==== Report for week of 9/10 ====
 * We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
 * We checked all the motors:
       * IM picos, BF picos.
       * BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
       * IP Steppers (Horizontal fishing rods).
 * We use the Steppers to set to nominal height the BF and SF, but for the SF we culd not move it too much and it is still too low.
 * We set up the temporary oplev for SR2.
 * We checked the pitch of the optics. The current pitch is:
 * We tried to check the TM actuators but there is a problem with the MEDM screens that we need to fix next week.
 * We measured TFs of the GAS filters and the 6 DoF of the IM. It seems to be healthy.
 * We set the F0 stepper to middle position.
 * ...
==== Report for the week of 4/8 ====
 * Support of Type Bp
  * Mark made lots of Guardian improvements:
   * Used Guardian's timer functionality to drastically reduce the number of notifications during ramping.
   * Added new requestable states DCCTRL_ONLY and NEUTRAL (and associated transitional states) to facilitate testing.
   * Tidied up the code to use tabs consistently throughout for indentation.
   * Disabled the test for the IM-H coil driver WD (to work around the fact that only the relay in the chassis has been disabled, not the WD signals going to the BIO).
 * We opened the BS tank lid and offloaded a large IM-Y offset to F0-Y with manual adjustment of the broken yaw mechanism).
 * We opened the SR2 side doors and adjusted the V1 OSEM to mid-range.
 * Mark offloaded a large SR2 IM-Y offset to F0-Y.
 * Mark did health checks for BS, SR2 and SR3.
 * Fabian offloaded yaw from SRM and did the SRM health check.
 * Fabian updated the Python code for the stepper driver MEDM screen to reflect that two stepper drivers have different mappings to work around dead channels.
 * Fabian monitored pumpdown on Friday afternoon and will continue on Saturday.
Line 20: Line 20:
=== Type B (Mark) ===
==== Report for week of 9/3 ====
 * We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
 * We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
 * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
 * We reset the IP FRs to midrange.
 * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
 * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
 * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.
==== Plan for week of 4/15 ====
 * Mark, Hirata-san at Kamioka Tue-Thu.
 * Fabian at Kamioka Mon-Wed.
 * All at f2f Meeting 4/19-21.
 * Post-pumpdown health checks.
 * Teach Hirata-san about the computer systems and control theory.
 * Work with Lucia to do blending of the IP LVDTs and geophones.
 * More Guardian improvements.
  * Update vistools.py (formerly LIGO sustools.py) for Type B and KAGRA, and have the TYPEB.py Guardian use it where appropriate.
  * Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
 * Work on Type B paper.
 * Tidy up.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.
Line 30: Line 35:
==== Plan for week of 9/10 ====
 * Monday 9/10 is scheduled power outage.
 * Mark in US (job interview).
 * Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
 * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.
===== Etc =====
 * Recover from power outage.
===== SR2 =====
 * Calibrate F0 LVDTs.
 * Calibrate IP LVDTs.
 * Cable geophones and any other remaining PI items.
 * Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
 * Do basic go/no-go test of electronic items.
 * Check SF keystone height and offload with FR as necessary.
 * Adjust ballast/trim mass of SF, with reserve for yaw stepper.
 * Set SF damper magnet ring height.
 * Check/tweak optic pitch.
 * TFs.
==== Plan for week of 9/17 ====
 * Monday 9/17 is holiday (Respect for the Aged Day).
 * Enzo on vacation.
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
===== SR2 =====
 * Crane SR2 into tank.
 * Move SR2 in-air cables.
 * Remove First Contact.
 * Unlock and realign suspension.
===== SRM =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.

==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
 * Suspend IM and tweak height/balance.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark: 9/10-14 (job interview in US).
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
==== Vacation/Travel Info ====
 * Mark at Mitaka 4/15.
 * f2f 4/19 (Friday), 4/20, 4/21.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's US vacation from 5/22 to 6/11.
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 4/8

  • Support of Type Bp
    • Mark made lots of Guardian improvements:
      • Used Guardian's timer functionality to drastically reduce the number of notifications during ramping.
      • Added new requestable states DCCTRL_ONLY and NEUTRAL (and associated transitional states) to facilitate testing.
      • Tidied up the code to use tabs consistently throughout for indentation.
      • Disabled the test for the IM-H coil driver WD (to work around the fact that only the relay in the chassis has been disabled, not the WD signals going to the BIO).
  • We opened the BS tank lid and offloaded a large IM-Y offset to F0-Y with manual adjustment of the broken yaw mechanism).
  • We opened the SR2 side doors and adjusted the V1 OSEM to mid-range.
  • Mark offloaded a large SR2 IM-Y offset to F0-Y.
  • Mark did health checks for BS, SR2 and SR3.
  • Fabian offloaded yaw from SRM and did the SRM health check.
  • Fabian updated the Python code for the stepper driver MEDM screen to reflect that two stepper drivers have different mappings to work around dead channels.
  • Fabian monitored pumpdown on Friday afternoon and will continue on Saturday.

Plan for week of 4/15

  • Mark, Hirata-san at Kamioka Tue-Thu.
  • Fabian at Kamioka Mon-Wed.
  • All at f2f Meeting 4/19-21.
  • Post-pumpdown health checks.
  • Teach Hirata-san about the computer systems and control theory.
  • Work with Lucia to do blending of the IP LVDTs and geophones.
  • More Guardian improvements.
    • Update vistools.py (formerly LIGO sustools.py) for Type B and KAGRA, and have the TYPEB.py Guardian use it where appropriate.
    • Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
  • Work on Type B paper.
  • Tidy up.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.

Vacation/Travel Info

  • Mark at Mitaka 4/15.
  • f2f 4/19 (Friday), 4/20, 4/21.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's US vacation from 5/22 to 6/11.
  • Mark's final day 6/28.