* Type B Past Week Summary * Mark and Fabian worked at Kamioka: * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added. * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction. * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area. * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction. * Hirata-san shipped 7 SFs and some parts to Kamioka. * Hirata-san made assembly drawings of the damper rings and cable clamps for SR. * Hirata-san liaised with Mirapro about the frame assembly. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables. * Feedthrough Adapters * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Installation stuff * Crane scale - RECEIVED * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Report for week of 3/19 ==== * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508). * Hirata-san set up the dummy BS to soak off the sapphire prisms. (In process) * Shoda-san, Hirata-san and Enzo finished the assembly of 12 OSEMs. We still need to measure the maximum output (In process) * We will send the OSEMs to Kamioka today. ==== Plan for week of 3/26 ==== * Tanioka-kun joins. * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * Lay SR3 in-air cabling (Enzo++). * Finish tuning of BFs (Hirata-san++). * SF check (Hirata-san++). * Check load capacity. * Check fit of caps. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. ==== Plan for week of 4/2 ==== * Mark at Mitaka Mon, Kamioka from Tue. * Shoda-san at Mitaka * Others at Kamioka * -- * Glue SR3 (if available) * Build 2xIM, 2xIRM (if parts available - due 3/30) ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Others at Kamioka * -- * Finish IMs and IRMs * Build 1xRM ==== Plan for week of 4/16 ==== * Start SR3 Hang? ==== Plan for week of 4/23 ==== * F0 blade prototype test ==== Plan for week of 4/30 ==== * Golden Week! ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 3/19
- Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508).
- Hirata-san set up the dummy BS to soak off the sapphire prisms. (In process)
- Shoda-san, Hirata-san and Enzo finished the assembly of 12 OSEMs. We still need to measure the maximum output (In process)
- We will send the OSEMs to Kamioka today.
Plan for week of 3/26
- Tanioka-kun joins.
- Mark vacation.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Lay SR3 in-air cabling (Enzo++).
- Finish tuning of BFs (Hirata-san++).
- SF check (Hirata-san++).
- Check load capacity.
- Check fit of caps.
- Add cable clamps to bases.
- Add cable clamps and Cu segments to caps (only if they fit well).
- Cable LVDTs and steppers.
Plan for week of 4/2
- Mark at Mitaka Mon, Kamioka from Tue.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Glue SR3 (if available)
- Build 2xIM, 2xIRM (if parts available - due 3/30)
Plan for week of 4/9
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Finish IMs and IRMs
- Build 1xRM
Plan for week of 4/16
- Start SR3 Hang?
Plan for week of 4/23
- F0 blade prototype test
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Fabian vacation, 3/26-4/27 (then gone).