==== Report for week of 10/1 ====
===== SR2 =====
 * We solved a mystery with the height of the BF keystone: it turns out that running the table KOACH filters in the tank warms it up (by about 1.5°C) and causes significant sag (700 µm). D'oh!
 * We ran power to the pico drivers.
 * We got the lower section of the SR2 fairly well aligned with just a bit of adjustment with the IM pitch and roll picos.
 * We helped Lucia double-check the geometry of the IP - the current matrix calculation assumes the FRs and the LVDT sensors and actuators are colocated, which is much closer to true than for the BS, but not quite right.
 * We gave up on doing anything more with SR2 for now because we're waiting on extra extension cables for the PI and Fujii-kun will want to borrow one of the geophones next week for a huddle test with new geophones.
===== SRM =====
 * We set the pitch of the SRM and RM, tightened the clamps and removed the winch system.
 * We installed the BF crossbars of the assembly frame and the BF ring section of the security structure.
 * We lifted the IM/... section on the load gauge to find its weight.
 * We craned in the BF and removed the cap.
 * We installed the BF-IRM rods and the IRM top plate.
 * We installed the BF-IM maraging rod and flying saucer cable clamps.
 * We suspended the IM/... section and adjusted the trim masses for balance and total mass. It took quite a lot of adjustment in each of pitch, roll and vertical. The vertical was due to the fact that the weight of the IM/... section is very close to that of SR2/SR3 but the SRM BF is about 0.5 kg weaker. The roll was due to the fact that the default configuration of trim mass had no correction for the horizontal wedge on the optic. However the pitch is a bit of a mystery - nearly all of the removed mass had to come off the AR side. Fortunately we were able to correct for it entirely with masses we had in hand.
 * We routed the TM OSEM cables via the flying saucer up to the underside of the BF.
 * We got 2 power supplies from Shimode-san so we can fire up the SRM rack next week. He will also supply suitable cables to connect the power supplies to the DC power strip in the rack.
 * We received the replated yoke for the SRM top filter.
==== Report for week of 1/14 ====
 * Etc
  * Mark inventoried lots of items and updated the [[KAGRA/Subgroups/VIS/TypeB/Status|Status]] page.
 * SR2
  * Hirata-san helped with installing the obelisk on the LBB, and added counterweights to get the LBB level and at the right height for the first rough alignment. However the springs were still at or near the top stops, so he later pulled down the LBB with excess mass, locked the blades at the bottom of their range and reset the LBB rods and damping magnet ring, aiming off by 10 mm so that it would be correct when the LBB was allowed to rise to midrange on the blades. He left it pressed down for now so that Hirose-san could apply FC. Early next week he will release it and do the final ballasting.
  * Hirose-san applied and removed FC on both sides of the optic for cleanliness.
 * SR3
  * Enzo installed IM damping filters.
  * Mark installed a BIO Converter for the stepper remote enable (which will eventually also be used for the WD).
  * Fabian researched buoyancy compensation and pre-applied as much as possible to SR3. The total compensation needed is 0.19 mm for F0, 0.48 mm for SF and 0.46 mm for BF, total 1.23 mm. 1.0 mm had been applied with the jacks. The initial plan was to apply the calculated amounts at each level but then offset F0 1.0 mm lower to undo the jack adjustment. However SF was stuck approximately 1 mm lower than it needed to end up, so the buoyancy correction for it will have to be done at F0, and F0 will end up quite close to nominal.
 * Fabian also offloaded the IM pico yaw adjustment done by Enomoto-kun-tachi to the F0 yaw stepper. This left the OSEMs well-centered, so we will not need to adjust them and the LBB can be released.
 * SRM
  * Enzo fixed the broken triple in-air pico adapter cable and we plugged it back in.
  * Fabian calibrated the F0 FR.
  * Enzo and Terrence installed the arc weights and geophones, tuned and centered the IP, and centered and calibrated the FRs.
  * Mirapro helped us with the camera viewport issue by giving us a gasket of the same type but a different brand from their stock, which snapped easily into place. We then installed the viewport on the tank. Kokeyama-san will help us add the camera and camera LAN cable next week.
  * Simon gave us all the remaining items for the SRM OL except the 3D stage for the LEN QPD.
Line 25: Line 23:
==== Plan for week of 10/8 ====
 * Monday 10/8 is Sports Day.
 * Enzo returns Tuesday 10/9.
 * Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
 * Enzo, Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.
===== SR2/SR3 =====
 * Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.
 * Suspend/weigh/balance the BF/... section.
==== Plan for week of 2/4 ====
 * Mark, Enzo, Fabian, Terrence at Kamioka Mon-Fri.
 * Hirata-san at Kamioka Mon+TBD.
 * Etc
  * Split SR2, SR3 and SRM RT models.
  * Get rid of the power reel behind SRM and plug stuff into the new power point instead.
 * BS
  * Run BNC cables for stepper remote enable, plug into BIO, debug.
 * SR2
  * Do buoyancy correction.
  * Install camera viewport.
  * Install camera.
  * Run BNC cables for stepper remote enable, plug into BIO, debug.
 * SR3
  * Release LBB.
  * Ballast LBB.
  * Install camera viewport.
  * Install camera.
  * Debug stepper remote enable.
 * SRM
  * Install camera.
  * Hook LBB
  * Ballast LBB.
  * Do buoyancy correction.
  * Set up OL.
  * Debug stepper remote enable.
Line 38: Line 50:
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation/Visitor Info ====
 * Enzo: 9/15 through 10/8 vacation in Chile.
 * Terrence: 10/8-12, 10/29-11/2 at Kamioka.
==== Vacation/Travel Info ====
 * Constitution Day, 2/11.
 * Mark and Enzo at KIW in Perugia, 2/12-18.
 * Enzo vacation, 3/5.
 * Enzo et al. Farewell Party, 3/7.
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/14

