* Electronics * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| D1503600-v9 BS Suspension Cabling]] * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111| E1605111-v1 BS Suspension Electronic Items List]] * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901| D1503901-v2 In-Vacuum Cable Detail]] * Need to hand-make geophone cables * Need to make longer versions of BF-PI and SF-PI cables (3.7 m and 2.5 m) * Need to check OSEM cables have same flip for flexicircuit as for PRx. * Asked Miyakawa-san for status on AEL items, especially stepper driver. * Compensation masses for RM/IRM ordered, expected 4/29 * Hirata-san drew up flags |
* Type B Past Week Summary * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]] * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece. * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them. * Some arrows were cleaned from the mirrors for the dummy optic. * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found. * Hirata-san measured another filter. * Hirata-san washed a large batch of parts. * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]] * Mark worked on list of items for purchase in FY2016. * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]]) |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
Fabian worked on IM and dummy BS assembly: photos1, photos2
- A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece.
- Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them.
- Some arrows were cleaned from the mirrors for the dummy optic.
- Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found.
- Hirata-san measured another filter.
- Hirata-san washed a large batch of parts.
Mark worked on solutions to allow a larger mirror on dummy BS
- Mark worked on list of items for purchase in FY2016.
Mark worked more on E1504235 BS Assembly Procedure (Draft on OneDrive)