 * f2f 4/19 (Friday), 4/20, 4/21.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's vacation from about 5/22 to 6/11.
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 4/1

  • Support of Type Bp
    • Hirata-san procured the jigs for PRs and Takahashi-san tested one at TAMA.
    • Hirata-san cleaned up the flags for PR2 and Mark did the one for PRM.
    • Fabian helped Fujii-kun and Takashashi-san to reglue the flags.
  • Mark did a lot of maintenance on the MEDM screens:
    • Made the name of the suspension more obvious (no yellow text!).
    • Added rack temperature indicators.
    • Fixed the labels in the ADC screen (to reflect the LEN OL moving from ADC#0 to #1).
    • Fixed broken links.
    • Committed files to the SVN.
  • Mark did maintenance on the Guardian to make it give more helpful messages in the TRIGGER state. Formerly it only checked the user model watchdog and the coil driver watchdog, not the DACKILL, and gave the same generic notification for both. Now it checks all three and tells the user which need attention.
  • Mark tidied up the cables in the SR2 rack and returned a large pile of no-longer-used cables to the tent.
  • Mark started a HealthCheck page on the Operation Manual wiki.

Fabian and Mark

Plan for week of 4/8

  • Mark, Fabian at Kamioka Mon-Fri.
  • Help with Type Bp.
  • Health checks on Type B.
  • Monitor pumpdown.
  • Work on Type B paper.
  • Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
  • Tidy up.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.

Plan for week of 4/15

  • Mark at Mitaka 4/15, Kamioka 4/16-18, f2f 4/19.
  • Fabian at Kamioka 4/15-18, f2f 4/19.

Vacation/Travel Info

  • Mark at Mitaka 4/15.
  • f2f 4/19 (Friday), 4/20, 4/21.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's vacation from about 5/22 to 6/11.
  • Mark's final day 6/28.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)