Line 6: | Line 6: |
==== Report for week of 9/10 ==== * We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank. * We checked all the motors, like: *the IM picos, BF picos. * We checked the BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod). * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains. * We reset the IP FRs to midrange. * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure. * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs. * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage. === Type B (Mark) === ==== Report for week of 9/3 ==== * We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected. * We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables. * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains. * We reset the IP FRs to midrange. * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure. * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs. * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage. ==== Plan for week of 9/10 ==== * Monday 9/10 is scheduled power outage. * Mark in US (job interview). * Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri. * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation. ===== Etc ===== * Recover from power outage. ===== SR2 ===== * Calibrate F0 LVDTs. * Calibrate IP LVDTs. * Cable geophones and any other remaining PI items. * Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables). * Do basic go/no-go test of electronic items. * Check SF keystone height and offload with FR as necessary. * Adjust ballast/trim mass of SF, with reserve for yaw stepper. * Set SF damper magnet ring height. * Check/tweak optic pitch. * TFs. ==== Plan for week of 9/17 ==== * Monday 9/17 is holiday (Respect for the Aged Day). * Enzo on vacation. * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. ===== SR2 ===== * Crane SR2 into tank. * Move SR2 in-air cables. * Remove First Contact. * Unlock and realign suspension. ===== SRM ===== * Set pitch of SRM and RM, tighten clamps, remove winch system. * Weigh IM/... section. * Build up SS to BF level. * Add BF. ==== Plan for week of 9/24 ==== * Monday 9/24 is holiday (Autumn Equinox). * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. * Suspend IM and tweak height/balance. ===== SRM ===== * Cable/test BF. * Install IRM. * Install/cable/test IM OSEMs. |
==== Report for week of 10/29 ==== * SRM * Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half. * Fabian and Hirata-san finished the in-vacuum cabling. * Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling. * We're now ready for final tests of the SF/... items and initial tests of the PI items. * Enzo and Fujii-kun built three geophones for SRM. * Mark worked on the height budget. * SR2 * Enzo experimented with [[http://www2.mpq.mpg.de/~ros/geo600_docu/soft/liso/manual.pdf|LISO]] (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.) |
Line 74: | Line 22: |
==== Vacation Info ==== * Mark: 9/10-14 (job interview in US). * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
==== Plan for week of 11/11 ==== * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri. ===== SRM ===== * Main sequence ==== Plan for week of 11/19 ==== * Friday 11/23 is Labor Thanksgiving Day. * Mark, Enzo and Fabian at Kamioka Mon-Thu. * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting). ===== SRM ===== * Go/no-go test of all electronics items, especially SF/... section. * Finish vertical height check and adjust SF trim mass as required. * Unlock IP and center roughly. * Check/adjust alignment of SS. * Calibrate IP LVDTs. * Add arc weights and geophones. * Improve centering/tuning of IP and SS alignment. * Disconnect cables at feedthroughs, lock suspension. * Crane into tank. ===== SR2 ===== * Assist MIF team with pico cables and LBB breadboard ballast. * Install SR2 OL pillar and shelf (with AOL supervision)? ==== Plan for week of 11/26 ==== * Move SRM in-air cables over to tank. * Remove First Contact. * Unlock and align SRM. * Hook and roughly ballast LBB. ==== Plan for week of 12/3 ==== * f2f Meeting at NAOJ - no Kamioka work. ==== Vacation/Event Info ==== * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 10/29
- SRM
- Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
- Fabian and Hirata-san finished the in-vacuum cabling.
- Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
- We're now ready for final tests of the SF/... items and initial tests of the PI items.
- Enzo and Fujii-kun built three geophones for SRM.
- Mark worked on the height budget.
- SR2
Enzo experimented with LISO (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)
To-Do Lists, Schedule
Plan for week of 11/11
- Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
SRM
- Main sequence
Plan for week of 11/19
- Friday 11/23 is Labor Thanksgiving Day.
- Mark, Enzo and Fabian at Kamioka Mon-Thu.
- Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
SRM
- Go/no-go test of all electronics items, especially SF/... section.
- Finish vertical height check and adjust SF trim mass as required.
- Unlock IP and center roughly.
- Check/adjust alignment of SS.
- Calibrate IP LVDTs.
- Add arc weights and geophones.
- Improve centering/tuning of IP and SS alignment.
- Disconnect cables at feedthroughs, lock suspension.
- Crane into tank.
SR2
- Assist MIF team with pico cables and LBB breadboard ballast.
- Install SR2 OL pillar and shelf (with AOL supervision)?
Plan for week of 11/26
- Move SRM in-air cables over to tank.
- Remove First Contact.
- Unlock and align SRM.
- Hook and roughly ballast LBB.
Plan for week of 12/3
- f2f Meeting at NAOJ - no Kamioka work.
Vacation/Event Info
- Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).