1648
Comment:
|
2427
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 7/17 ==== * We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement. * We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force. * We calibrated all the PI LVDTs. * We set the SF damper ring gap. * We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods. * Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank). * We installed more cable clamps on the SR2 PI. ==== Plan for week of 7/23 ==== * Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Hirata-san at Kamioka Mon-Thu. * Mirapro moves assembly frame ≈7/25 (Wed). ===== SR3 ===== * Unlock suspension. * Rearrange cables. * Test. ===== SR2 ===== * Finish PI prep. * Crane into AF, suspend. * Start cable routing. ===== SRM ===== * Prepare to assemble SRM metal mass (most parts due Wed 7/25). * Help Mirapro with AF move. * Start rebuild of top filter of PI #2. |
==== Report for week of 11/12 ==== * SRM * Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half. * Fabian and Hirata-san finished the in-vacuum cabling. * Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling. * We're now ready for final tests of the SF/... items and initial tests of the PI items. * Enzo and Fujii-kun built three geophones for SRM. * Mark worked on the height budget. * SR2 * Enzo experimented with [[http://www2.mpq.mpg.de/~ros/geo600_docu/soft/liso/manual.pdf|LISO]] (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.) |
Line 38: | Line 22: |
==== Vacation Info ==== * Hirata-san at Mitaka 7/27. * Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
==== Plan for week of 11/19 ==== * Friday 11/23 is Labor Thanksgiving Day. * Mark, Enzo and Fabian at Kamioka Mon-Thu. * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting). ===== SRM ===== * Go/no-go test of all electronics items, especially SF/... section. * Finish vertical height check and adjust SF trim mass as required. * Unlock IP and center roughly. * Check/adjust alignment of SS. * Calibrate IP LVDTs. * Add arc weights and geophones. * Improve centering/tuning of IP and SS alignment. * Disconnect cables at feedthroughs, lock suspension. * Crane into tank. ===== SR2 ===== * Assist MIF team with pico cables and LBB breadboard ballast. * Install SR2 OL pillar and shelf (with AOL supervision)? ==== Plan for week of 11/26 ==== * Move SRM in-air cables over to tank. * Remove First Contact. * Unlock and align SRM. * Hook and roughly ballast LBB. ==== Plan for week of 12/3 ==== * f2f Meeting at NAOJ - no Kamioka work. ==== Vacation/Event Info ==== * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 11/12
- SRM
- Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
- Fabian and Hirata-san finished the in-vacuum cabling.
- Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
- We're now ready for final tests of the SF/... items and initial tests of the PI items.
- Enzo and Fujii-kun built three geophones for SRM.
- Mark worked on the height budget.
- SR2
Enzo experimented with LISO (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)
To-Do Lists, Schedule
Plan for week of 11/19
- Friday 11/23 is Labor Thanksgiving Day.
- Mark, Enzo and Fabian at Kamioka Mon-Thu.
- Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
SRM
- Go/no-go test of all electronics items, especially SF/... section.
- Finish vertical height check and adjust SF trim mass as required.
- Unlock IP and center roughly.
- Check/adjust alignment of SS.
- Calibrate IP LVDTs.
- Add arc weights and geophones.
- Improve centering/tuning of IP and SS alignment.
- Disconnect cables at feedthroughs, lock suspension.
- Crane into tank.
SR2
- Assist MIF team with pico cables and LBB breadboard ballast.
- Install SR2 OL pillar and shelf (with AOL supervision)?
Plan for week of 11/26
- Move SRM in-air cables over to tank.
- Remove First Contact.
- Unlock and align SRM.
- Hook and roughly ballast LBB.
Plan for week of 12/3
- f2f Meeting at NAOJ - no Kamioka work.
Vacation/Event Info
- Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).