==== Report for week of 10/15 ====
===== SRM =====
 * We received the fourth feedthrough we had been waiting for and installed it on the AF.
 * Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model.
 * Fabian and Enzo connected up the Sat Amps.
 * Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange.
 * Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough.
 * Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade.
 * Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2.
 * We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS.
 * Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT.
 * Enzo made a new batch of feedthrough adapters.
===== SR2 =====
 * We finalized the geophone cabling and reinstalled the geophones.
 * We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz.
 * Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29.
==== Plan for week of 10/22 ====
 * Friday is NAOJ Open Day Prep - no Kamioka work.
 * Mark, Hirata-san and Fabian at Kamioka Mon-Thu.
 * Enzo at Kamioka Tue-Thu.
===== SR2 =====
 * Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
 * Continue shakedown.
 * Gather parts for the OL (with help from Simon).
===== SRM =====
 * Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified.
 * Suspend/weigh/balance the BF/... section.
 * Build up the AF and SS to the SF level.
 * Install the SF.
==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
===== SR2 =====
 * Set up OL.
===== SRM =====
 * Continue assembly.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
==== Report for the week of 3/25 ====
 * Mark and Fabian helped Fujii-kun with PR2. The problem turned out to be two broken flags. Hirata-san drew up a design for a jig to help reglue the flags in situ.
 * Fabian documented the height budget for the Type B suspension in the wiki ([[KAGRA/Subgroups/VIS/OpsManual/TypeB/SR3Data]] etc).
 * Terrence wrote up the final version of his OL diagonalization scheme.
 * Terrence worked on L2P decoupling for the TM.
 * Terrence and Mark edited the Type B Guardian to put turning on the payload damping later in the sequence, to help ensure that the OSEMs are not touching by the time they're needed (which can happen if the BF is buoyancy compensated for vacuum but the suspension is vented).
 * Mark started on a big tidy-up of the cleanbooth.
==== Plan for week of 3/25 ====
 * Mark, Fabian at Kamioka Mon-Fri.
 * Assist with PR2.
 * Work on Type B paper.
 * Tidy up.
  * Throw out foil and other garbage.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.
  * Return all unused cables to tent.
  * Tidy up cables in rear of SR2 rack.
Line 46: Line 23:
==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.
==== Vacation/Travel Info ====
 * Enzo's last day 3/29.
 * Terrence's last day for now, 3/29.
 * Mark compensation day for 3/21: 3/29. (He is not really typing these minutes, and anyone who sounds like him in the meeting is an impostor!)
 * Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's vacation from about 5/22 to 6/11 (TBD).
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/25

  • Mark and Fabian helped Fujii-kun with PR2. The problem turned out to be two broken flags. Hirata-san drew up a design for a jig to help reglue the flags in situ.
  • Fabian documented the height budget for the Type B suspension in the wiki (KAGRA/Subgroups/VIS/OpsManual/TypeB/SR3Data etc).

  • Terrence wrote up the final version of his OL diagonalization scheme.
  • Terrence worked on L2P decoupling for the TM.
  • Terrence and Mark edited the Type B Guardian to put turning on the payload damping later in the sequence, to help ensure that the OSEMs are not touching by the time they're needed (which can happen if the BF is buoyancy compensated for vacuum but the suspension is vented).
  • Mark started on a big tidy-up of the cleanbooth.

Plan for week of 3/25

  • Mark, Fabian at Kamioka Mon-Fri.
  • Assist with PR2.
  • Work on Type B paper.
  • Tidy up.
    • Throw out foil and other garbage.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.
    • Return all unused cables to tent.
    • Tidy up cables in rear of SR2 rack.

Vacation/Travel Info

  • Enzo's last day 3/29.
  • Terrence's last day for now, 3/29.
  • Mark compensation day for 3/21: 3/29. (He is not really typing these minutes, and anyone who sounds like him in the meeting is an impostor!)
  • Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's vacation from about 5/22 to 6/11 (TBD).
  • Mark's final day 6/28.