Line 5: Line 5:
 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He is trying the cup that had been made for the PR2 on the dummy BS. Despite not having the ideal radius of curvature, it works to confine the acetone, and we will see shortly how much soaking is required to get a prism off.
  * Akutsu-san provided stainless steel mirror panels for the dummy BS made by ATC.
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Hirata-san worked on the crane height problem with Saito-sensei. They concluded that craning in the suspension is possible but will require not just the vacuum tank lid but the ≈30 cm section of tank below it to be removed.
  * Hirata-san liaised with Nakamura-san of Mirapro. Mirapro could start assembling the frame in the first week of July.
  * Hirata-san cleaned more parts and measured another filter.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and will be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark did a top level schedule. The BS can probably be finished roughly when promised to Ando-san earlier, but the SRs will probably take rather longer because of all the prep work that still needs to be done. It may save time overall to delay the start of the BS installation a few weeks and concentrate on parts for SR.
  * Mark released a draft (about half-finished) of [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| JGW-E1504235 - BS Installation Procedure]].
  * Mark updated [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] with a better arrangement for the IM and BF pico motor cables, as well as various other minor fixes.
  * Mark organized a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - SOLVED
  * Installation stuff
   * Crane scale - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 11/19 ====
 * BS
  * Fabian did some debugging on the BS and found that the calibration for the F0 LVDT was off due to an Excel error, and that the sag wasn't quite the 7 mm originally observed, but still enough to cause the suspension to touch down. Enzo tried applying LVDT actuation at the GAS filters and got it to lift off far enough to get sensible TFs, but the required BF offset was enough to put the IM OSEMs at the very edge of their usable range, so this is not a good long-term solution. We can probably raise the F0 keystone during the vent by removing mass and/or installing an auxiliary spring, which will then allow us to return the BF keystone to nominal height.
  * While working on the BS, Enzo noticed that one of the stepper drivers was not responding. It turned out to be water damaged from the rain issues earlier in the year. Enzo and Fujii-kun opened the rest of the BS chassises on the second floor but they seem to be OK. Tanaka-san had made a third driver chassis as a spare, so we reserved that and will install it in the week of 12/10.
 * SRM
  * The SRM-W optic arrived and we installed it in place of the SRM-M in the metal mass, taking care to use 1.4 mm shims as recommended by Hirose-san. The weight of the new assembly was within 1 g of the old and did not disturb the height of the payload. There was a very small change in pitch which we corrected with the IM picos.
  * We installed the shelf for the OL receiver.
  * We added the arc weights and geophones and went through several rounds of improving the centering of the IP and then realigning the security structure back to vertical.
  * We calibrated the F0 LVDT, and checked the F0 and IP actuation signs.
  * We adjusted the SF trim masses to set the SF pitch and roll, did an inventory of the trim mass and set the damper gap.
  * We did a final alignment of the whole chain and left the suspension ready for TFs during the f2f week. There is only a few hours of work left before we can install and we hope to do that on Monday 12/10.
 * SR2
  * Enzo replaced the geophones and cables that had been borrowed for calibration and did several rounds of optimization of the IP frequency. He got as low as 46 mHz but with poor Q and so backed off a bit to 55 mHz and may back off a tiny bit more.
  * I derived updated IP matrices for the BS and SR, with more precise geometry data provided by Hirata-san, and published them as T1707205 and T1807663.
  * I created a CENTERING screen for the IP, with large panel meters for the LVDT signals and the derived L, T and Y signals.
  * Enzo confirmed that the fancy stepper control screen created by Shoda-san worked.
  * We installed a modified LPCD as IM-V for testing.
 * SR3
  * We moved HPCDs from BS and SR2 to replace the ones that had been stolen from SR3, so as to create a working suspension with an OL for Kozu-kun.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]


==== Plan for week of 12/3 ====
 * f2f Meeting at NAOJ - no Kamioka work.
==== Plan for week of 12/10 ====
 * Crane SRM into tank.
 * Install new F0 yaw mechanisms on SRs.
 * Remove First Contact from SRM, unlock and realign.
 * Move SRM in-air cables over.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 11/19

  • BS
    • Fabian did some debugging on the BS and found that the calibration for the F0 LVDT was off due to an Excel error, and that the sag wasn't quite the 7 mm originally observed, but still enough to cause the suspension to touch down. Enzo tried applying LVDT actuation at the GAS filters and got it to lift off far enough to get sensible TFs, but the required BF offset was enough to put the IM OSEMs at the very edge of their usable range, so this is not a good long-term solution. We can probably raise the F0 keystone during the vent by removing mass and/or installing an auxiliary spring, which will then allow us to return the BF keystone to nominal height.
    • While working on the BS, Enzo noticed that one of the stepper drivers was not responding. It turned out to be water damaged from the rain issues earlier in the year. Enzo and Fujii-kun opened the rest of the BS chassises on the second floor but they seem to be OK. Tanaka-san had made a third driver chassis as a spare, so we reserved that and will install it in the week of 12/10.
  • SRM
    • The SRM-W optic arrived and we installed it in place of the SRM-M in the metal mass, taking care to use 1.4 mm shims as recommended by Hirose-san. The weight of the new assembly was within 1 g of the old and did not disturb the height of the payload. There was a very small change in pitch which we corrected with the IM picos.
    • We installed the shelf for the OL receiver.
    • We added the arc weights and geophones and went through several rounds of improving the centering of the IP and then realigning the security structure back to vertical.
    • We calibrated the F0 LVDT, and checked the F0 and IP actuation signs.
    • We adjusted the SF trim masses to set the SF pitch and roll, did an inventory of the trim mass and set the damper gap.
    • We did a final alignment of the whole chain and left the suspension ready for TFs during the f2f week. There is only a few hours of work left before we can install and we hope to do that on Monday 12/10.
  • SR2
    • Enzo replaced the geophones and cables that had been borrowed for calibration and did several rounds of optimization of the IP frequency. He got as low as 46 mHz but with poor Q and so backed off a bit to 55 mHz and may back off a tiny bit more.
    • I derived updated IP matrices for the BS and SR, with more precise geometry data provided by Hirata-san, and published them as T1707205 and T1807663.
    • I created a CENTERING screen for the IP, with large panel meters for the LVDT signals and the derived L, T and Y signals.
    • Enzo confirmed that the fancy stepper control screen created by Shoda-san worked.
    • We installed a modified LPCD as IM-V for testing.
  • SR3
    • We moved HPCDs from BS and SR2 to replace the ones that had been stolen from SR3, so as to create a working suspension with an OL for Kozu-kun.

To-Do Lists, Schedule

Plan for week of 12/3

  • f2f Meeting at NAOJ - no Kamioka work.

Plan for week of 12/10

  • Crane SRM into tank.
  • Install new F0 yaw mechanisms on SRs.
  • Remove First Contact from SRM, unlock and realign.
  • Move SRM in-air cables over.