==== Report for week of 5/28 ==== * Enzo tested the LVDT driver repaired by Tanaka-san - it was fine. * Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data. * Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF. * Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings). * After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole. * Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2). * Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3). * Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades. * We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles. * We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap. * Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank. * Enzo installed damping filters for the IM OSEMs. |
==== Report for week of 9/10 ==== * We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank. * We checked all the motors: * IM picos, BF picos. * BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod). * IP Steppers (Horizontal fishing rods). * We use the Steppers to set to nominal height the BF and SF, but for the SF we culd not move it too much and it is still too low. * We set up the temporary oplev for SR2. * We checked the pitch of the optics. The current pitch is: * We tried to check the TM actuators but there is a problem with the MEDM screens that we need to fix next week. * We measured TFs of the GAS filters and the 6 DoF of the IM. It seems to be healthy. * We set the F0 stepper to middle position. * ... |
Line 20: | Line 20: |
==== Plan for week of 6/4 ==== * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.) * -- * Cable and test BF cap picos. * Crane in security structure disk at SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Characterize final F0 blades. |
=== Type B (Mark) === ==== Report for week of 9/3 ==== * We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected. * We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables. * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains. * We reset the IP FRs to midrange. * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure. * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs. * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage. |
Line 33: | Line 30: |
==== Plan for week of 6/11 ==== * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.) * -- * Any unfinished SR3 SF/... stuff. * Add budgeted ballast mass to SF and weigh SF/... section. * Cable, test SF LVDT and FR. * Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. |
==== Plan for week of 9/10 ==== * Monday 9/10 is scheduled power outage. * Mark in US (job interview). * Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri. * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation. ===== Etc ===== * Recover from power outage. ===== SR2 ===== * Calibrate F0 LVDTs. * Calibrate IP LVDTs. * Cable geophones and any other remaining PI items. * Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables). * Do basic go/no-go test of electronic items. * Check SF keystone height and offload with FR as necessary. * Adjust ballast/trim mass of SF, with reserve for yaw stepper. * Set SF damper magnet ring height. * Check/tweak optic pitch. * TFs. ==== Plan for week of 9/17 ==== * Monday 9/17 is holiday (Respect for the Aged Day). * Enzo on vacation. * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. ===== SR2 ===== * Crane SR2 into tank. * Move SR2 in-air cables. * Remove First Contact. * Unlock and realign suspension. ===== SRM ===== * Set pitch of SRM and RM, tighten clamps, remove winch system. * Weigh IM/... section. * Build up SS to BF level. * Add BF. ==== Plan for week of 9/24 ==== * Monday 9/24 is holiday (Autumn Equinox). * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. * Suspend IM and tweak height/balance. ===== SRM ===== * Cable/test BF. * Install IRM. * Install/cable/test IM OSEMs. |
Line 46: | Line 75: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] | * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] |
Line 49: | Line 78: |
* Mark: 9/10-14 (job interview in US). * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 9/10
- We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
- We checked all the motors:
- IM picos, BF picos.
- BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
- IP Steppers (Horizontal fishing rods).
- We use the Steppers to set to nominal height the BF and SF, but for the SF we culd not move it too much and it is still too low.
- We set up the temporary oplev for SR2.
- We checked the pitch of the optics. The current pitch is:
- We tried to check the TM actuators but there is a problem with the MEDM screens that we need to fix next week.
- We measured TFs of the GAS filters and the 6 DoF of the IM. It seems to be healthy.
- We set the F0 stepper to middle position.
- ...
Type B (Mark)
Report for week of 9/3
- We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
- We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
- We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
- We reset the IP FRs to midrange.
- We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
- We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
- We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.
Plan for week of 9/10
- Monday 9/10 is scheduled power outage.
- Mark in US (job interview).
- Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
- Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.
Etc
- Recover from power outage.
SR2
- Calibrate F0 LVDTs.
- Calibrate IP LVDTs.
- Cable geophones and any other remaining PI items.
- Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
- Do basic go/no-go test of electronic items.
- Check SF keystone height and offload with FR as necessary.
- Adjust ballast/trim mass of SF, with reserve for yaw stepper.
- Set SF damper magnet ring height.
- Check/tweak optic pitch.
- TFs.
Plan for week of 9/17
- Monday 9/17 is holiday (Respect for the Aged Day).
- Enzo on vacation.
- Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
SR2
- Crane SR2 into tank.
- Move SR2 in-air cables.
- Remove First Contact.
- Unlock and realign suspension.
SRM
- Set pitch of SRM and RM, tighten clamps, remove winch system.
- Weigh IM/... section.
- Build up SS to BF level.
- Add BF.
Plan for week of 9/24
- Monday 9/24 is holiday (Autumn Equinox).
- Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
- Suspend IM and tweak height/balance.
SRM
- Cable/test BF.
- Install IRM.
- Install/cable/test IM OSEMs.
To-Do Lists, Schedule
Vacation Info
- Mark: 9/10-14 (job interview in US).
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.