1783
Comment:
|
2556
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 6/11 ==== * Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem. * Enzo replaced LPCDs with HPCDs in the SR3. * Hirata-san installed the cable clamps and Cu segments on the SF cap. * Hirata-san and Kozu-kun continued tuning the filter in PI #3. Unfortunately it seems to be rather weaker than expected, and we have not found a compression setting that gives a good frequency. We may have to use tricks like reducing the number of Cu segments on the SF (or using Al ones) to save weight. * Mark, Enzo and Terrence suspended the BF/... section from the SF, and got it aligned for TFs. ==== Plan for week of 6/18 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri. * -- * Receive second and third sets of LBB damper rings. * Take TFs. * Cable, test SF LVDT and FR. * Add calculated ballast to SF. * Finish tuning F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Move F0 #1 to "factory" area (in front of SRM) and start rebuild. * Install PI. * Suspend SF/... section. * Lots of cabling. ==== Plan for week of 6/25 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri. |
==== Report for week of 10/29 ==== * SRM * Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half. * Fabian and Hirata-san finished the in-vacuum cabling. * Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling. * We're now ready for final tests of the SF/... items and initial tests of the PI items. * Enzo and Fujii-kun built three geophones for SRM. * Mark worked on the height budget. * SR2 * Enzo experimented with [[http://www2.mpq.mpg.de/~ros/geo600_docu/soft/liso/manual.pdf|LISO]] (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.) |
Line 36: | Line 22: |
==== Vacation Info ==== * Enzo: 9/14 JPS, 9/15 through 10/18 vacation in Chile * Terrence: 8/24-26 f2f, then returns to Hong Kong. |
==== Plan for week of 11/11 ==== * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri. ===== SRM ===== * Main sequence ==== Plan for week of 11/19 ==== * Friday 11/23 is Labor Thanksgiving Day. * Mark, Enzo and Fabian at Kamioka Mon-Thu. * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting). ===== SRM ===== * Go/no-go test of all electronics items, especially SF/... section. * Finish vertical height check and adjust SF trim mass as required. * Unlock IP and center roughly. * Check/adjust alignment of SS. * Calibrate IP LVDTs. * Add arc weights and geophones. * Improve centering/tuning of IP and SS alignment. * Disconnect cables at feedthroughs, lock suspension. * Crane into tank. ===== SR2 ===== * Assist MIF team with pico cables and LBB breadboard ballast. * Install SR2 OL pillar and shelf (with AOL supervision)? ==== Plan for week of 11/26 ==== * Move SRM in-air cables over to tank. * Remove First Contact. * Unlock and align SRM. * Hook and roughly ballast LBB. ==== Plan for week of 12/3 ==== * f2f Meeting at NAOJ - no Kamioka work. ==== Vacation/Event Info ==== * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 10/29
- SRM
- Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
- Fabian and Hirata-san finished the in-vacuum cabling.
- Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
- We're now ready for final tests of the SF/... items and initial tests of the PI items.
- Enzo and Fujii-kun built three geophones for SRM.
- Mark worked on the height budget.
- SR2
Enzo experimented with LISO (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)
To-Do Lists, Schedule
Plan for week of 11/11
- Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
SRM
- Main sequence
Plan for week of 11/19
- Friday 11/23 is Labor Thanksgiving Day.
- Mark, Enzo and Fabian at Kamioka Mon-Thu.
- Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
SRM
- Go/no-go test of all electronics items, especially SF/... section.
- Finish vertical height check and adjust SF trim mass as required.
- Unlock IP and center roughly.
- Check/adjust alignment of SS.
- Calibrate IP LVDTs.
- Add arc weights and geophones.
- Improve centering/tuning of IP and SS alignment.
- Disconnect cables at feedthroughs, lock suspension.
- Crane into tank.
SR2
- Assist MIF team with pico cables and LBB breadboard ballast.
- Install SR2 OL pillar and shelf (with AOL supervision)?
Plan for week of 11/26
- Move SRM in-air cables over to tank.
- Remove First Contact.
- Unlock and align SRM.
- Hook and roughly ballast LBB.
Plan for week of 12/3
- f2f Meeting at NAOJ - no Kamioka work.
Vacation/Event Info
- Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).