Differences between revisions 307 and 331 (spanning 24 versions)
Revision 307 as of 2018-08-03 15:53:37
Size: 2564
Editor: MarkBarton
Comment:
Revision 331 as of 2018-10-05 18:27:58
Size: 3203
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for week of 7/30 ====
 * We set up an OL outside the tank and checked the SR3 pitch - it was OK.
 * We ran power to the SR3 pico and stepper drivers and tested them.
 * We tried to offload a 700 µm discrepancy between the BF GAS zero position and the IM-V zero position but ended up scrambling the IRM-IM alignment, probably through sending a command to the wrong pico driver. We mostly fixed the BF/IRM pitch/roll, but we have some more work to do to fix the IM/RM/TM pitch/roll.
 * We debugged a problem with the SR2 alignment - the chain was offset by about 5 mm to +T, leading to fouling at the IM and RM levels. Some 2 mm of the offset was due to the F0 keystone being off center, apparently due to some combination of different-strength blades and the CuBe auxiliary spring, but the rest is a mystery.
 * We fixed a problem with the levelness of the PI due to the feet of the IP being set at uneven heights into the PI weldment, and it got the IP very closed to centered but it didn't fix the fouling problem.
 * We eventually fixed the fouling by setting the security structure at a slight angle so it remains slightly off at the SF level but is good at the bottom.
 * We installed the SR2 SF damper Cu segments and magnet ring.
 * Enzo and team debugged a malfunctioning bit in the SR3 IP BIO which turned out to be a defective 37-pin gender changer.
==== Report for week of 10/1 ====
===== SR2 =====
 * We solved a mystery with the height of the BF keystone: it turns out that running the table KOACH filters in the tank warms it up (by about 1.5°C) and causes significant sag (700 µm). D'oh!
 * We ran power to the pico drivers.
 * We got the lower section of the SR2 fairly well aligned with just a bit of adjustment with the IM pitch and roll picos.
 * We helped Lucia double-check the geometry of the IP - the current matrix calculation assumes the FRs and the LVDT sensors and actuators are colocated, which is much closer to true than for the BS, but not quite right.
 * We gave up on doing anything more with SR2 for now because we're waiting on extra extension cables for the PI and Fujii-kun will want to borrow one of the geophones next week for a huddle test with new geophones.
===== SRM =====
 * We set the pitch of the SRM and RM, tightened the clamps and removed the winch system.
 * We installed the BF crossbars of the assembly frame and the BF ring section of the security structure.
 * We lifted the IM/... section on the load gauge to find its weight.
 * We craned in the BF and removed the cap.
 * We installed the BF-IRM rods and the IRM top plate.
 * We installed the BF-IM maraging rod and flying saucer cable clamps.
 * We suspended the IM/... section and adjusted the trim masses for balance and total mass. It took quite a lot of adjustment in each of pitch, roll and vertical. The vertical was due to the fact that the weight of the IM/... section is very close to that of SR2/SR3 but the SRM BF is about 0.5 kg weaker. The roll was due to the fact that the default configuration of trim mass had no correction for the horizontal wedge on the optic. However the pitch is a bit of a mystery - nearly all of the removed mass had to come off the AR side. Fortunately we were able to correct for it entirely with masses we had in hand.
 * We routed the TM OSEM cables via the flying saucer up to the underside of the BF.
 * We got 2 power supplies from Shimode-san so we can fire up the SRM rack next week. He will also supply suitable cables to connect the power supplies to the DC power strip in the rack.
 * We received the replated yoke for the SRM top filter.
Line 16: Line 25:
==== Plan for week of 8/6 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Do TFs with temporary OL.
 * Install final OL.
 * Hook LBB, add ballast mass.

===== SR2 =====
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
 
==== Plan for week of 10/8 ====
 * Monday 10/8 is Sports Day.
 * Enzo returns Tuesday 10/9.
 * Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
 * Enzo, Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.
===== SR2/SR3 =====
 * Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.
Line 32: Line 33:
 * Assemble metal mass.
 * Glue prisms, flags.
 * Reconfigure, align assembly frame.
 * Tune F0 for SRM.
 * Add LBB blade units, cable clamps etc.
 * Check PI coil connections, IP LVDT magnets.
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.
 * Suspend/weigh/balance the BF/... section.
Line 44: Line 43:
==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 *
Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Vacation/Visitor Info ====
 * Enzo: 9/15 through 10/8 vacation in Chile.
 * Terrence: 10/8-12, 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/1

SR2
  • We solved a mystery with the height of the BF keystone: it turns out that running the table KOACH filters in the tank warms it up (by about 1.5°C) and causes significant sag (700 µm). D'oh!
  • We ran power to the pico drivers.
  • We got the lower section of the SR2 fairly well aligned with just a bit of adjustment with the IM pitch and roll picos.
  • We helped Lucia double-check the geometry of the IP - the current matrix calculation assumes the FRs and the LVDT sensors and actuators are colocated, which is much closer to true than for the BS, but not quite right.
  • We gave up on doing anything more with SR2 for now because we're waiting on extra extension cables for the PI and Fujii-kun will want to borrow one of the geophones next week for a huddle test with new geophones.

SRM
  • We set the pitch of the SRM and RM, tightened the clamps and removed the winch system.
  • We installed the BF crossbars of the assembly frame and the BF ring section of the security structure.
  • We lifted the IM/... section on the load gauge to find its weight.
  • We craned in the BF and removed the cap.
  • We installed the BF-IRM rods and the IRM top plate.
  • We installed the BF-IM maraging rod and flying saucer cable clamps.
  • We suspended the IM/... section and adjusted the trim masses for balance and total mass. It took quite a lot of adjustment in each of pitch, roll and vertical. The vertical was due to the fact that the weight of the IM/... section is very close to that of SR2/SR3 but the SRM BF is about 0.5 kg weaker. The roll was due to the fact that the default configuration of trim mass had no correction for the horizontal wedge on the optic. However the pitch is a bit of a mystery - nearly all of the removed mass had to come off the AR side. Fortunately we were able to correct for it entirely with masses we had in hand.
  • We routed the TM OSEM cables via the flying saucer up to the underside of the BF.
  • We got 2 power supplies from Shimode-san so we can fire up the SRM rack next week. He will also supply suitable cables to connect the power supplies to the DC power strip in the rack.
  • We received the replated yoke for the SRM top filter.

Plan for week of 10/8

  • Monday 10/8 is Sports Day.
  • Enzo returns Tuesday 10/9.
  • Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
  • Enzo, Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.

SR2/SR3
  • Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.

SRM
  • Cable/test BF.
  • Install IRM.
  • Install/cable/test IM OSEMs.
  • Suspend/weigh/balance the BF/... section.

To-Do Lists, Schedule

Vacation/Visitor Info

  • Enzo: 9/15 through 10/8 vacation in Chile.
  • Terrence: 10/8-12, 10/29-11/2 at Kamioka.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)