Size: 2284
Comment:
|
Size: 3678
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
* Mark and Fabian worked at Kamioka: * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added. * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction. * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area. * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction. * Hirata-san shipped 7 SFs and some parts to Kamioka. * Hirata-san made assembly drawings of the damper rings and cable clamps for SR. * Hirata-san liaised with Mirapro about the frame assembly. |
* Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more. * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]). * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease. * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it. * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber. * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working. * Fabian did more pre-assembly of the RM/IM/IRM. * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags. * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank. * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well. * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18. |
Line 15: | Line 18: |
* Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. |
|
Line 20: | Line 21: |
* Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables. * Feedthrough Adapters * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Installation stuff * Crane scale - RECEIVED * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. |
* Connectors RECEIVED, cables being made. * SR machining test ongoing. |
Line 32: | Line 26: |
* Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. | * Nail-head parts - RECEIVED. |
Line 35: | Line 29: |
* To-do list during Mark's vacation * Apply grease to jacks for assembly frame (Takahashi) * Finish assembly of BS IM, RM and IRM (Fabian). * Weigh IM/RM/IRM (Fabian, Hirata) * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Mark, Shoda) * Remove glue from dummy BS face (Fabian) * Remove prism from dummy BS (Hirose, Fabian?) * Reglue flags and prisms (Tatsumi, Fabian) * Buy wire for BS and RM (Hirata) * Clean wire for BS and RM (Hirata) * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) * Apply vacuum grease to jacks for BS assembly frame (Takahashi) * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
- Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more.
Mark and Hirata-san helped Mirapro construct the assembly frame (photos).
- Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease.
- Mark and Hirata-san wiped down the assembly frame and put the clean bag on it.
- Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber.
- Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working.
- Fabian did more pre-assembly of the RM/IM/IRM.
- Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags.
- Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank.
- Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well.
Tatsumi-san ordered modifications to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18.
- Type B ongoing issues
- OSEMs
- Akutsu-san is working to get wide-mouth OSEMs
Longer cables for BF->PI and SF->PI.
- Connectors RECEIVED, cables being made.
- SR machining test ongoing.
- Lower breadboard stuff
- Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
- Breadboard springs (in manufacture, expected end of July)
- Nail-head parts - RECEIVED.
- Documents
BS Assembly Procedure E1504235, E1504235 draft
- OSEMs
- To-do list during Mark's vacation
- Apply grease to jacks for assembly frame (Takahashi)
- Finish assembly of BS IM, RM and IRM (Fabian).
- Weigh IM/RM/IRM (Fabian, Hirata)
- Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
- Analyze geophone data (Mark, Shoda)
- Remove glue from dummy BS face (Fabian)
- Remove prism from dummy BS (Hirose, Fabian?)
- Reglue flags and prisms (Tatsumi, Fabian)
- Buy wire for BS and RM (Hirata)
- Clean wire for BS and RM (Hirata)
- Do fit/function test of winches (Fabian/Hirata)
- Ship winches to Kamioka (Hirata/Fabian)
- Work on BS simulation (Fabian)
- Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
- Apply vacuum grease to jacks for BS assembly frame (Takahashi)
- Write more of payload assembly procedure (Fabian)
- Write more of main assembly procedure (Mark)
- Longer term to-do list
- Do BS Simulink model (Mark, Kokeyama)
- Do 2D drawings of SR2 parts (Hirata)
- Redesign SRx IM wire clamps for larger prisms, remachined RMs.
- Order SRM/PRM parts (Hirata/Shoda)
- Order SRx fasteners (Hirata)
- Check SR RM machining test progress (Hirata)