Line 6: Line 6:
==== Report for week of 7/23 ====
 * We finished adding cable clamps to the SR2 PI and SF.
 * We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF.
 * We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments.
 * We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side.
 * We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.)
 * We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution.
 * With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters.
 * Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces.
 * Mark did inventory of the BIO stuff for the WD and of the OL parts.
==== Report for week of 12/17 ====
 * BS
  * Miyakawa-san worked on the BS real-time model and the gain/offset settings for the F0 LVDTINF block were lost, so we reentered them and did a new safe.snap file.
 * SRM
  * We unlocked the IP adjusted the level with the jacks to center it. As hoped, this also improved the alignment of the chain insecurity structure and fixed a touching issue.
  * Hirata-san installed and cabled the new F0 yaw stepper. We had allowed plenty of reserve mass, so there was no problem getting back to nominal height of the keystone. [''As of Thursday afternoon, it had not yet been tested - UPDATE?'']
  * We found that the Nikhef method Fabian had used to tune the F0 LVDT driver gave an artificially narrow working range, so he retuned it with Enzo's method and recalibrated the LVDT.
  * Fabian did a vertical position survey with all the GAS filters at nominal and found the height of the RM above the SS bottom plate was about 2.5 mm lower than in the CAD. This is about what we expected from a chain 7 mm longer than CAD and and F0 keystone set to 5 mm higher than CAD. In future we can survey to either the optic or the security structure as convenient, and we are in the range where we should easily be able to match the correct beam height with the jacks under the PI.
  * We got two OL viewports for SRM from Akutsu-san, and will install them sometime in January, whenever we have a free moment. Akutsu-san pre-torqued the inner ring of screws around the glass, so we only need to torque the outer bolts.
  * We took transfer functions for the IM. All of them look good except IM-T. We will inspect the payload next week in case anything is touching or rubbing.
  * Hirata-san opened the +X door of the vacuum chamber for visual inspection. We closed it back and covered with tape a small gap at the door.
 * SR3
  * We also got a camera viewport for SR3 from Akutsu-san and will install it sometime in January.
  * Hirata-san installed and cabled the new F0 yaw stepper.
 * SR2
  * Enzo calibrated the SR2 OL. He noted that with the standard f=2500 mm collimator, the angular range was only about 100 µrad in pitch and 150 µrad in yaw, which is rather less than Enomoto-kun's preferred range of more like 400 µrad, so we borrowed f=1100 mm and f=3500 mm collimators to characterize. [''Enzo was going to do f=1100 mm and maybe f=3500 mm on Friday morning 12/21 - UPDATE?'']
  * Hirata-san installed and cabled the new F0 yaw stepper. We did not have enough reserve mass for SR2, so to save 300 g we had Mesco make a new, lighter top plate, and Hirata-san ultrasonically cleaned it. We were then able to get the desired F0 keystone height with about 200 g to spare.
  * The RM was touching the security structure due to a large yaw displacement. We were able to move it free by adjusting the cylinder with the spring and leaving the stepper motor in its nominal position. The f=1100 mm collimator was installed and the QPD was calibrated.
Line 17: Line 25:
==== Plan for week of 7/30 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.
---- /!\ '''Edit conflict - your version:''' ----
  * Hirata-san opened the +X door of the vacuum chamber so we could inspect the payload, especially the OSEMs. We closed it back and covered with tape a small gap at the door.
 * SR3
  * We also got a camera viewport for SR3 from Akutsu-san and will install it sometime in January.
  * Hirata-san installed and cabled the new F0 yaw stepper.
 * SR2
  * Enzo calibrated the SR2 OL. He noted that with the standard f=2500 mm collimator, the angular range was only about 100 µrad in pitch and 150 µrad in yaw, which is rather less than Enomoto-kun's preferred range of more like 400 µrad, so we borrowed f=1100 mm and f=3500 mm collimators to characterize. Enzo did f=1100 mm and will do f=3500 mm soon.]
  * Hirata-san installed and cabled the new F0 yaw stepper. We did not have enough reserve mass for SR2, so to save 300 g we had Mesco make a new, lighter top plate, and Hirata-san ultrasonically cleaned it. We were then able to get the desired F0 keystone height with about 200 g to spare.
  * After installing the yaw stepper, the RM was touching the security structure but we were able to move it free by adjusting the cylinder with the spring and leaving the stepper motor in its nominal position.
Line 21: Line 35:
===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
 * Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator).

