==== Report for week of 9/17 ====
 * Monday 9/17 was holiday.
 * We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico.
 * We set the SF damper gap to 6 mm.
 * We set the SR2 pitch with the optic lever, aligned the IRM, and set all the OSEMs to have good clearance and midrange output.
 * We locked the SR2 suspension, craned it into the tank and hooked the LBB damper rings (but not the LBB yet).
 * With help from Ohishi-san, we removed the First Contact from SR2.
 * Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc.
 * Mark added some thin arc weights to the inventory and finalized the number of various types to order (8*38 mm + 9*10 mm).
 * Panwei copied control filters over from the SR3.
 
==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
==== Report for week of 10/8 ====
 * This was Panwei's last week (for now at least) - thanks for all the help!
 * Thanks also to Terrence for visiting again for the week.
===== SR3 =====
 * Terrence and Mark finished setting up the LEN half of the OL (Simon had roughly placed the components). They ran a new cable for LEN in the cable tray and relaid the cable for TILT to get it off the floor.
 * Terrence worked on diagonalizing the LEN OL. A report is forthcoming.
===== SRM =====
 * Mark installed a pair of power supplies in the SRM and copied settings across to the SRM real-time model.
 * Fabian did lots of rack cabling, including installing and connecting BIO cards.
 * Mark and Hirata-san checked and adjusted the pitch of the BF (with a bubble level) and the IM/... section (with the OL.
 * Mark and Panwei installed the sides of the IRM and the IM OSEMs.
 * Hirata-san hung the dummy load from the F0 and started compressing the blade. There was a significant lateral offset (≈2-3 mm towards the blade at 5:30) at first but Takahashi-san advised that it would probably improve with compression, and it did.
 * Mark and Hirata-san cleared off most of two optical tables and a set of shelves in the OMMT area that Type B had been using but were now required by Somiya-san and Ohishi-san. We still need to remove the geophone and OSEM testing setups.
Line 21: Line 21:
 * Move SR2 in-air cables.
 * Unlock and realign suspension.
 * Mark, Enzo and Hirata-san all inspected the lower section of the SR2 to see if there were any interference points that might explain some unexpected peaks in the TFs that weren't present before installation. There were no stops touching, but some TM OSEM cables were rubbing against each other. [??? Did the fix work?]
 * We removed the tank lid, and Enzo and Panwei inspected the cabling that had been done during Enzo's vacation and installed some new cables that had arrived. They also unlocked the IP.

==== Plan for week of 10/15 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SR2=====
 * Continue shakedown.
Line 24: Line 29:
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.
 * Suspend IM and tweak height/balance.

==== Plan for week of 10/1 ====
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.

==== Plan for week of 10/8 ====
 * Monday 10/8 is Sports Day.
 * Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
 * Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.
===== SR2/SR3 =====
 * Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.
===== SRM =====
 * Continue installation.
 * Align IRM with IM.
 * Suspend/weigh/balance the BF/... section.
 * Build up the AF and SS to the SF level.
 * Install the SF.
Line 52: Line 40:
 * Enzo: 9/15 through 10/8 vacation in Chile.
* Terrence: 10/8-12, 10/29-11/2 at Kamioka.
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/8

  • This was Panwei's last week (for now at least) - thanks for all the help!
  • Thanks also to Terrence for visiting again for the week.

SR3
  • Terrence and Mark finished setting up the LEN half of the OL (Simon had roughly placed the components). They ran a new cable for LEN in the cable tray and relaid the cable for TILT to get it off the floor.
  • Terrence worked on diagonalizing the LEN OL. A report is forthcoming.

SRM
  • Mark installed a pair of power supplies in the SRM and copied settings across to the SRM real-time model.
  • Fabian did lots of rack cabling, including installing and connecting BIO cards.
  • Mark and Hirata-san checked and adjusted the pitch of the BF (with a bubble level) and the IM/... section (with the OL.
  • Mark and Panwei installed the sides of the IRM and the IM OSEMs.
  • Hirata-san hung the dummy load from the F0 and started compressing the blade. There was a significant lateral offset (≈2-3 mm towards the blade at 5:30) at first but Takahashi-san advised that it would probably improve with compression, and it did.
  • Mark and Hirata-san cleared off most of two optical tables and a set of shelves in the OMMT area that Type B had been using but were now required by Somiya-san and Ohishi-san. We still need to remove the geophone and OSEM testing setups.

SR2
  • Mark, Enzo and Hirata-san all inspected the lower section of the SR2 to see if there were any interference points that might explain some unexpected peaks in the TFs that weren't present before installation. There were no stops touching, but some TM OSEM cables were rubbing against each other. [??? Did the fix work?]
  • We removed the tank lid, and Enzo and Panwei inspected the cabling that had been done during Enzo's vacation and installed some new cables that had arrived. They also unlocked the IP.

Plan for week of 10/15

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

===== SR2=====

  • Continue shakedown.

SRM
  • Align IRM with IM.
  • Suspend/weigh/balance the BF/... section.
  • Build up the AF and SS to the SF level.
  • Install the SF.

To-Do Lists, Schedule

Vacation/Visitor Info

  • Terrence: 10/29-11/2 at Kamioka.