Differences between revisions 290 and 334 (spanning 44 versions)
Revision 290 as of 2018-06-01 11:52:28
Size: 2751
Editor: MarkBarton
Comment:
Revision 334 as of 2018-10-12 13:28:07
Size: 2761
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for week of 5/28 ====
 * Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
 * Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
 * Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
 * Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
 * After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
 * Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
 * Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
 * Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
 * We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
 * We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
 * Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank.
 * Enzo installed damping filters for the IM OSEMs.
==== Report for week of 10/8 ====
 * This was Panwei's last week (for now at least) - thanks for all the help!
 * Thanks also to Terrence for visiting again for the week.
===== SR3 =====
 * Terrence and Mark finished setting up the LEN half of the OL (Simon had roughly placed the components). They ran a new cable for LEN in the cable tray and relaid the cable for TILT to get it off the floor.
 * Terrence worked on diagonalizing the LEN OL. A report is forthcoming.
===== SRM =====
 * Mark installed a pair of power supplies in the SRM and copied settings across to the SRM real-time model.
 * Fabian did lots of rack cabling, including installing and connecting BIO cards.
 * Mark and Hirata-san checked and adjusted the pitch of the BF (with a bubble level) and the IM/... section (with the OL).
 * Mark and Panwei installed the sides of the IRM and the IM OSEMs.
 * Hirata-san hung the dummy load from the F0 and started compressing the blade. There was a significant lateral offset (≈2-3 mm towards the blade at 5:30) at first but Takahashi-san advised that it would probably improve with compression, and it did.
 * Mark and Hirata-san cleared off most of two optical tables and a set of shelves in the OMMT area that Type B had been using but were now required by Somiya-san and Ohishi-san. We still need to remove the geophone and OSEM testing setups.
Line 20: Line 20:
==== Plan for week of 6/4 ====
 * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
 * --
 * Cable and test BF cap picos.
 * Crane in security structure disk at SF level.
 * Crane in SF and remove cap.
 * Hook BF and adjust total ballast.
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Adjust BF trim mass.
 * Readjust payload.
 * Take TFs.
 * Characterize final F0 blades.
===== SR2 =====
 * Mark, Enzo and Hirata-san all inspected the lower section of the SR2 to see if there were any interference points that might explain some unexpected peaks in the TFs (especially the RM pitch made appearing in longitudinal) that weren't present before installation. There were no stops touching, but some TM OSEM cables were rubbing against each other, which we fixed. The problem turned out to be swapped cables in the coil actuation.
 * We removed the tank lid, and Enzo and Panwei inspected the cabling that had been done during Enzo's vacation and installed some new cables that had arrived. They also unlocked the IP.
Line 33: Line 24:
==== Plan for week of 6/11 ====
 * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
 * --
 * Any unfinished SR3 SF/... stuff.
 * Add budgeted ballast mass to SF and weigh SF/... section.
 * Cable, test SF LVDT and FR.
 * Rebuild F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
==== Plan for week of 10/15 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SR2 =====
 * Continue shakedown of PI section.
===== SRM =====
 * Align IRM with IM.
 * Suspend/weigh/balance the BF/... section.
 * Build up the AF and SS to the SF level.
 * Install the SF.
Line 46: Line 37:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 48: Line 39:
==== Vacation Info ==== ==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/8

  • This was Panwei's last week (for now at least) - thanks for all the help!
  • Thanks also to Terrence for visiting again for the week.

SR3
  • Terrence and Mark finished setting up the LEN half of the OL (Simon had roughly placed the components). They ran a new cable for LEN in the cable tray and relaid the cable for TILT to get it off the floor.
  • Terrence worked on diagonalizing the LEN OL. A report is forthcoming.

SRM
  • Mark installed a pair of power supplies in the SRM and copied settings across to the SRM real-time model.
  • Fabian did lots of rack cabling, including installing and connecting BIO cards.
  • Mark and Hirata-san checked and adjusted the pitch of the BF (with a bubble level) and the IM/... section (with the OL).
  • Mark and Panwei installed the sides of the IRM and the IM OSEMs.
  • Hirata-san hung the dummy load from the F0 and started compressing the blade. There was a significant lateral offset (≈2-3 mm towards the blade at 5:30) at first but Takahashi-san advised that it would probably improve with compression, and it did.
  • Mark and Hirata-san cleared off most of two optical tables and a set of shelves in the OMMT area that Type B had been using but were now required by Somiya-san and Ohishi-san. We still need to remove the geophone and OSEM testing setups.

SR2
  • Mark, Enzo and Hirata-san all inspected the lower section of the SR2 to see if there were any interference points that might explain some unexpected peaks in the TFs (especially the RM pitch made appearing in longitudinal) that weren't present before installation. There were no stops touching, but some TM OSEM cables were rubbing against each other, which we fixed. The problem turned out to be swapped cables in the coil actuation.
  • We removed the tank lid, and Enzo and Panwei inspected the cabling that had been done during Enzo's vacation and installed some new cables that had arrived. They also unlocked the IP.

Plan for week of 10/15

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SR2
  • Continue shakedown of PI section.

SRM
  • Align IRM with IM.
  • Suspend/weigh/balance the BF/... section.
  • Build up the AF and SS to the SF level.
  • Install the SF.

To-Do Lists, Schedule

Vacation/Visitor Info

  • Terrence: 10/29-11/2 at Kamioka.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)