==== Report for week of 9/17 ====
 * Monday 9/17 was holiday.
 * We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico.
 * We set the SF damper gap to 6 mm.
 * We set the SR2 pitch with the optic lever, aligned the IRM and set all the OSEMs to have good clearance and midrange output.
 * We locked the SR2 suspension (except for the SF) and craned it into the tank.
 * We moved the vacuum feedthroughs over to the tank.
 * With help from Ohishi-san, we removed the First Contact from SR2.
 * Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc.
 * Mark did an inventory of some thin arc weights and finalized the number to order (8*38 mm + 9*10 mm).
 * Panwei copied control filters over from the SR3.
 
==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
==== Report for week of 10/22 ====
===== SRM =====
 * We borrowed the TM HPCDs from SR2 and SR3 so that SRM had HPCDs for IM-H, IM-V and GAS.
 * Fabian adjusted the last two OSEMs (IM-H2 and H3).
 * We closed the BF and weighed the BF/... section.
 * Fabian and Hirata-san routed all the BF/... cables via the BF cap (except for the four TM OSEM cables, where we're still waiting for extensions).
 * We built up the assembly frame and security structure to the SF level and craned in the SF.
 * We installed the SF-BF rod and flying saucer, and suspended the BF/... section. We will need about 600 g on the BF cap for balance and SF keystone height, which is as expected and not a problem.
 * Hirata-san collected a suitable CuBe spring and bracket parts from Type A. He ultrasonically cleaned the bracket and then installed the bracket and spring on the F0. The frequency increased from 0.5 Hz to 0.625 Hz, so he did another round of compression, from 30 mm to 31.3 mm.
 * Enzo soldered some short and/or broken cables to make longer cables that we need urgently. He got in touch with Yamamoto-san to arrange bringing them to Toyama University and ultrasonically cleaning them.
 * We pulled out cables running to the OMMT area that were used for the old OSEM/geophone testing setup and started a new geophone testing setup in the SR3 area using the optical table from the SR2 assembly frame.
 * Hirose-san reported results from his astigmatism test on the second SRM small optic and metal mass. With the tight shims (1.0 mm thickness, as used for the installed SRM) there was substantial astigmatism, but with the next looser available size (1.5 mm) there was no astigmatism but the optic is held very poorly and rattles. Hirose-san is ordering some intermediate thicknesses and will make a recommendation. However he will almost certainly suggest that we change the shims on the hanging SRM, so we need to think about whether that is feasible.
Line 22: Line 20:
 * Remove First Contact.
 * Move SR2 in-air cables.
 * Unlock and realign suspension.
 * Akutsu-san collected the parts we will need for the SR2 OL so that Terrence can install it next week.
 * Hirata-san supervised the disassembly of the assembly frame. The pieces are now in the IMMT area, although we may need to move them again because they're a bit in the way.

==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
===== SR2 =====
 * Set up OL.
 * Possibly do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
 * Possibly add more arc weights, to get below 0.1 Hz.
Line 26: Line 30:
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.
 * Suspend IM and tweak height/balance.

==== Plan for week of 10/1 ====
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.

==== Plan for week of 10/8 ====
 * Monday 10/8 is Sports Day.
 * Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
 * Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.
===== SR2 =====
 * Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.
===== SRM =====
 
 * Continue assembly.
Line 52: Line 36:
==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri (except Hirata-san to take compensation day Friday or Monday (TBD)).
===== SRM =====
 * Continue assembly.
Line 53: Line 42:
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
* Terrence: 10/8-12, 10/29-11/2 at Kamioka.
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/22

SRM
  • We borrowed the TM HPCDs from SR2 and SR3 so that SRM had HPCDs for IM-H, IM-V and GAS.
  • Fabian adjusted the last two OSEMs (IM-H2 and H3).
  • We closed the BF and weighed the BF/... section.
  • Fabian and Hirata-san routed all the BF/... cables via the BF cap (except for the four TM OSEM cables, where we're still waiting for extensions).
  • We built up the assembly frame and security structure to the SF level and craned in the SF.
  • We installed the SF-BF rod and flying saucer, and suspended the BF/... section. We will need about 600 g on the BF cap for balance and SF keystone height, which is as expected and not a problem.
  • Hirata-san collected a suitable CuBe spring and bracket parts from Type A. He ultrasonically cleaned the bracket and then installed the bracket and spring on the F0. The frequency increased from 0.5 Hz to 0.625 Hz, so he did another round of compression, from 30 mm to 31.3 mm.

  • Enzo soldered some short and/or broken cables to make longer cables that we need urgently. He got in touch with Yamamoto-san to arrange bringing them to Toyama University and ultrasonically cleaning them.
  • We pulled out cables running to the OMMT area that were used for the old OSEM/geophone testing setup and started a new geophone testing setup in the SR3 area using the optical table from the SR2 assembly frame.
  • Hirose-san reported results from his astigmatism test on the second SRM small optic and metal mass. With the tight shims (1.0 mm thickness, as used for the installed SRM) there was substantial astigmatism, but with the next looser available size (1.5 mm) there was no astigmatism but the optic is held very poorly and rattles. Hirose-san is ordering some intermediate thicknesses and will make a recommendation. However he will almost certainly suggest that we change the shims on the hanging SRM, so we need to think about whether that is feasible.

SR2
  • Akutsu-san collected the parts we will need for the SR2 OL so that Terrence can install it next week.
  • Hirata-san supervised the disassembly of the assembly frame. The pieces are now in the IMMT area, although we may need to move them again because they're a bit in the way.

Plan for week of 10/29

  • Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.

SR2
  • Set up OL.
  • Possibly do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
  • Possibly add more arc weights, to get below 0.1 Hz.

SRM
  • Continue assembly.

To-Do Lists, Schedule

Plan for week of 10/29

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri (except Hirata-san to take compensation day Friday or Monday (TBD)).

SRM
  • Continue assembly.

Vacation/Visitor Info

  • Terrence: 10/29-11/2 at Kamioka.