  * Mark and Fabian worked at Kamioka with Fujii-san:
   * We attempted to measure the tilt sensitivity of the accelerometers by adding shims under the legs but gave up when we discovered that picking up and putting down the accelerometer perturbs the zero point even without shims. We will probably need a special tilt stage to do this properly.
   * We took some frequency and Q measurements. The results were amplitude dependent. Joris thinks that this is due to not operating the accelerometers close enough to zero DC output.
   * We set up for a test of the geophone noise. One geophone is reading half the output of the others - one side of a differential signal has probably failed.
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Hung RM.
   * Did permanent routing of RM OSEM cables to IM.
   * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
   * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
   * Did temporary routing of RM OSEMs to PR2 rack (4 channels).
Line 11: Line 13:
   * Received extra compensation masses and washed them.
   * Received PI guides, assembled them and shipped them to Kamioka.
   * Removed adhesive from base of BS flags in preparation for regluing.
   * Did assembly drawings for cable clamps and other add-on parts for BF and SF.
   * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
   * Started 3D CAD for SRM.
   * Checked flag design.
   * Assembled a bottom filter (ongoing).
   * Cleaned maraging rods.
Line 16: Line 19:
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Installation stuff
   * "Ceiling" work in BS clean booth (removal of second floor section) scheduled for Fri 7/1.
   * Assembly frame construction scheduled for 7/4
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
      • Hung RM.
      • Did permanent routing of RM OSEM cables to IM.
      • Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
      • Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
      • Did temporary routing of RM OSEMs to PR2 rack (4 channels).
    • Hirata-san:
      • Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
      • Started 3D CAD for SRM.
      • Checked flag design.
      • Assembled a bottom filter (ongoing).
      • Cleaned maraging rods.
  • Type B ongoing issues
  • Longer term to-do list
    • Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
      • Part "disk security" top has to be modified - screw positions do not match.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of BS Assembly Procedure E1504235, E1504235 draft (Mark) - ONGOING

    • Lower breadboard installation to be incorporated into the procedure document.
    • Work on BS simulation (Fabian)
    • Do BS Simulink model (Mark, Kokeyama)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)