Differences between revisions 314 and 400 (spanning 86 versions)
Revision 314 as of 2018-08-29 15:15:51
Size: 4834
Editor: MarkBarton
Comment:
Revision 400 as of 2019-03-08 14:05:56
Size: 1842
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
Line 6: Line 5:
==== Report for week of 8/13 ====
 * KAGRA was closed Mon/Tue 8/13-14 due to O-Bon.
 * Enzo and team debugged an issue with height of the SR3 keystone coupling to yaw of the payload as measured by the OL. We suspect a ferromagnetic item on the SF damper, but we're not sure.
==== Report for the week of 3/4 ====
 * On Monday, Mark helped Aso-san with PR3, and Monday, Tuesday and Wednesday, Fabian helped Fujii-kun with PRM.
 * Mark and Terrence attempted to offload some BS IM/IRM yaw adjustments that had been done by Enomoto-san last Friday. They rezeroed the OL and then opened the tank lid and did a compensating adjustment to the F0 yaw stepper, then undid the IM/IRM yaw with the pico. However this did not have the desired effect, probably because the buoyancy correction had not been cancelled when Enomoto-san was working and the BF keystone was very high, with the IM-V OSEMs way too far in and possibly touching. We did our best to back out all the adjustments but the roll TFs were still messy and there were signs that the IM was not free in yaw (the IM/IRM Y varied oppositely to IP Y, indicating that the IMR was free and the IM wasn't). We ended up deciding to have Mirapro remove the ducts on the ±X sides of the tank so we could go in and inspect.
 * Terrence tuned the SR3 LEN OL to be free of yaw cross-coupling.
 * Terrence and Enzo did a full set of filters and a Guardian for SR2 and SR3.
 * Terrence did health checks on SR2 and SR3.
 * Enzo measured mode Qs on SR2.
Line 10: Line 13:
==== Report for week of 8/20 ====
===== SR3 =====
 * Hatoya-san and Enzo gathered date for a study of yaw mode Q damping time as a study of damper ring height.
===== SR2 =====
 * We continued with cabling work.
 * We configured the second pico driver and connected it.
 * We assembled the LBB damper rings in the tank, craned them to near the top and hooked them. While the tank was open we also set the jacks below the mushroom that will support the suspension to nominal height.
==== Plan for week of 3/11 ====
 * Mark at Kamioka full week.
 * Enzo at Kamioka Mon, Tue, then JPS.
 * Hirata-san at Kamioka from Monday lunchtime through Friday.
 * Fix BS.
 * Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
 * Continue monitoring SRM yaw drift.
 * More mode Q measurements.
 * Work on Type B paper.
Line 18: Line 23:
===== SRM =====
 * We reserved and configured two pico drivers.
 * We checked the prism gluing and all the jigs came away successfully.
 * Fabian assembled the RM.
 * Hirata-san added ballast masses to the IM and we weighed it, as well as the RM and the optic in the mirror box.
 * We suspended the optic and RM.
Line 25: Line 24:
==== Report for week of 8/27 ====
===== SR3 =====
 * We did an inventory of arc weights to see if we had enough for SRM and found that we had only enough for a basic allocation for all of type B (172 kg for BS and 103.2 kg per SR) with almost no spare for tuning.
 * Using SR3, we did a quick study of the IP frequency as a function of the number of arc weights, to see how much more we might need. 3 pairs of small arc weights (10 mm thick, 4.53 kg each) brought the frequency below 0.1 Hz, 4 pairs made it unstable. If SR3 is typical we would need about 27 kg extra per suspension.
 * After the IP study, we left three pairs of 10 mm arc weights installed on the IP for more investigation with the digital system (instead of a stopwatch).

===== SR2 =====
 * We finished routing the in-vacuum cables, and connected everything through to the rack for final testing.
 * We brought a basic 103.2 kg set of arc weights (3 large (38 mm) and 6 medium (19 mm)) into the SR2 cleanbooth.

===== SRM =====
 * Panwei calibrated 6 OSEMs to be used on the IM.
 * We brought in all the remaining arc weights from the pallet into the SRM cleanbooth, and Hirata-san cleaned up 1 large arc weight and 3 mediums left over from the BS that complete a basic set of 103.2 kg, plus about 5 kg spare. (However 27 kg of these are on loan to SR3.)
 * We assembled and installed the bottom section of the security structure under the optic and RM.
 * We set up a new OL for setting the pitch. We found the reflection off the AR surface was much weaker than for SR2 and SR3, but fortunately the HR surface is almost flat (ROC≈300 m) so we were able to use the HR reflection instead.
 * ''We set the pitch of the SRM and RM and tightened the wire clamps.''

==== Plan for week of 9/3 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Mon-Fri.
 * (Mark possible trip to LIGO Hanford - TBD.)
===== SR2 =====
 * Crane in SR2.
 * Move SR2 in-air cables.
 * Remove First Contact
 * Unlock and realign payload.

===== SRM =====
 *
===== Etc =====
 * Prepare for scheduled power outage on 9/10.

==== Plan for week of 9/10 ====
 * Monday 9/10 is scheduled power outage.
 * Mark, Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
 * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.
 * Recover from power outage.

==== Plan for week of 9/17 ====
 * Monday 9/17 is holiday (Respect for the Aged Day).
 * Enzo on vacation.
 * Mark, Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.

==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.

===== SR3 =====
 * Hook LBB, add ballast mass.
 * Tune IP.

===== SR2 =====
 * Adjust ballast/trim mass, with reserve for yaw stepper.
 * Cable/test PI items (LVDTs, steppers, geophones).
 * Set damper height.
 * Add arc weights, adjust IP.
 * Stage LBB damper rings in tank.
 
===== SRM =====
 * Check gluing result - redo if necessary.
 * Assemble RM.
 * Add IM ballast masses (we forgot this before).
 * Get parts from AOL and set up new pitch-setting OL.
 * Hang metal mass.
 * Hang RM.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark: 8/13-16.
 * Hirata-san: 8/13-17
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Vacation/Travel Info ====
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/4

  • On Monday, Mark helped Aso-san with PR3, and Monday, Tuesday and Wednesday, Fabian helped Fujii-kun with PRM.
  • Mark and Terrence attempted to offload some BS IM/IRM yaw adjustments that had been done by Enomoto-san last Friday. They rezeroed the OL and then opened the tank lid and did a compensating adjustment to the F0 yaw stepper, then undid the IM/IRM yaw with the pico. However this did not have the desired effect, probably because the buoyancy correction had not been cancelled when Enomoto-san was working and the BF keystone was very high, with the IM-V OSEMs way too far in and possibly touching. We did our best to back out all the adjustments but the roll TFs were still messy and there were signs that the IM was not free in yaw (the IM/IRM Y varied oppositely to IP Y, indicating that the IMR was free and the IM wasn't). We ended up deciding to have Mirapro remove the ducts on the ±X sides of the tank so we could go in and inspect.
  • Terrence tuned the SR3 LEN OL to be free of yaw cross-coupling.
  • Terrence and Enzo did a full set of filters and a Guardian for SR2 and SR3.
  • Terrence did health checks on SR2 and SR3.
  • Enzo measured mode Qs on SR2.

Plan for week of 3/11

  • Mark at Kamioka full week.
  • Enzo at Kamioka Mon, Tue, then JPS.
  • Hirata-san at Kamioka from Monday lunchtime through Friday.
  • Fix BS.
  • Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
  • Continue monitoring SRM yaw drift.
  • More mode Q measurements.
  • Work on Type B paper.

Vacation/Travel Info

  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)