Size: 2284
Comment:
|
Size: 2134
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Mark and Fabian worked at Kamioka: * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added. * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction. * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area. * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction. * Hirata-san shipped 7 SFs and some parts to Kamioka. * Hirata-san made assembly drawings of the damper rings and cable clamps for SR. * Hirata-san liaised with Mirapro about the frame assembly. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables. * Feedthrough Adapters * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Installation stuff * Crane scale - RECEIVED * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs". * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power. * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll. * We aligned the IRM to the IM and set the OSEMs to mid-range. * We added ballast to the BF. * We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it. * We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap. * We cabled and tested the BF cap picos. * We lifted the BF and weighed and balanced it. * We installed the SF ring and brought in the SF. * We cabled the SF LVDT and did a quick test (not a full calibration). * We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol. * We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it. ==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. ==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Vacation Info ==== Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
- We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs".
- We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
- We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
- We aligned the IRM to the IM and set the OSEMs to mid-range.
- We added ballast to the BF.
- We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it.
- We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap.
- We cabled and tested the BF cap picos.
- We lifted the BF and weighed and balanced it.
- We installed the SF ring and brought in the SF.
- We cabled the SF LVDT and did a quick test (not a full calibration).
- We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol.
- We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it.
Plan for week of 8/28
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
- Fix/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Suspend BF/IRM/IM/RM/BS.
Plan for week of 9/4
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Vacation Info
Mark: TBD Mid-Oct