Size: 2930
Comment:
|
Size: 3428
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 7/23 ==== * We finished adding cable clamps to the SR2 PI and SF. * We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF. * We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments. * We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side. * We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.) * We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution. * With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters. * Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces. * Mark did inventory of the BIO stuff for the WD and of the OL parts. ==== Plan for week of 7/30 ==== * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon. ===== SR3 ===== * Finalize optic pitch, OSEM alignment. * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only). * Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator). |
==== Report for week of 10/15 ==== ===== SRM ===== * We received the fourth feedthrough we had been waiting for and installed it on the AF. * Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model. * Fabian and Enzo connected up the Sat Amps. * Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange. * Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough. * Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade. * Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2. * We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS. * Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT. * Enzo made a new batch of feedthrough adapters. |
Line 27: | Line 19: |
* Fix issue with PI/SS/chain alignment. * Put magnets on SR damper ring (2 Cu segment pattern). * Remove PI-SF rod temporarily, install Cu segments and damper ring. * Do vertical height budget; choose optimum F0 keystone height. * Add estimated final ballast mass. * Do PI cable routing. * Adjust ballast/trim mass, with reserve for cables. |
* We finalized the geophone cabling and reinstalled the geophones. * We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz. * Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29. ==== Plan for week of 10/22 ==== * Friday is NAOJ Open Day Prep - no Kamioka work. * Mark, Hirata-san and Fabian at Kamioka Mon-Thu. * Enzo at Kamioka Tue-Thu. ===== SR2 ===== * Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.) * Continue shakedown. * Gather parts for the OL (with help from Simon). |
Line 36: | Line 31: |
* Set up filter tuning area. * Tune F0 for SRM. * Add LBB blade units, cable clamps etc. * Check PI coil connections, IP LVDT magnets. |
* Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified. * Suspend/weigh/balance the BF/... section. * Build up the AF and SS to the SF level. * Install the SF. ==== Plan for week of 10/29 ==== * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri. ===== SR2 ===== * Set up OL. ===== SRM ===== * Continue assembly. |
Line 46: | Line 46: |
==== Vacation Info ==== * Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
==== Vacation/Visitor Info ==== * Terrence: 10/29-11/2 at Kamioka. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 10/15
SRM
- We received the fourth feedthrough we had been waiting for and installed it on the AF.
- Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model.
- Fabian and Enzo connected up the Sat Amps.
- Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange.
Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough.
- Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade.
- Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2.
- We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS.
- Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT.
- Enzo made a new batch of feedthrough adapters.
SR2
- We finalized the geophone cabling and reinstalled the geophones.
- We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz.
- Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29.
Plan for week of 10/22
- Friday is NAOJ Open Day Prep - no Kamioka work.
- Mark, Hirata-san and Fabian at Kamioka Mon-Thu.
- Enzo at Kamioka Tue-Thu.
SR2
- Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
- Continue shakedown.
- Gather parts for the OL (with help from Simon).
SRM
- Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified.
- Suspend/weigh/balance the BF/... section.
- Build up the AF and SS to the SF level.
- Install the SF.
Plan for week of 10/29
- Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
SR2
- Set up OL.
SRM
- Continue assembly.
To-Do Lists, Schedule
Vacation/Visitor Info
- Terrence: 10/29-11/2 at Kamioka.