===== SR2 =====
 * Fix issue with PI/SS/chain alignment.
 * Put magnets on SR damper ring (2 Cu segment pattern).
 * Remove PI-SF rod temporarily, install Cu segments and damper ring.
 * Do vertical height budget; choose optimum F0 keystone height.
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
 
===== SRM =====
 * Set up filter tuning area.
 * Tune F0 for SRM.
 * Add LBB blade units, cable clamps etc.
 * Check PI coil connections, IP LVDT magnets.
---- /!\ '''End of edit conflict''' ----
 * Etc
  * Enzo did a historical survey of the temperature as the various suspensions were being built and concluded that ideal operating temperature would be 25°C in the BS/SR2 area and 24°C for SR3/SRM.
  * Mark wrote a bash script to log all the GAS filter heights and LVDT actuation offsets, and an Excel spreadsheet to analyze the data to get an overview of the heights of the suspensions and the amount of height adjustment being used. He also reviewed old TF data to get near-DC values for the effect of GAS actuation on GAS height. This uncovered a few issues with calibration settings (such as for BS F0) having been lost because they hadn't been recorded in a safe.snap file, which we fixed.
Line 46: Line 45:
==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Plan for week of 12/17 ====
 * Final alignment of SRM payload, plus BF and SF GAS.
 * (Time permitting) unlocking/centering/tuning of IP.
 * Installation of Enomoto-kun's beam target on SRM (if available).
 * Installation/testing of F0 steppers on SR2, SR3, SRM, and (hopefully) final vertical height adjustment.
 * Installation of viewports on SRM.

==== Plan for week of 12/24 ====
 * Mark and Hirata-san on holidays, Enzo at Mitaka, Fabian.

==== Plan for week of 1/7 ====
 * Make sure BS is floating, recenter OL to capture current yaw position.
 * Vent BS.
 * Inspect BS F0 blades for cracks.
 * Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.
 * Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
 * Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
 * Add more mass to IP to get lower frequency.
 * Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).

==== Vacation/Etc Info ====
 * Mark: 12/24 - 1/4.
 * Hirata-san: 12/24 - 1/4.
 * Fabian: 12/31 - 1/4
 * Enzo: 12/31 - 1/4.
 * Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
 * Terrence: back at Kamioka from 1/7.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 12/17

  • BS
    • Miyakawa-san worked on the BS real-time model and the gain/offset settings for the F0 LVDTINF block were lost, so we reentered them and did a new safe.snap file.
  • SRM
    • We unlocked the IP adjusted the level with the jacks to center it. As hoped, this also improved the alignment of the chain insecurity structure and fixed a touching issue.
    • Hirata-san installed and cabled the new F0 yaw stepper. We had allowed plenty of reserve mass, so there was no problem getting back to nominal height of the keystone. [As of Thursday afternoon, it had not yet been tested - UPDATE?]

    • We found that the Nikhef method Fabian had used to tune the F0 LVDT driver gave an artificially narrow working range, so he retuned it with Enzo's method and recalibrated the LVDT.
    • Fabian did a vertical position survey with all the GAS filters at nominal and found the height of the RM above the SS bottom plate was about 2.5 mm lower than in the CAD. This is about what we expected from a chain 7 mm longer than CAD and and F0 keystone set to 5 mm higher than CAD. In future we can survey to either the optic or the security structure as convenient, and we are in the range where we should easily be able to match the correct beam height with the jacks under the PI.
    • We got two OL viewports for SRM from Akutsu-san, and will install them sometime in January, whenever we have a free moment. Akutsu-san pre-torqued the inner ring of screws around the glass, so we only need to torque the outer bolts.
    • We took transfer functions for the IM. All of them look good except IM-T. We will inspect the payload next week in case anything is touching or rubbing.
    • Hirata-san opened the +X door of the vacuum chamber for visual inspection. We closed it back and covered with tape a small gap at the door.
  • SR3
    • We also got a camera viewport for SR3 from Akutsu-san and will install it sometime in January.
    • Hirata-san installed and cabled the new F0 yaw stepper.
  • SR2
    • Enzo calibrated the SR2 OL. He noted that with the standard f=2500 mm collimator, the angular range was only about 100 µrad in pitch and 150 µrad in yaw, which is rather less than Enomoto-kun's preferred range of more like 400 µrad, so we borrowed f=1100 mm and f=3500 mm collimators to characterize. [Enzo was going to do f=1100 mm and maybe f=3500 mm on Friday morning 12/21 - UPDATE?]

