Differences between revisions 31 and 142 (spanning 111 versions)
Revision 31 as of 2016-06-24 13:21:11
Size: 2284
Editor: MarkBarton
Comment:
Revision 142 as of 2017-05-18 17:18:39
Size: 2573
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian worked at Kamioka:
   * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added.
   * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction.
   * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area.
   * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction.
   * Hirata-san shipped 7 SFs and some parts to Kamioka.
   * Hirata-san made assembly drawings of the damper rings and cable clamps for SR.
   * Hirata-san liaised with Mirapro about the frame assembly.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Installation stuff
   * Crane scale - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

 * We removed the PI from the assembly frame.
 * We encountered a problem with the PI-SF rod jamming in the SF. We finally got it out by clamping a pig of vice grips to the rod and hammering. We found that the receptacle part was the right size (7.0 mm) but had been deformed around the edge. Hirata-san used a knife and sandpaper to lean up the edge and then ultrasonically cleaned it.
 * We cleared space for the PR2 team to remove a bellows from their tank.
 * We installed safety bars near the assembly frame at about waist height for someone on the tall ladder. We reinforced the clamps with cable ties.
 * We removed the LLB blade units from the PI, removed the blades from the clamps and sent the blades away for more rework to fix the length problem. Fortunately the tab section at the tip is fairly long, so we can just add a second hole further from the end.
 * We removed the SF cap and stored it on crossbars within the assembly frame.
 * We tested the SR fishing rod again, but it would only go up, not down. We found that reseting the driver fixed it, but we also moved the driver boxes into the cleanbooth to reduce the length of the motor cables. (Instead, we had to run some long DC and LAN cables.)
 * We adjusted the limit nut on the SF fishing rod to increase the range.
 * We removed one segment of the Cu ring on the SF cap and reconfigured the rest to be symmetrical.
 * Fabian designed a layout for the SF damper ring magnets that would work with the modified Cu ring, and placed the magnets with the template. The poles of the magnets were not on the expected faces so we had to stand the magnets up with the ,


==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 5/15:
 * Enzo from Tuesday 5/16 (driving test), rest of team from Monday.
 * Fix PI-SF rod jamming.
 * Remove PI and SF cap.
 * Continue debugging SF LVDT.
 * Reconfigure Cu damper ring on SF.
 * Add magnets to upper SF damper ring.
 * Add cable clamps on the PI (a few places are inaccessible when the PI is on the assembly frame).
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Prepare for PR2 bellows removal on 5/15 (move table with tools).
 * Cable/test PI horizontal LVDTs and steppers.
 * Install/cable/test geophones.
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • We removed the PI from the assembly frame.
  • We encountered a problem with the PI-SF rod jamming in the SF. We finally got it out by clamping a pig of vice grips to the rod and hammering. We found that the receptacle part was the right size (7.0 mm) but had been deformed around the edge. Hirata-san used a knife and sandpaper to lean up the edge and then ultrasonically cleaned it.
  • We cleared space for the PR2 team to remove a bellows from their tank.
  • We installed safety bars near the assembly frame at about waist height for someone on the tall ladder. We reinforced the clamps with cable ties.
  • We removed the LLB blade units from the PI, removed the blades from the clamps and sent the blades away for more rework to fix the length problem. Fortunately the tab section at the tip is fairly long, so we can just add a second hole further from the end.
  • We removed the SF cap and stored it on crossbars within the assembly frame.
  • We tested the SR fishing rod again, but it would only go up, not down. We found that reseting the driver fixed it, but we also moved the driver boxes into the cleanbooth to reduce the length of the motor cables. (Instead, we had to run some long DC and LAN cables.)
  • We adjusted the limit nut on the SF fishing rod to increase the range.
  • We removed one segment of the Cu ring on the SF cap and reconfigured the rest to be symmetrical.
  • Fabian designed a layout for the SF damper ring magnets that would work with the modified Cu ring, and placed the magnets with the template. The poles of the magnets were not on the expected faces so we had to stand the magnets up with the ,

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 5/15:

  • Enzo from Tuesday 5/16 (driving test), rest of team from Monday.
  • Fix PI-SF rod jamming.
  • Remove PI and SF cap.
  • Continue debugging SF LVDT.
  • Reconfigure Cu damper ring on SF.
  • Add magnets to upper SF damper ring.
  • Add cable clamps on the PI (a few places are inaccessible when the PI is on the assembly frame).
  • Reinstall PI, this time with rods and damper ring.
  • Reinstall PI-SF rod, this time with hex cable clamp.
  • Prepare for PR2 bellows removal on 5/15 (move table with tools).
  • Cable/test PI horizontal LVDTs and steppers.
  • Install/cable/test geophones.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)