==== Report for week of 8/13 ====
 * KAGRA was closed Mon/Tue 8/13-14 due to Obon.
 * Enzo and team investigated an issue with the height of the SR3 keystone coupling to yaw of the payload as measured by the OL. We suspect a ferromagnetic item on the SF damper, but we're not sure.

==== Report for week of 8/20 ====
===== SR3 =====
 * Hatoya-san and Enzo gathered date for a study of yaw mode Q damping time as a study of damper ring height.
==== Report for week of 10/15 ====
===== SRM =====
 * We received the fourth feedthrough we had been waiting for and installed it on the AF.
 * Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model.
 * Fabian and Enzo connected up the Sat Amps.
 * Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange.
 * Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough.
 * Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade.
 * Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2.
 * We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS.
 * Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT.
 * Enzo made a new batch of feedthrough adapters.
Line 14: Line 19:
 * We continued with cabling work.
 * We configured a second pico driver and connected it.
 * We assembled the LBB damper rings in the tank, craned them to near the top and hooked them. While the tank was open we also set to nominal height the jacks below the mushroom that will support the suspension.
 * We finalized the geophone cabling and reinstalled the geophones.
 * We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz.
 * Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29.
==== Plan for week of 10/22 ====
 * Friday is NAOJ Open Day Prep - no Kamioka work.
 * Mark and Fabian at Kamioka Mon-Thu.
 * Enzo and Hirata-san at Kamioka Tue-Thu.
===== SR2 =====
 * Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
 * Continue shakedown.
 * Gather parts for the OL (with help from Simon).
Line 19: Line 31:
 * We reserved and configured two pico drivers.
 * We checked the prism gluing - all the jigs came away successfully.
 * Fabian assembled the RM.
 * Hirata-san added ballast masses to the IM and we weighed it, as well as the RM and the optic in the mirror box.
 * We suspended the optic and RM.

==== Report for week of 8/27 ====
===== Arc weights =====
 * We did an inventory of arc weights to see if we had enough for SRM. Including the weights on the pallet, some weights left over from the BS, and the weights already on SR3, we have enough for a basic allocation for all of type B (172 kg for BS and 103.2 kg per SR) but with only 5 kg spare for tuning.
 * We brought all the arc weights into the cleanrooms and divided them up for the SRs.
 * Hirata-san cleaned up 1 large arc weight and 3 mediums left over from the BS that got wet during the heavy rain.

===== SR3 =====
 * Using SR3, we did a quick study of the IP frequency as a function of the number of arc weights, to see how much more we might need. 3 pairs of small arc weights (10 mm thick, 4.53 kg each) brought the frequency below 0.1 Hz, 4 pairs made it unstable. If SR3 is typical we would need about 27 kg extra per suspension.
 * After the IP study, we left three pairs of 10 mm arc weights installed on the IP and measured the frequencies with the digital system (instead of a stopwatch). Both L and T were around 0.08 Hz, which is good.
 * We unclamped the LBB damper rings, installed the rods down to the LBB and hooked the LBB. Mirapro then moved the SR2-SR3 duct to give more space at the SR2 end.
 * Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified.
 * Suspend/weigh/balance the BF/... section.
 * Build up the AF and SS to the SF level.
 * Install the SF.
==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
Line 37: Line 38:
 * We finished routing the in-vacuum cables, and started connecting everything through to the rack for final testing.
 * Set up OL.
Line 40: Line 40:
 * Panwei calibrated 6 OSEMs to be used on the IM. Two OSEMs have a long-term drift issue and may need repair. He took some long time series to characterize the drift.
 * We assembled and installed the bottom section of the security structure under the optic and RM.
 * We set up a new OL for setting the pitch. We found the reflection off the AR surface was much weaker than for SR2 and SR3, but fortunately the HR surface is almost flat (ROC≈300 m) and the reflection is weak but better so we were able to use the HR side instead.

==== Plan for week of 9/3 ====
 * Mark, Fabian, Kozu-kun, Panwei at Kamioka Mon-Fri.
 * Enzo at Kamioka Mon-Thu.
 * Hirata-san at Kamioka Tue-Fri.
 * Major crane inspection Mon/Wed mornings using space where Type B work table is. SR2 craning will have to fit in around it.
 
===== SR2 (highest priority) =====
 * Connect cables through to rack.
 * Check/tweak alignment of chain.
 * Add arc weights (103 kg) and geophones - check IP.
 * Go/no-go test of electronics.
 * Crane in SR2.

===== SRM (lower priority) =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
===== Etc =====
 * Inspect all crane slots (SR, BS, PR) and check for missing bars and curtains.
 * Prepare for scheduled power outage on 9/10.

==== Plan for week of 9/10 ====
 * Monday 9/10 is scheduled power outage.
 * Mark in US (job interview).
 * Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
 * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.
===== Etc =====
 * Recover from power outage.
===== SRM (highest priority) =====
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.
 * Suspend IM and tweak height/balance.
 
==== Plan for week of 9/17 ====
 * Monday 9/17 is holiday (Respect for the Aged Day).
 * Enzo on vacation.
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
===== SRM (highest priority) =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.
===== SR2 (lower priority) =====
 * Move SR2 in-air cables.
 * Remove First Contact.
 * Unlock and realign suspension.

==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
 * Continue assembly.
Line 98: Line 46:
==== Vacation Info ====
 * Mark: 9/10-14 (job interview in US).
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/15

SRM
  • We received the fourth feedthrough we had been waiting for and installed it on the AF.
  • Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model.
  • Fabian and Enzo connected up the Sat Amps.
  • Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange.
  • Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough.

  • Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade.
  • Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2.
  • We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS.
  • Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT.
  • Enzo made a new batch of feedthrough adapters.

SR2
  • We finalized the geophone cabling and reinstalled the geophones.
  • We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz.
  • Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29.

Plan for week of 10/22

  • Friday is NAOJ Open Day Prep - no Kamioka work.
  • Mark and Fabian at Kamioka Mon-Thu.
  • Enzo and Hirata-san at Kamioka Tue-Thu.

SR2
  • Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
  • Continue shakedown.
  • Gather parts for the OL (with help from Simon).

SRM
  • Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified.
  • Suspend/weigh/balance the BF/... section.
  • Build up the AF and SS to the SF level.
  • Install the SF.

Plan for week of 10/29

  • Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.

SR2
  • Set up OL.

SRM
  • Continue assembly.

To-Do Lists, Schedule

Vacation/Visitor Info

  • Terrence: 10/29-11/2 at Kamioka.