Differences between revisions 31 and 162 (spanning 131 versions)
Revision 31 as of 2016-06-24 13:21:11
Size: 2284
Editor: MarkBarton
Comment:
Revision 162 as of 2017-06-30 13:54:45
Size: 2556
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian worked at Kamioka:
   * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added.
   * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction.
   * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area.
   * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction.
   * Hirata-san shipped 7 SFs and some parts to Kamioka.
   * Hirata-san made assembly drawings of the damper rings and cable clamps for SR.
   * Hirata-san liaised with Mirapro about the frame assembly.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Installation stuff
   * Crane scale - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Enzo, Simon, Type Bp team):
 * Mark remade the BF pico adapter cable which was poorly made and had also been damaged.
 * The Type Bp team tided up the BS rack and made new labels for many cables (thanks!).
 * Enzo connected up the in-air cables for the picos and steppers.
 * Mark and Enzo renumbered the PI LVDTs, geophones and LVDTs to make a consistent scheme working anticlockwise.
 * Enzo and Mark debugged all the cables. The only problem we couldn't solve was that the actuator coil for PI LVDT #0 is open-circuit at the connector on the LVDT. (It has been intermittent but worked before the craning.) We may have to redo the connector or replace the LVDT. Limited TFs will be possible in the next week.
 * Simon set up the LSOL and was easily able to get a return beam from the mirror on the dummy BS.
 * Shoda-san copied over the LSOL section of the PR3 real-time model into the BS model and made other improvements (thanks!).
 * Mark brought home

At Mitaka (Fabian, Hirata-san):
 * Fabian finished designing final trim masses for IM/BF/SF for the final hang of the BS and passed it to Hirata-san to make drawings and get quotes.
 * Hirata-san requested quotes for the replaceable-jaw version of the BS wire clamps.
 * Fabian and Hirata-san gathered needed items for the BS prism/flag gluing.
 * Hirata-san designed receptacles for the new rods with 8 mm heads and requested quotes.

==== Plan for week of 7/3 ====
 * Do prism/flag gluing on real BS at Kashiwa (whole team).
 * Do new 3D CAD (Hirata-san):
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
  * Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
   * In-tank version.
 * Solve arc weight versus magic wand problem.
 * Do mass budget for LBB - design ballast masses (Fabian)
 * Run TFs, make improvements to real-time model (Mark, Enzo).

==== Plan for week of 7/10 ====
Mark and Enzo at Kamioka:
 * Fix broken LVDT actuator coil.
 * Learn how Miyo-kun's pico driver software works and make improvements.
 * Test picos and steppers more fully.
 * Finish tidying rack and labeling cables.
Fabian and Hirata-san at Mitaka.
 * Design SR assembly frame.
 * Inventory for SR.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Enzo, Simon, Type Bp team):

  • Mark remade the BF pico adapter cable which was poorly made and had also been damaged.
  • The Type Bp team tided up the BS rack and made new labels for many cables (thanks!).
  • Enzo connected up the in-air cables for the picos and steppers.
  • Mark and Enzo renumbered the PI LVDTs, geophones and LVDTs to make a consistent scheme working anticlockwise.
  • Enzo and Mark debugged all the cables. The only problem we couldn't solve was that the actuator coil for PI LVDT #0 is open-circuit at the connector on the LVDT. (It has been intermittent but worked before the craning.) We may have to redo the connector or replace the LVDT. Limited TFs will be possible in the next week.
  • Simon set up the LSOL and was easily able to get a return beam from the mirror on the dummy BS.
  • Shoda-san copied over the LSOL section of the PR3 real-time model into the BS model and made other improvements (thanks!).
  • Mark brought home

At Mitaka (Fabian, Hirata-san):

  • Fabian finished designing final trim masses for IM/BF/SF for the final hang of the BS and passed it to Hirata-san to make drawings and get quotes.
  • Hirata-san requested quotes for the replaceable-jaw version of the BS wire clamps.
  • Fabian and Hirata-san gathered needed items for the BS prism/flag gluing.
  • Hirata-san designed receptacles for the new rods with 8 mm heads and requested quotes.

Plan for week of 7/3

  • Do prism/flag gluing on real BS at Kashiwa (whole team).
  • Do new 3D CAD (Hirata-san):
    • SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
    • Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
      • On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
      • In-tank version.
  • Solve arc weight versus magic wand problem.
  • Do mass budget for LBB - design ballast masses (Fabian)
  • Run TFs, make improvements to real-time model (Mark, Enzo).

Plan for week of 7/10

Mark and Enzo at Kamioka:

  • Fix broken LVDT actuator coil.
  • Learn how Miyo-kun's pico driver software works and make improvements.
  • Test picos and steppers more fully.
  • Finish tidying rack and labeling cables.

Fabian and Hirata-san at Mitaka.

  • Design SR assembly frame.
  • Inventory for SR.