  • Etc
    • Mark inventoried lots of items and updated the Status page.

  • SR2
    • Hirata-san helped with installing the obelisk on the LBB, and added counterweights to get the LBB level and at the right height for the first rough alignment. However the springs were still at or near the top stops, so he later pulled down the LBB with excess mass, locked the blades at the bottom of their range and reset the LBB rods and damping magnet ring, aiming off by 10 mm so that it would be correct when the LBB was allowed to rise to midrange on the blades. He left it pressed down for now so that Hirose-san could apply FC. Early next week he will release it and do the final ballasting.
    • Hirose-san applied and removed FC on both sides of the optic for cleanliness.
  • SR3
    • Enzo installed IM damping filters.
    • Mark installed a BIO Converter for the stepper remote enable (which will eventually also be used for the WD).
    • Fabian researched buoyancy compensation and pre-applied as much as possible to SR3. The total compensation needed is 0.19 mm for F0, 0.48 mm for SF and 0.46 mm for BF, total 1.23 mm. 1.0 mm had been applied with the jacks. The initial plan was to apply the calculated amounts at each level but then offset F0 1.0 mm lower to undo the jack adjustment. However SF was stuck approximately 1 mm lower than it needed to end up, so the buoyancy correction for it will have to be done at F0, and F0 will end up quite close to nominal.
  • Fabian also offloaded the IM pico yaw adjustment done by Enomoto-kun-tachi to the F0 yaw stepper. This left the OSEMs well-centered, so we will not need to adjust them and the LBB can be released.
  • SRM
    • Enzo fixed the broken triple in-air pico adapter cable and we plugged it back in.
    • Fabian calibrated the F0 FR.
    • Enzo and Terrence installed the arc weights and geophones, tuned and centered the IP, and centered and calibrated the FRs.
    • Mirapro helped us with the camera viewport issue by giving us a gasket of the same type but a different brand from their stock, which snapped easily into place. We then installed the viewport on the tank. Kokeyama-san will help us add the camera and camera LAN cable next week.
    • Simon gave us all the remaining items for the SRM OL except the 3D stage for the LEN QPD.

Plan for week of 2/4

  • Mark, Enzo, Fabian, Terrence at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Mon+TBD.
  • Etc
    • Split SR2, SR3 and SRM RT models.
    • Get rid of the power reel behind SRM and plug stuff into the new power point instead.
  • BS
    • Run BNC cables for stepper remote enable, plug into BIO, debug.
  • SR2
    • Do buoyancy correction.
    • Install camera viewport.
    • Install camera.
    • Run BNC cables for stepper remote enable, plug into BIO, debug.
  • SR3
    • Release LBB.
    • Ballast LBB.
    • Install camera viewport.
    • Install camera.
    • Debug stepper remote enable.
  • SRM
    • Install camera.
    • Hook LBB
    • Ballast LBB.
    • Do buoyancy correction.
    • Set up OL.
    • Debug stepper remote enable.

Vacation/Travel Info

  • Constitution Day, 2/11.
  • Mark and Enzo at KIW in Perugia, 2/12-18.
  • Enzo vacation, 3/5.
  • Enzo et al. Farewell Party, 3/7.
  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.