==== Report for week of 9/10 ====
 * We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
 * We checked all the motors:
       * IM picos, BF picos.
       * BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
       * IP Steppers (Horizontal fishing rods).
 * We use the Steppers to set to nominal height the BF and SF, but for the SF we culd not move it too much and it is still too low.
 * We set up the temporary oplev for SR2.
 * We checked the pitch of the optics. The current pitch is:
 * We tried to check the TM actuators but there is a problem with the MEDM screens that we need to fix next week.
 * We measured TFs of the GAS filters and the 6 DoF of the IM. It seems to be healthy.
 * We set the F0 stepper to middle position.
 * ...

=== Type B (Mark) ===
==== Report for week of 9/3 ====
 * We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
 * We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
 * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
 * We reset the IP FRs to midrange.
 * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
 * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
 * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

==== Plan for week of 9/10 ====
 * Monday 9/10 is scheduled power outage.
 * Mark in US (job interview).
 * Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
 * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.
===== Etc =====
 * Recover from power outage.
===== SR2 =====
 * Calibrate F0 LVDTs.
 * Calibrate IP LVDTs.
 * Cable geophones and any other remaining PI items.
 * Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
 * Do basic go/no-go test of electronic items.
 * Check SF keystone height and offload with FR as necessary.
 * Adjust ballast/trim mass of SF, with reserve for yaw stepper.
 * Set SF damper magnet ring height.
 * Check/tweak optic pitch.
 * TFs.
==== Plan for week of 9/17 ====
 * Monday 9/17 is holiday (Respect for the Aged Day).
 * Enzo on vacation.
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
===== SR2 =====
 * Crane SR2 into tank.
 * Move SR2 in-air cables.
 * Remove First Contact.
 * Unlock and realign suspension.
===== SRM =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.

==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
 * Suspend IM and tweak height/balance.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.
==== Report for week of 10/29 ====
 * SRM
  * Enzo repaired some broken cables and made some long cables from shorter ones. We ultrasonically cleaned them at Toyama U, with help from Yamamoto-san. Enzo then reinforced the joins with EP30 9two cables) or heat shrink (one cable).
  * Hirata-san finished tuning the PI. It is now complete except for some PEEK cable clamp pieces which are expected next Monday.
  * Hirata-san wiped writing off the F0 and SF yoke magnets, and off the PI.
  * Hirata-san found we were running out of magnets and ordered more - we have almost enough (short by one) for the SF damper, but will need more for the LBB damper.
  * Fabian cabled and tested the BF cap picos.
  * Fabian routed all the cables up to the underside of the SF. He cabled and tested the SF LVDT and stepper.
  * We added the SF cap and weighed the SF/... section. We appear to have a good amount of load capacity margin.
  * We put receptacles and magnets on the SF damper ring.
 * SR2
  * We opened the SR2 tank, borrowed a geophone for Fujii-kun's geophone test, and left the IP locked.
  * We gathered parts for the SR2 OL. We believe we have all the pieces we need except for an LED (the one originally allocated to SR2 is currently being used for pitch setting on SRM and we may need to steal it back). Akutsu-san wants to supervise us setting up the LED and receiver supports, so that will happen next week.
 * SR3
  * Terrence visited for another week and made more measurements on the OL.
 * BS
  * We searched for the dog clamps that we had borrowed from AOS to serve as ballast for the BS LBB and returned them to the AOS pallet.
 * Electronics
  * Enzo analyzed the LPCD and worked out the resistors we need to get the drive current recommended for the IM-V OSEMs by Shoda-san. We brought back three LPCDs for modification.
Line 77: Line 30:
==== Vacation Info ====
 * Mark: 9/10-14 (job interview in US).
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Plan for week of 11/4 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence
  * Add magnets to SF damper.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.

==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.

==== Plan for week of 11/18 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Crane into tank.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/29

  • SRM
    • Enzo repaired some broken cables and made some long cables from shorter ones. We ultrasonically cleaned them at Toyama U, with help from Yamamoto-san. Enzo then reinforced the joins with EP30 9two cables) or heat shrink (one cable).
    • Hirata-san finished tuning the PI. It is now complete except for some PEEK cable clamp pieces which are expected next Monday.
    • Hirata-san wiped writing off the F0 and SF yoke magnets, and off the PI.
    • Hirata-san found we were running out of magnets and ordered more - we have almost enough (short by one) for the SF damper, but will need more for the LBB damper.
    • Fabian cabled and tested the BF cap picos.
    • Fabian routed all the cables up to the underside of the SF. He cabled and tested the SF LVDT and stepper.
    • We added the SF cap and weighed the SF/... section. We appear to have a good amount of load capacity margin.
    • We put receptacles and magnets on the SF damper ring.
  • SR2
    • We opened the SR2 tank, borrowed a geophone for Fujii-kun's geophone test, and left the IP locked.
    • We gathered parts for the SR2 OL. We believe we have all the pieces we need except for an LED (the one originally allocated to SR2 is currently being used for pitch setting on SRM and we may need to steal it back). Akutsu-san wants to supervise us setting up the LED and receiver supports, so that will happen next week.
  • SR3
    • Terrence visited for another week and made more measurements on the OL.
  • BS
    • We searched for the dog clamps that we had borrowed from AOS to serve as ballast for the BS LBB and returned them to the AOS pallet.
  • Electronics
    • Enzo analyzed the LPCD and worked out the resistors we need to get the drive current recommended for the IM-V OSEMs by Shoda-san. We brought back three LPCDs for modification.

To-Do Lists, Schedule

Plan for week of 11/4

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Main sequence
    • Add magnets to SF damper.
    • Install #353 poles
    • Move NB-03 jacks down.
    • Crane PI into AF.
    • Install F0-SF rod (#331) and flying saucer.
    • Route SF/... cables up to underside of F0.
    • Do vertical height budget.
    • Adjust SF trim mass for balance and keystone height.
    • Cable/test IP LVDTs.
    • Cable/test IP FRs.
  • LBB
    • Move KOACH filters
    • Put LBB damper rings in tank.
    • Set tank jacks to nominal height.

Plan for week of 11/11

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.

Plan for week of 11/18

  • Friday 11/23 is Labor Thanksgiving Day.
  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.
  • Crane into tank.