* Type B Past Week Summary * Mark and Fabian worked at Kamioka: * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added. * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction. * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area. * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction. * Hirata-san shipped 7 SFs and some parts to Kamioka. * Hirata-san made assembly drawings of the damper rings and cable clamps for SR. * Hirata-san liaised with Mirapro about the frame assembly. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables. * Feedthrough Adapters * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Installation stuff * Crane scale - RECEIVED * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun): * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it. * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it. * We craned the PI. There was a minor safety incident - see below. * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3). * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one. * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing. * We set up the BS gluing jigs and applied the glue. We will check the results on Monday. ==== Plan for week of 7/24 ==== Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation). * Check results of gluing. * Finish BF rebuild. * Recheck alignment of assembly frame and centering of optical table. * Install IM, suspend BS and RM. ==== Plan for week of 7/31 ==== Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation). * Weigh/trim BS/RM/IM. * Bring in rebuilt BF. Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
- We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
- Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
- We craned the PI. There was a minor safety incident - see below.
- Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
- Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
- We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
- We set up the BS gluing jigs and applied the glue. We will check the results on Monday.
Plan for week of 7/24
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
- Check results of gluing.
- Finish BF rebuild.
- Recheck alignment of assembly frame and centering of optical table.
- Install IM, suspend BS and RM.
Plan for week of 7/31
Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).
- Weigh/trim BS/RM/IM.
- Bring in rebuilt BF.
Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct