==== Report for week of 7/9 ====
 * We cleaned up after the heavy rain. There was no significant damage but some cardboard boxes of parts got wet and the contents needed to be moved to other containers and the boxes discarded. Water collected on the SR2 crane slot cover and had to be vacuumed away before the cover could be opened. A new section of corrugated roof was installed to minimize the problem for the future.
 * Enzo and team got all of the in-vacuum and in-air cables for the SF/... and PI properly routed and tested except (so far) for the geophones.
 * Hirata-san and team finished tuning of the F0 for SR2 and moved the PI into the SR2 cleanbooth. It turns out to be about 8 kg weaker than for SR3, whereas the SR2 chain is only 3 kg lighter, so we will have to do some combination of decompression, removing Cu segments and using a stronger CuBe spring (e.g., a Type A F0 FR blade instead of the F2 one in SR3). We closed the floor in the SRM area for safety, but we will probably reopen it as soon as next week for the SRM F0 build.
 * Hirata-san opened the SR3 tank, craned the LBB damper ring sandwich up to the top of the tank and suspended it.
 * Enzo and team corrected a lot of flipped connections on the SR3 PI LVDTs (primary<->secondary on the horizontal, primary<->actuation on the F0).
 * We added the arc weights and geophones and re-centered the IP. It seems stable and very soft, which is good.
Report for the week of 2/18 (February 18th)
Line 14: Line 7:
==== Plan for week of 7/9 ====
==== Plan for week of 7/16 ====
 * Monday 7/16 is Sea Day.
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.
===== Main Sequence =====
 * Check/restore alignment of payload, especially optic pitch.
 * Testing, TFs.
 * Lock suspension.
 * Crane into tank.
 * Unlock suspension.
 * Rearrange cables.
 * Test.
 * On Friday and Saturday last week the pump down of the central area took place. We monitored the drift in the four Type B IPs.
 * During the week we recovered the four suspensions successfully: we recovered the alignment of IMs, GAS filters, IPs, oplevs and measured TFs.
 * Terrence, Enzo and Mark installed the length sensing components in SR2 oplev. It's working now and we should use it now to measure the optic's corresponding TF.
 * The SRM IM is still drifting but the speed is decreasing. Yesterday Thursday the speed was '''-81 nrad/min'''. With the aim of predicting when the drift may stop Terrece removed offsets from the time series segments and spliced them in order. The work is still on progress.
 * Terrence did more work in changing the real-time models.
 * Mark did some initial debugging on the stepper reset system, starting with SRM. However there seems to be some model-related problem. A BIO Checker Board gave sensible results for the low 32 bits of DIO card #0 (used for the TM LPCD) but nothing for the high 32 bits (used for steppers, and eventually also the WD). He added the stepper reset stuff to the circuit diagram (D1503660) and made other corrections.
Line 27: Line 14:
===== F0/LBB Stuff =====
 * Install correct IP in PI #2.
 * Crane PI #2 to second floor.
 * Rebuild top filter of PI #2.
=== Plan for week of 2/25 ===
 * Mark from Tuesday.
 * Enzo from Monday lunchtime.
 * Continue debugging stepper reset system.
 * Continue monitoring SRM yaw drift.
 * Install new RTMs and Guardian.
 * Work on Type B paper.
Line 32: Line 22:
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Vacation/Travel Info ====
 * Enzo vacation, 3/5 and possibly 3/6.
 * Enzo et al. Farewell Party, 3/7.
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 2/18 (February 18th)

  • On Friday and Saturday last week the pump down of the central area took place. We monitored the drift in the four Type B IPs.
  • During the week we recovered the four suspensions successfully: we recovered the alignment of IMs, GAS filters, IPs, oplevs and measured TFs.
  • Terrence, Enzo and Mark installed the length sensing components in SR2 oplev. It's working now and we should use it now to measure the optic's corresponding TF.
  • The SRM IM is still drifting but the speed is decreasing. Yesterday Thursday the speed was -81 nrad/min. With the aim of predicting when the drift may stop Terrece removed offsets from the time series segments and spliced them in order. The work is still on progress.

  • Terrence did more work in changing the real-time models.
  • Mark did some initial debugging on the stepper reset system, starting with SRM. However there seems to be some model-related problem. A BIO Checker Board gave sensible results for the low 32 bits of DIO card #0 (used for the TM LPCD) but nothing for the high 32 bits (used for steppers, and eventually also the WD). He added the stepper reset stuff to the circuit diagram (D1503660) and made other corrections.

Plan for week of 2/25

  • Mark from Tuesday.
  • Enzo from Monday lunchtime.
  • Continue debugging stepper reset system.
  • Continue monitoring SRM yaw drift.
  • Install new RTMs and Guardian.
  • Work on Type B paper.

Vacation/Travel Info

  • Enzo vacation, 3/5 and possibly 3/6.
  • Enzo et al. Farewell Party, 3/7.
  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.