Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian worked at Kamioka:
   * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added.
   * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction.
   * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area.
   * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction.
   * Hirata-san shipped 7 SFs and some parts to Kamioka.
   * Hirata-san made assembly drawings of the damper rings and cable clamps for SR.
   * Hirata-san liaised with Mirapro about the frame assembly.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Installation stuff
   * Crane scale - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 12/25 ====
 * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
 * Shoda-san recovered the BS from the power outage on 12/25.
 * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
 * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
 * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
 * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
 * They ran cables for the SR2 steppers and OSEMs.
 * They calibrated the BF LVDT.

==== Report for week of 1/4 ====
 * Mark fixed a number of errors with the Type B screens.

==== Report for week of 1/9 ====
 * We weighed the mirror in its box (and later the empty box), and the RM.
 * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
 * We hung the SR2 and RM.
 * We assembled the bottom section of the security structure below the RM.
 * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
 * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.

==== Plan for week of 1/15 ====
 * Shoda-san at Mitaka making OSEMs.
 *
==== Plan for week of 1/22 ====

==== Plan for week of 1/22 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.

==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 12/25

  • Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
  • Shoda-san recovered the BS from the power outage on 12/25.
  • Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
  • Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
  • They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
  • They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
  • They ran cables for the SR2 steppers and OSEMs.
  • They calibrated the BF LVDT.

Report for week of 1/4

  • Mark fixed a number of errors with the Type B screens.

Report for week of 1/9

  • We weighed the mirror in its box (and later the empty box), and the RM.
  • Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
  • We hung the SR2 and RM.
  • We assembled the bottom section of the security structure below the RM.
  • Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
  • Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.

Plan for week of 1/15

  • Shoda-san at Mitaka making OSEMs.

Plan for week of 1/22

Plan for week of 1/22

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2