* Electronics * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| D1503600-v9 BS Suspension Cabling]] * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111| E1605111-v1 BS Suspension Electronic Items List]] * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901| D1503901-v2 In-Vacuum Cable Detail]] * Need to hand-make geophone cables * Need to make longer versions of BF-PI and SF-PI cables (3.7 m and 2.5 m) * Need to check OSEM cables have same flip for flexicircuit as for PRx. * Asked Miyakawa-san for status on AEL items, especially stepper driver. * Compensation masses for RM/IRM ordered, expected 4/29 * Hirata-san drew up flags |
* Type B * Hirata-san finished the design of the trolley system (including adapter plates for the mirror box). * Mirapro reported that rails for the trolley system had a long lead time, so we decided to order them separately. * IM and BS flags were ordered. * Tatsumi-san ordered the prism gluing jig parts for the mirror box. * Hirata-san measured another SF. * Mark worked on the assembly procedure. * Fabian worked on the Mathematica/Matlab model of the BS. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B
- Hirata-san finished the design of the trolley system (including adapter plates for the mirror box).
- Mirapro reported that rails for the trolley system had a long lead time, so we decided to order them separately.
- IM and BS flags were ordered.
- Tatsumi-san ordered the prism gluing jig parts for the mirror box.
- Hirata-san measured another SF.
- Mark worked on the assembly procedure.
- Fabian worked on the Mathematica/Matlab model of the BS.