Line 6: Line 6:
==== Report for week of 7/9 ====
 * We cleaned up after the heavy rain. There was no significant damage but some cardboard boxes of parts got wet and the contents needed to be moved to other containers and the boxes discarded. Water collected on the SR2 crane slot cover and had to be vacuumed away before the cover could be opened. A new section of corrugated roof was installed to minimize the problem for the future.
 * Enzo and team got all of the in-vacuum and in-air cables for the SF/... and PI properly routed and tested except (so far) for the geophones.
 * Hirata-san and team finished tuning of the F0 for SR2 and moved the PI into the SR2 cleanbooth. It turns out to be about 8 kg weaker than for SR3, whereas the SR2 chain is only 3 kg lighter, so we will have to do some combination of decompression, removing Cu segments and using a stronger CuBe spring (e.g., a Type A F0 FR blade instead of the F2 one in SR3). We closed the floor in the SRM area for safety, but we will probably reopen it as soon as next week for the SRM F0 build.
 * Hirata-san opened the SR3 tank, craned the LBB damper ring sandwich up to the top of the tank and suspended it.
 * Enzo and team corrected a lot of flipped connections on the SR3 PI LVDTs (primary<->secondary on the horizontal, primary<->actuation on the F0).
 * We added the arc weights and geophones and re-centered the IP. It seems stable and very soft, which is good.
==== Report for week of 10/29 ====
 * SRM
  * Enzo realized that he could cover the next round of needed cables with more cable soldering and did another batch. Because Yamamoto-san's lab was running low on isopropanol, Hirata-san washed them with ethanol at Mozumi.
  * Enzo worked out the optimum output resistance for the LPCDs to substitute for HPCDs with the horizontal IM OSEMs. The value was quite close to that already chosen for modified LPCDs by the cryogenic group, so we're going to standardize. The modified LPCDs will have to be operated with the internal watchdog disabled for now because it was hard-wired to 2 mA.
  * Fabian finished adding the TM OSEM cables out to the rack and tested them.
  * We ran DC power and network to the second SRM stepper driver. We still need to get one more DC power cable to replace one we borrowed from SR3. We added the remaining steppers to the Python driver and MEDM screen.
  * We reconfigured the top of the assembly frame in preparation for the PI (removing crossbars and moving jacks down).
  * Hirata-san put the magnets on the SF damper and we hooked it to the PI, craned the PI into the assembly frame and joined it to the security structure.
  * We installed the F0-SF rod and flying saucer and suspended the SF/... section. We had plenty of spare load capacity, so we changed the CuBe spring to a weaker one and put 2.3 kg of ballast on the SF cap. This leaves 1.2 kg reserve for cables and an F0 yaw stepper mechanism.
  * We reduced the trim mass on the BF to compensate for the mass of the TM OSEM cables.
  * We measured all the bounce frequencies.
  * Hirata-san put magnets on the LBB damper magnet ring, put the pieces into the tank and assembled them into a sandwich ready for craning.
 * SR2
  * Hirata-san unclamped the LBB damper rings and suspended the LBB. It still needs ballast mass and is currently sitting high, with the blades at their upper stops.
Line 14: Line 21:
==== Plan for week of 7/9 ====
==== Plan for week of 7/16 ====
 * Monday 7/16 is Sea Day.
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.
===== Main Sequence =====
 * Check/restore alignment of payload, especially optic pitch.
 * Testing, TFs.
 * Lock suspension.
 * Crane into tank.
 * Unlock suspension.
 * Rearrange cables.
 * Test.

===== F0/LBB Stuff =====
 * Install correct IP in PI #2.
 * Crane PI #2 to second floor.
 * Rebuild top filter of PI #2.
 
Line 37: Line 27:
==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Plan for week of 11/4 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence
  * Add magnets to SF damper.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.

==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.

==== Plan for week of 11/18 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Crane into tank.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/29

  • SRM
    • Enzo realized that he could cover the next round of needed cables with more cable soldering and did another batch. Because Yamamoto-san's lab was running low on isopropanol, Hirata-san washed them with ethanol at Mozumi.
    • Enzo worked out the optimum output resistance for the LPCDs to substitute for HPCDs with the horizontal IM OSEMs. The value was quite close to that already chosen for modified LPCDs by the cryogenic group, so we're going to standardize. The modified LPCDs will have to be operated with the internal watchdog disabled for now because it was hard-wired to 2 mA.
    • Fabian finished adding the TM OSEM cables out to the rack and tested them.
    • We ran DC power and network to the second SRM stepper driver. We still need to get one more DC power cable to replace one we borrowed from SR3. We added the remaining steppers to the Python driver and MEDM screen.
    • We reconfigured the top of the assembly frame in preparation for the PI (removing crossbars and moving jacks down).
    • Hirata-san put the magnets on the SF damper and we hooked it to the PI, craned the PI into the assembly frame and joined it to the security structure.
    • We installed the F0-SF rod and flying saucer and suspended the SF/... section. We had plenty of spare load capacity, so we changed the CuBe spring to a weaker one and put 2.3 kg of ballast on the SF cap. This leaves 1.2 kg reserve for cables and an F0 yaw stepper mechanism.

    • We reduced the trim mass on the BF to compensate for the mass of the TM OSEM cables.
    • We measured all the bounce frequencies.
    • Hirata-san put magnets on the LBB damper magnet ring, put the pieces into the tank and assembled them into a sandwich ready for craning.
  • SR2
    • Hirata-san unclamped the LBB damper rings and suspended the LBB. It still needs ballast mass and is currently sitting high, with the blades at their upper stops.

To-Do Lists, Schedule

Plan for week of 11/4

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Main sequence
    • Add magnets to SF damper.
    • Install #353 poles
    • Move NB-03 jacks down.
    • Crane PI into AF.
    • Install F0-SF rod (#331) and flying saucer.
    • Route SF/... cables up to underside of F0.
    • Do vertical height budget.
    • Adjust SF trim mass for balance and keystone height.
    • Cable/test IP LVDTs.
    • Cable/test IP FRs.
  • LBB
    • Move KOACH filters
    • Put LBB damper rings in tank.
    • Set tank jacks to nominal height.

Plan for week of 11/11

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.

Plan for week of 11/18

  • Friday 11/23 is Labor Thanksgiving Day.
  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.
  • Crane into tank.