Differences between revisions 31 and 79 (spanning 48 versions)
Revision 31 as of 2016-06-24 13:21:11
Size: 2284
Editor: MarkBarton
Comment:
Revision 79 as of 2016-10-27 12:56:30
Size: 781
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * Mark and Fabian worked at Kamioka:
   * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added.
   * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction.
   * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area.
   * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction.
   * Hirata-san shipped 7 SFs and some parts to Kamioka.
   * Hirata-san made assembly drawings of the damper rings and cable clamps for SR.
   * Hirata-san liaised with Mirapro about the frame assembly.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Installation stuff
   * Crane scale - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
   * Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
   * Removed IM trim mass to set the average height of the keystone to the CAD value.
   * Moved IM trim mass around to set the pitch of the dummy BS.
  * Hirata-san
   * TBD.
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Fabian, Mark and Liu-kun did BS installation at Kamioka:
      • Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
      • Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
      • Removed IM trim mass to set the average height of the keystone to the CAD value.
      • Moved IM trim mass around to set the pitch of the dummy BS.
    • Hirata-san
      • TBD.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)