==== Report for week of 7/30 ====
===== SR3 ======
 * We undid the accidental misalignment of the SR3. We also switched off the BF GAS offset we had been using, let the IM rise until near zero on the BF LVDT, and adjusted the IM vertical OSEMs back to mid-range.
 * We closed control loops for the SR3 GAS filters.
===== SR2 =====
 * We installed the SR2 SF damper magnet ring but found that the magnet pattern didn't match the Cu segments due to a different in the caps between SR3 and SR2. We raised the ring but left it suspended, clamped the template to the underside and rearranged the magnets.
 * We did a vertical height budget of the SR2. It turns out to have a very similar issue to the SR3: the chain is about 5 mm longer than the CAD, with about 3 mm of that between the SF and BF. We decided to do the same fix and operate with the F0 keystone 5 mm higher. We chose an total amount of ballast to give that keystone height and secured most of it to the SF, keeping a reserve for cables and the yaw stepper.
==== Report for week of 10/22 ====
Line 14: Line 8:
 * We moved the SRM assembly frame into its final position, reset it to the initial configuration, double-checked the heights of the crossbars, and lowered the optical table by 3 mm (to give margin for the optic to rise during hanging, which we had kept forgetting to do). We cleaned it up with the airgun and wet-wipes. We installed the IM ring and IM.
 * We assembled the SRM metal mass. Hirata-san made a jig from a plate with 4 screws which could safely hold the delicate front Sol-Black-coated ring upside down while the rest of the components were mounted on it.
 * We moved the metal mass to the mirror box and added the prisms and magnet standoffs.

==== Plan for week of 8/20 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Terrence and TBD at f2f on Friday 8/24.
 * Kozu-kun works at Mozumi Mon, Fri.

===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Do TFs with temporary OL.
 * Install final OL.
 * Hook LBB, add ballast mass.
 * Tune IP.
 * We borrowed the TM HPCDs from SR2 and SR3 so that SRM had HPCDs for IM-H, IM-V and GAS.
 * Fabian adjusted the last two OSEMs (IM-H2 and H3).
 * We closed the BF and weighed the BF/... section.
 * Fabian and Hirata-san routed all the BF/... cables via the BF cap (except for the four TM OSEM cables, where we're still waiting for extensions).
 * We built up the assembly frame and security structure to the SF level and craned in the SF.
 * We installed the SF-BF rod and flying saucer, and suspended the BF/... section. We will need about 600 g on the BF cap for balance and SF keystone height, which is as expected and not a problem.
 * Hirata-san collected a suitable CuBe spring and bracket parts from Type A. He ultrasonically cleaned the bracket and then installed the bracket and spring on the F0. The frequency increased from 0.5 Hz to 0.625 Hz, so he did another round of compression, from 30 mm to 31.3 mm.
 * Enzo soldered some short and/or broken cables to make longer cables that we need urgently. He got in touch with Yamamoto-san to arrange bringing them to Toyama University and ultrasonically cleaning them.
 * We pulled out cables running to the OMMT area that were used for the old OSEM/geophone testing setup and started a new geophone testing setup in the SR3 area using the optical table from the SR2 assembly frame.
 * Hirose-san reported results from his astigmatism test on the second SRM small optic and metal mass. With the tight shims (1.0 mm thickness, as used for the installed SRM) there was substantial astigmatism, but with the next looser available size (1.5 mm) there was no astigmatism but the optic is held very poorly and rattles. Hirose-san is ordering some intermediate thicknesses and will make a recommendation. However he will almost certainly suggest that we change the shims on the hanging SRM, so we need to think about whether that is feasible.
Line 31: Line 20:
 * Do vertical height budget.
 * Choose F0 keystone height.
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
 * Stage LBB damper rings in tank.
 
 * Akutsu-san gathered the parts we will need for the SR2 OL so that Terrence can install it next week.
 * Hirata-san supervised the disassembly of the assembly frame. The pieces are now in the IMMT area, although we may need to move them again because they're a bit in the way.

