2284
Comment:
|
2520
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Mark and Fabian worked at Kamioka: * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added. * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction. * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area. * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction. * Hirata-san shipped 7 SFs and some parts to Kamioka. * Hirata-san made assembly drawings of the damper rings and cable clamps for SR. * Hirata-san liaised with Mirapro about the frame assembly. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables. * Feedthrough Adapters * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Installation stuff * Crane scale - RECEIVED * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Report for week of 2/26 ==== * We routed all the cables from the BF level up via the flying saucer to the SF. * Hirata-san tried filing the SF cap to improve the fit, but without much success. * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables. * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.) * We worked on recovering the IM OSEM alignment. ==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri. * Others at Kamioka. * - * '''Remove LBB temporary ballast masses from BS chamber.''' * Finish recovering IM OSEM alignment. * Calibrate SF LVDT. * Lift SF/... section and check total mass and balance. * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * Set up for rebuilding of two BFs. ==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri, then Mitaka. * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri * Others Kamioka Mon-Thu * Install boxes in SR3 and SRM racks. * Lay SR3 in-air cabling. * Continue rebuild of BFs. ==== Plan for week of 3/19 ==== * Mark at LVC meeting * All others at Mitaka * Make two sets of IM OSEMs * Make last in-air pico adapter cable * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Set up Dummy BS prism removal. ==== Plan for week of 3/26 ==== * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * F0 Prototype Blade Test * Characterize blades. * Choose best set of three. * Remove cracked blades from filter in SRM area. * Set up test weights in SRM area, first floor. * Remove floor panel in SRM area, second floor. * Install chosen blades. * Measure load capacity. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Hirata-san vacation, Mon 3/5. * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 2/26
- We routed all the cables from the BF level up via the flying saucer to the SF.
- Hirata-san tried filing the SF cap to improve the fit, but without much success.
- Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
- We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
- We worked on recovering the IM OSEM alignment.
Plan for week of 3/5
- Shoda-san at Mitaka.
- Hirata-san vacation Mon 3/5, then Kamioka
- Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri.
- Others at Kamioka.
- -
Remove LBB temporary ballast masses from BS chamber.
- Finish recovering IM OSEM alignment.
- Calibrate SF LVDT.
- Lift SF/... section and check total mass and balance.
- Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
- Set up for rebuilding of two BFs.
Plan for week of 3/12
- Shoda-san at Mitaka.
- Mark at ASJ (Chiba) Fri, then Mitaka.
- Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
- Others Kamioka Mon-Thu
- Install boxes in SR3 and SRM racks.
- Lay SR3 in-air cabling.
- Continue rebuild of BFs.
Plan for week of 3/19
- Mark at LVC meeting
- All others at Mitaka
- Make two sets of IM OSEMs
- Make last in-air pico adapter cable
- Make three in-air stepper splitter cables for SR2, SR3 and SRM.
- Set up Dummy BS prism removal.
Plan for week of 3/26
- Mark vacation.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- F0 Prototype Blade Test
- Characterize blades.
- Choose best set of three.
- Remove cracked blades from filter in SRM area.
- Set up test weights in SRM area, first floor.
- Remove floor panel in SRM area, second floor.
- Install chosen blades.
- Measure load capacity.
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Hirata-san vacation, Mon 3/5.
- Fabian vacation, 3/26-4/27 (then gone).