Differences between revisions 290 and 325 (spanning 35 versions)
Revision 290 as of 2018-06-01 11:52:28
Size: 2751
Editor: MarkBarton
Comment:
Revision 325 as of 2018-09-13 15:39:54
Size: 3728
Editor: EnzoTapia
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for week of 5/28 ====
 * Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
 * Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
 * Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
 * Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
 * After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
 * Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
 * Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
 * Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
 * We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
 * We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
 * Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank.
 * Enzo installed damping filters for the IM OSEMs.
==== Report for week of 9/10 ====
 * We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
 * We checked all the motors:
       * IM picos, BF picos.
       * BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
       * IP Steppers (Horizontal fishing rods).
 * We use the Steppers to set to nominal height the BF and SF, but for the SF we culd not move it too much and it is still too low.
 * We set up the temporary oplev for SR2.
 * We checked the pitch of the optics. The current pitch is:
 * We tried to check the TM actuators but there is a problem with the MEDM screens that we need to fix next week.
 * We measured TFs of the GAS filters and the 6 DoF of the IM. It seems to be healthy.
 * We set the F0 stepper to middle position.
 * ...
Line 20: Line 20:
==== Plan for week of 6/4 ====
 * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
 * --
 * Cable and test BF cap picos.
 * Crane in security structure disk at SF level.
 * Crane in SF and remove cap.
 * Hook BF and adjust total ballast.
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Adjust BF trim mass.
 * Readjust payload.
 * Take TFs.
 * Characterize final F0 blades.
=== Type B (Mark) ===
==== Report for week of 9/3 ====
 * We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
 * We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
 * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
 * We reset the IP FRs to midrange.
 * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
 * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
 * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.
Line 33: Line 30:
==== Plan for week of 6/11 ====
 * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
 * --
 * Any unfinished SR3 SF/... stuff.
 * Add budgeted ballast mass to SF and weigh SF/... section.
 * Cable, test SF LVDT and FR.
 * Rebuild F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
==== Plan for week of 9/10 ====
 * Monday 9/10 is scheduled power outage.
 * Mark in US (job interview).
 * Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
 * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.
===== Etc =====
 * Recover from power outage.
===== SR2 =====
 * Calibrate F0 LVDTs.
 * Calibrate IP LVDTs.
 * Cable geophones and any other remaining PI items.
 * Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
 * Do basic go/no-go test of electronic items.
 * Check SF keystone height and offload with FR as necessary.
 * Adjust ballast/trim mass of SF, with reserve for yaw stepper.
 * Set SF damper magnet ring height.
 * Check/tweak optic pitch.
 * TFs.
==== Plan for week of 9/17 ====
 * Monday 9/17 is holiday (Respect for the Aged Day).
 * Enzo on vacation.
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
===== SR2 =====
 * Crane SR2 into tank.
 * Move SR2 in-air cables.
 * Remove First Contact.
 * Unlock and realign suspension.
===== SRM =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.

==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
 * Suspend IM and tweak height/balance.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.
Line 46: Line 75:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 49: Line 78:
 * Mark: 9/10-14 (job interview in US).
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 9/10

  • We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
  • We checked all the motors:
    • IM picos, BF picos.
    • BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
    • IP Steppers (Horizontal fishing rods).
  • We use the Steppers to set to nominal height the BF and SF, but for the SF we culd not move it too much and it is still too low.
  • We set up the temporary oplev for SR2.
  • We checked the pitch of the optics. The current pitch is:
  • We tried to check the TM actuators but there is a problem with the MEDM screens that we need to fix next week.
  • We measured TFs of the GAS filters and the 6 DoF of the IM. It seems to be healthy.
  • We set the F0 stepper to middle position.
  • ...

Type B (Mark)

Report for week of 9/3

  • We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
  • We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
  • We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
  • We reset the IP FRs to midrange.
  • We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
  • We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
  • We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

Plan for week of 9/10

  • Monday 9/10 is scheduled power outage.
  • Mark in US (job interview).
  • Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
  • Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.

Etc
  • Recover from power outage.

SR2
  • Calibrate F0 LVDTs.
  • Calibrate IP LVDTs.
  • Cable geophones and any other remaining PI items.
  • Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
  • Do basic go/no-go test of electronic items.
  • Check SF keystone height and offload with FR as necessary.
  • Adjust ballast/trim mass of SF, with reserve for yaw stepper.
  • Set SF damper magnet ring height.
  • Check/tweak optic pitch.
  • TFs.

Plan for week of 9/17

  • Monday 9/17 is holiday (Respect for the Aged Day).
  • Enzo on vacation.
  • Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.

SR2
  • Crane SR2 into tank.
  • Move SR2 in-air cables.
  • Remove First Contact.
  • Unlock and realign suspension.

SRM
  • Set pitch of SRM and RM, tighten clamps, remove winch system.
  • Weigh IM/... section.
  • Build up SS to BF level.
  • Add BF.

Plan for week of 9/24

  • Monday 9/24 is holiday (Autumn Equinox).
  • Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
  • Suspend IM and tweak height/balance.

SRM
  • Cable/test BF.
  • Install IRM.
  • Install/cable/test IM OSEMs.

To-Do Lists, Schedule

Vacation Info

  • Mark: 9/10-14 (job interview in US).
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)