==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
===== SR2 =====
 * Set up OL.
 * Possibly do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
 * Possibly add more arc weights, to get below 0.1 Hz.
Line 39: Line 30:
 * Assemble metal mass.
 * Glue prisms, flags.
 * Reconfigure, align assembly frame.
 * Electronics
  * More cable soldering?
  * Get soldered cables ultrasonically cleaned.
  * Collect unused cables for return to AEL.
 * PI
  * Finalize tuning.
  * Add more cable clamps.
  * Prepare SF magnet ring.
 * Main sequence
  * Cable/test SF LVDT and FR.
  * Decide and install SF internal ballast mass (probably 1 Promec).
  * Reinstall SF cap.
  * Weigh SF/... section.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
Line 48: Line 56:
==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri (except Hirata-san to take compensation day Friday or Monday (TBD)).
===== SRM =====
 * Main sequence
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
  * Unlock IP and center roughly.
  * Calibrate IP LVDTs.
  * Check/adjust alignment of SS.
  * Add arc weights and geophones (or extra mass equivalent to geophones).
  * Cable/test geophones.
  * Improve centering/tuning of IP and SS alignment.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.

==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/22

SRM
  • We borrowed the TM HPCDs from SR2 and SR3 so that SRM had HPCDs for IM-H, IM-V and GAS.
  • Fabian adjusted the last two OSEMs (IM-H2 and H3).
  • We closed the BF and weighed the BF/... section.
  • Fabian and Hirata-san routed all the BF/... cables via the BF cap (except for the four TM OSEM cables, where we're still waiting for extensions).
  • We built up the assembly frame and security structure to the SF level and craned in the SF.
  • We installed the SF-BF rod and flying saucer, and suspended the BF/... section. We will need about 600 g on the BF cap for balance and SF keystone height, which is as expected and not a problem.
  • Hirata-san collected a suitable CuBe spring and bracket parts from Type A. He ultrasonically cleaned the bracket and then installed the bracket and spring on the F0. The frequency increased from 0.5 Hz to 0.625 Hz, so he did another round of compression, from 30 mm to 31.3 mm.

  • Enzo soldered some short and/or broken cables to make longer cables that we need urgently. He got in touch with Yamamoto-san to arrange bringing them to Toyama University and ultrasonically cleaning them.
  • We pulled out cables running to the OMMT area that were used for the old OSEM/geophone testing setup and started a new geophone testing setup in the SR3 area using the optical table from the SR2 assembly frame.
  • Hirose-san reported results from his astigmatism test on the second SRM small optic and metal mass. With the tight shims (1.0 mm thickness, as used for the installed SRM) there was substantial astigmatism, but with the next looser available size (1.5 mm) there was no astigmatism but the optic is held very poorly and rattles. Hirose-san is ordering some intermediate thicknesses and will make a recommendation. However he will almost certainly suggest that we change the shims on the hanging SRM, so we need to think about whether that is feasible.

SR2
  • Akutsu-san gathered the parts we will need for the SR2 OL so that Terrence can install it next week.
  • Hirata-san supervised the disassembly of the assembly frame. The pieces are now in the IMMT area, although we may need to move them again because they're a bit in the way.

Plan for week of 10/29

  • Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.

SR2
  • Set up OL.
  • Possibly do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
  • Possibly add more arc weights, to get below 0.1 Hz.

SRM
  • Electronics
    • More cable soldering?
    • Get soldered cables ultrasonically cleaned.
    • Collect unused cables for return to AEL.
  • PI
    • Finalize tuning.
    • Add more cable clamps.
    • Prepare SF magnet ring.
  • Main sequence
    • Cable/test SF LVDT and FR.
    • Decide and install SF internal ballast mass (probably 1 Promec).
    • Reinstall SF cap.
    • Weigh SF/... section.
    • Install #353 poles
    • Move NB-03 jacks down.
    • Crane PI into AF.
    • Install F0-SF rod (#331) and flying saucer.
    • Route SF/... cables up to underside of F0.
    • Do vertical height budget.
    • Adjust SF trim mass for balance and keystone height.

To-Do Lists, Schedule

Plan for week of 10/29

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri (except Hirata-san to take compensation day Friday or Monday (TBD)).

SRM
  • Main sequence
    • Cable/test IP LVDTs.
    • Cable/test IP FRs.
    • Unlock IP and center roughly.
    • Calibrate IP LVDTs.
    • Check/adjust alignment of SS.
    • Add arc weights and geophones (or extra mass equivalent to geophones).
    • Cable/test geophones.
    • Improve centering/tuning of IP and SS alignment.
  • LBB
    • Move KOACH filters
    • Put LBB damper rings in tank.
    • Set tank jacks to nominal height.