Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian worked at Kamioka:
   * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added.
   * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction.
   * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area.
   * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction.
   * Hirata-san shipped 7 SFs and some parts to Kamioka.
   * Hirata-san made assembly drawings of the damper rings and cable clamps for SR.
   * Hirata-san liaised with Mirapro about the frame assembly.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Installation stuff
   * Crane scale - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Enzo, Hirata-san, Yoshioka-kun):
 * We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.
 * We put the service port covers back on at the BF level of the BS tank.
 * We used the PI jacks to center the bottom of the security structure around the RM.
 * We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
 * We used the IP FRs to center the IP.
 * We set the gains on the IP LVDT driver.
 * We tested the picos and most of the steppers. The picos and IP steppers all work nicely. The PI FR and yaw steppers have jamming issues. We haven't tested the BF and SF FR steppers.
 * We debugged an issue with one of the geophones (#1) which has a DC offset. We did cable swaps and determined that the issue is internal to the geophone pod. A second geophone (#2) saturates at a suspiciously small voltage on the negative side. Again the issue is internal.
At Mitaka (Fabian, Hirata-san):
 * Fabian designed an improvement to the PI yaw stepper driver mount to stop the stepper jamming.
 * Fabian worked on a plan to measure the load capacity of the SR PIs.
 * Hirata-san did 2D drawings of the PI for the SR, and of SF2 and SRM in their vacuum chambers.
 * Hirata-san did drawings if the SR LBB damper rings and asked for quotes.
 * Hirata-san asked for quotes for SR secondary wire breakers and SR IM/IRM lock screws
 * Hirata-san ordered SR IM wire clamps.
 * Hirata-san worked on parts lists for SR cable clamps.

==== Plan for week of 10/10 ====
Kamioka: Mark, Fabian, Enzo, Ohishi-san, Kozu-kun.
Mitaka: Hirata-san
Holiday Mon 10/9, Open Day prep Fri 10/13.<<BR>>
 * Tune IP, do LVDT/stepper calibration.
 * Remove First Contact, try OL.
 * TFs, final preparation for alignment in week of 10/16.
 * SR procurement.
 * Design ballast for LBB.
 * Continue design of improved PI yaw adjustment, also improved F0 FR.

==== Plan for week of 10/16 ====
Kamioka: all but Mark, Hirata-san
Mitaka: Hirata-san
 * Work with alignment team.
 * SR procurement

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Enzo, Hirata-san, Yoshioka-kun):

  • We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.

  • We put the service port covers back on at the BF level of the BS tank.
  • We used the PI jacks to center the bottom of the security structure around the RM.
  • We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
  • We used the IP FRs to center the IP.
  • We set the gains on the IP LVDT driver.
  • We tested the picos and most of the steppers. The picos and IP steppers all work nicely. The PI FR and yaw steppers have jamming issues. We haven't tested the BF and SF FR steppers.
  • We debugged an issue with one of the geophones (#1) which has a DC offset. We did cable swaps and determined that the issue is internal to the geophone pod. A second geophone (#2) saturates at a suspiciously small voltage on the negative side. Again the issue is internal.

At Mitaka (Fabian, Hirata-san):

  • Fabian designed an improvement to the PI yaw stepper driver mount to stop the stepper jamming.
  • Fabian worked on a plan to measure the load capacity of the SR PIs.
  • Hirata-san did 2D drawings of the PI for the SR, and of SF2 and SRM in their vacuum chambers.
  • Hirata-san did drawings if the SR LBB damper rings and asked for quotes.
  • Hirata-san asked for quotes for SR secondary wire breakers and SR IM/IRM lock screws
  • Hirata-san ordered SR IM wire clamps.
  • Hirata-san worked on parts lists for SR cable clamps.

Plan for week of 10/10

Kamioka: Mark, Fabian, Enzo, Ohishi-san, Kozu-kun. Mitaka: Hirata-san Holiday Mon 10/9, Open Day prep Fri 10/13.

  • Tune IP, do LVDT/stepper calibration.
  • Remove First Contact, try OL.
  • TFs, final preparation for alignment in week of 10/16.
  • SR procurement.
  • Design ballast for LBB.
  • Continue design of improved PI yaw adjustment, also improved F0 FR.

Plan for week of 10/16

Kamioka: all but Mark, Hirata-san Mitaka: Hirata-san

  • Work with alignment team.
  • SR procurement

Vacation Info

Mark: 10/16-24