==== Report for week of 7/30 ====
===== SR3 =====
 * We undid the accidental misalignment of the SR3. We also switched off the BF GAS offset we had been using, let the IM rise until near zero on the BF LVDT, and adjusted the IM vertical OSEMs back to mid-range.
 * We closed control loops for the SR3 GAS filters.
 * Terrence set up the LED and TILT QPD for the final OL, and did a new calibration.
===== SR2 =====
 * We installed the SR2 SF damper magnet ring but found that the magnet pattern didn't match the Cu segments due to a different in the caps between SR3 and SR2. We raised the ring but left it suspended, clamped the template to the underside and rearranged the magnets.
 * We did a vertical height budget of the SR2. It turns out to have a very similar issue to the SR3: the chain is about 5 mm longer than the CAD, with about 3 mm of that between the SF and BF. We decided to do the same fix and operate with the F0 keystone 5 mm higher. We chose an total amount of ballast to give that keystone height and secured most of it to the SF, keeping a reserve for cables and the yaw stepper.
 * We routed most (all?) of the SF/... cabling up to the PI.

===== SRM =====
 * We moved the SRM assembly frame into its final position, reset it to the initial configuration, double-checked the heights of the crossbars, and lowered the optical table by 3 mm (to give margin for the optic to rise during hanging, which we had kept forgetting to do). We cleaned it up with the airgun and wet-wipes. We installed the IM ring and IM.
 * We assembled the SRM metal mass. Hirata-san made a jig from a plate with 4 screws which could safely hold the delicate front Sol-Black-coated ring upside down while the rest of the components were mounted on it.
 * We moved the metal mass to the mirror box and added the prisms and magnet standoffs. We applied the EP30 on Friday morning, but probably won't be able to check the result until after Obon.

==== Plan for week of 8/13 ====
 * KAGRA closed Mon, Tue.
 * Mark on vacation Mon-Thu, then Mitaka on Friday.
 * Enzo, Fabian, Terrence, Panwei, Rikako at Kamioka Wed-Fri.
 * Hirata-san on vacation all week.
 * Fujii-kun to help part-time with crane work and/or the IP tuning.
 * Diagonalization of new OL.
 * TFs with new OL.
 * Test of SF damper ring.
 * Controls work.
 * Tune SR3 IP.

==== Plan for week of 8/20 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Thu, then f2f.
 * Kozu-kun works at Mozumi Mon.

===== SR3 =====
 * Hook LBB, add ballast mass.
 * Tune IP.

===== SR2 =====
 * Adjust ballast/trim mass, with reserve for yaw stepper.
 * Cable/test PI items (LVDTs, steppers, geophones).
 * Set damper height.
 * Add arc weights, adjust IP.
 * Stage LBB damper rings in tank.
==== Report for week of 11/12 ====
 * BS
  * Kozu-kun noticed the BS OL was out of range, and Fabian and Fujii-kun investigated. It turns out that the temperature has risen by over 2°C, so all the GAS filters have sagged and several stages are touching. Miyoki-san and Furuta-san are looking at what can be done.
 * SRM
  * We did the vertical height survey and found that as with SR2 and SR3, the chain is longer than the CAD, this time by ≈7 mm, and again mostly between the SF and BF.
  * The final SRM small glass mirror became available, so we had Hirose-san ship it to us so we can install it while the suspension is still on the assembly frame. Hirata-san ordered shims to make up the new recommended thickness of 1.4 mm and a micrometer to check the combination, which should arrive on Monday 11/26.
 * SR2
  *
Line 49: Line 15:
===== SRM =====
 * Check gluing result - redo if necessary.
 * Assemble RM.
 * Add IM ballast masses (we forgot this before).
 * Get parts from AOL and set up new pitch-setting OL.
 * Hang metal mass.
 * Hang RM.
Line 62: Line 20:
==== Vacation Info ====
 * Mark: 8/13-16.
 * Hirata-san: 8/13-17
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Plan for week of 11/19 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo and Fabian at Kamioka Mon-Thu.
 * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
===== SRM =====
 * Go/no-go test of all electronics items, especially SF/... section.
 * Finish vertical height check and adjust SF trim mass as required.
 * Unlock IP and center roughly.
 * Check/adjust alignment of SS.
 * Calibrate IP LVDTs.
 * Add arc weights and geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Disconnect cables at feedthroughs, lock suspension.
 * Crane into tank.
===== SR2 =====
 * Assist MIF team with pico cables and LBB breadboard ballast.
 * Install SR2 OL pillar and shelf (with AOL supervision)?

==== Plan for week of 11/26 ====
 * Move SRM in-air cables over to tank.
 * Remove First Contact.
 * Unlock and align SRM.
 * Hook and roughly ballast LBB.

==== Plan for week of 12/3 ====
 * f2f Meeting at NAOJ - no Kamioka work.

==== Vacation/Event Info ====
 * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 11/12

  • BS
    • Kozu-kun noticed the BS OL was out of range, and Fabian and Fujii-kun investigated. It turns out that the temperature has risen by over 2°C, so all the GAS filters have sagged and several stages are touching. Miyoki-san and Furuta-san are looking at what can be done.
  • SRM
    • We did the vertical height survey and found that as with SR2 and SR3, the chain is longer than the CAD, this time by ≈7 mm, and again mostly between the SF and BF.
    • The final SRM small glass mirror became available, so we had Hirose-san ship it to us so we can install it while the suspension is still on the assembly frame. Hirata-san ordered shims to make up the new recommended thickness of 1.4 mm and a micrometer to check the combination, which should arrive on Monday 11/26.
  • SR2

To-Do Lists, Schedule

Plan for week of 11/19

  • Friday 11/23 is Labor Thanksgiving Day.
  • Mark, Enzo and Fabian at Kamioka Mon-Thu.
  • Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).

SRM
  • Go/no-go test of all electronics items, especially SF/... section.
  • Finish vertical height check and adjust SF trim mass as required.
  • Unlock IP and center roughly.
  • Check/adjust alignment of SS.
  • Calibrate IP LVDTs.
  • Add arc weights and geophones.
  • Improve centering/tuning of IP and SS alignment.
  • Disconnect cables at feedthroughs, lock suspension.
  • Crane into tank.

SR2
  • Assist MIF team with pico cables and LBB breadboard ballast.
  • Install SR2 OL pillar and shelf (with AOL supervision)?

Plan for week of 11/26

  • Move SRM in-air cables over to tank.
  • Remove First Contact.
  • Unlock and align SRM.
  • Hook and roughly ballast LBB.

Plan for week of 12/3

  • f2f Meeting at NAOJ - no Kamioka work.

Vacation/Event Info

  • Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).