    • Hirata-san installed and cabled the new F0 yaw stepper. We did not have enough reserve mass for SR2, so to save 300 g we had Mesco make a new, lighter top plate, and Hirata-san ultrasonically cleaned it. We were then able to get the desired F0 keystone height with about 200 g to spare.
    • The RM was touching the security structure due to a large yaw displacement. We were able to move it free by adjusting the cylinder with the spring and leaving the stepper motor in its nominal position. The f=1100 mm collimator was installed and the QPD was calibrated.


/!\ Edit conflict - your version:


  • Hirata-san opened the +X door of the vacuum chamber so we could inspect the payload, especially the OSEMs. We closed it back and covered with tape a small gap at the door.
  • SR3
    • We also got a camera viewport for SR3 from Akutsu-san and will install it sometime in January.
    • Hirata-san installed and cabled the new F0 yaw stepper.
  • SR2
    • Enzo calibrated the SR2 OL. He noted that with the standard f=2500 mm collimator, the angular range was only about 100 µrad in pitch and 150 µrad in yaw, which is rather less than Enomoto-kun's preferred range of more like 400 µrad, so we borrowed f=1100 mm and f=3500 mm collimators to characterize. Enzo did f=1100 mm and will do f=3500 mm soon.]
    • Hirata-san installed and cabled the new F0 yaw stepper. We did not have enough reserve mass for SR2, so to save 300 g we had Mesco make a new, lighter top plate, and Hirata-san ultrasonically cleaned it. We were then able to get the desired F0 keystone height with about 200 g to spare.
    • After installing the yaw stepper, the RM was touching the security structure but we were able to move it free by adjusting the cylinder with the spring and leaving the stepper motor in its nominal position.


/!\ End of edit conflict


  • Etc
    • Enzo did a historical survey of the temperature as the various suspensions were being built and concluded that ideal operating temperature would be 25°C in the BS/SR2 area and 24°C for SR3/SRM.
    • Mark wrote a bash script to log all the GAS filter heights and LVDT actuation offsets, and an Excel spreadsheet to analyze the data to get an overview of the heights of the suspensions and the amount of height adjustment being used. He also reviewed old TF data to get near-DC values for the effect of GAS actuation on GAS height. This uncovered a few issues with calibration settings (such as for BS F0) having been lost because they hadn't been recorded in a safe.snap file, which we fixed.

To-Do Lists, Schedule

Plan for week of 12/17

  • Final alignment of SRM payload, plus BF and SF GAS.
  • (Time permitting) unlocking/centering/tuning of IP.
  • Installation of Enomoto-kun's beam target on SRM (if available).
  • Installation/testing of F0 steppers on SR2, SR3, SRM, and (hopefully) final vertical height adjustment.
  • Installation of viewports on SRM.

Plan for week of 12/24

  • Mark and Hirata-san on holidays, Enzo at Mitaka, Fabian.

Plan for week of 1/7

  • Make sure BS is floating, recenter OL to capture current yaw position.
  • Vent BS.
  • Inspect BS F0 blades for cracks.
  • Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.

  • Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
  • Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
  • Add more mass to IP to get lower frequency.
  • Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).

Vacation/Etc Info

  • Mark: 12/24 - 1/4.
  • Hirata-san: 12/24 - 1/4.
  • Fabian: 12/31 - 1/4
  • Enzo: 12/31 - 1/4.
  • Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
  • Terrence: back at Kamioka from 1/7.