==== Report for week of 10/22 ====
===== SRM =====
 * We borrowed the TM HPCDs from SR2 and SR3 so that SRM had HPCDs for IM-H, IM-V and GAS.
 * Fabian adjusted the last two OSEMs (IM-H2 and H3).
 * We closed the BF and weighed the BF/... section.
 * Fabian and Hirata-san routed all the BF/... cables via the BF cap (except for the four TM OSEM cables, where we're still waiting for extensions).
 * We built up the assembly frame and security structure to the SF level and craned in the SF.
 * We installed the SF-BF rod and flying saucer, and suspended the BF/... section. We will need about 600 g on the BF cap for balance and SF keystone height, which is as expected and not a problem.
 * Hirata-san collected a suitable CuBe spring and bracket parts from Type A. He ultrasonically cleaned the bracket and then installed the bracket and spring on the F0. The frequency increased from 0.5 Hz to 0.625 Hz, so he did another round of compression, from 30 mm to 31.3 mm.
 * Enzo soldered some short and/or broken cables to make longer cables that we need urgently. He got in touch with Yamamoto-san to arrange bringing them to Toyama University and ultrasonically cleaning them.
 * We pulled out cables running to the OMMT area that were used for the old OSEM/geophone testing setup and started a new geophone testing setup in the SR3 area using the optical table from the SR2 assembly frame.
 * Hirose-san reported results from his astigmatism test on the second SRM small optic and metal mass. With the tight shims (1.0 mm thickness, as used for the installed SRM) there was substantial astigmatism, but with the next looser available size (1.5 mm) there was no astigmatism but the optic is held very poorly and rattles. Hirose-san is ordering some intermediate thicknesses and will make a recommendation. However he will almost certainly suggest that we change the shims on the hanging SRM, so we need to think about whether that is feasible.
==== Report for week of 2/12 (February 12th) ====
 * On Saturday we moved the vertical IM OSEMs in order to compensate for a large pitch in the IM introduced when the IR laser as aligned.
  * I took transfer functions over the weekend and the system looks healthy.
  * Although moving the OSEMs was done successfully, I accidentally pulled the cables and moved the flying saucer cable clamp set. I rotated it back judging the position by visual inspection, but an IM yaw drift appeared since then. It's moving with a speed of 0.2 urad/min.
  * On Tuesday we moved the Im back to zero but the drift continued. At the time of writing these lines it is at -833 urad, with H2 and H3 at 93 um and 47 um and still drifting.
 * On Saturday we connected the SRM geophones in-air cables and confirmed we had a signal.
  * However, on Wednesday morning the geophones are not giving any signal. We cheked the master model channel and realized the problem was not the slave model. We suspect a hardware fault.
  * I checked the in-air cables were connected.
 * We released the SRM optical bench and wiped the places where sticky tape was used to fix support blocks.
 * We wiped the SR2 optical bench and security structure. SR3 and SRM had been wiped by Hirose-san, Hirata-san and Fujii-kun.
 * Terrence worked on splitting the real-time models for all the SR suspensions.
 * Today the pumping down of the central area will begin around noon. We will monitor the four inverted pendulums.
Line 19: Line 18:
===== SR2 =====
 * Akutsu-san collected the parts we will need for the SR2 OL so that Terrence can install it next week.
 * Hirata-san supervised the disassembly of the assembly frame. The pieces are now in the IMMT area, although we may need to move them again because they're a bit in the way.
==== Report for week of 1/28 ====
 * Etc
  * Mark inventoried lots of items and updated the [[KAGRA/Subgroups/VIS/TypeB/Status|Status]] page.
 * SR2
  * Hirata-san helped with installing the obelisk on the LBB, and added counterweights to get the LBB level and at the right height for the first rough alignment. However the springs were still at or near the top stops, so he later pulled down the LBB with excess mass, locked the blades at the bottom of their range and reset the LBB rods and damping magnet ring, aiming off by 10 mm so that it would be correct when the LBB was allowed to rise to midrange on the blades. He left it pressed down for now so that Hirose-san could apply FC. Early next week he will release it and do the final ballasting.
  * Hirose-san applied and removed FC on both sides of the optic for cleanliness.
  * Mirapro hooked the LBB.
 * SR3
  * Enzo installed IM damping filters.
  * Mark installed a BIO Converter for the stepper remote enable (which will eventually also be used for the WD).
  * Fabian researched buoyancy compensation and pre-applied as much as possible to SR3. The total compensation needed is 0.19 mm for F0, 0.48 mm for SF and 0.46 mm for BF, total 1.23 mm. 1.0 mm had been applied with the jacks. The initial plan was to apply the calculated amounts at each level but then offset F0 1.0 mm lower to undo the jack adjustment. However SF was stuck approximately 1 mm lower than it needed to end up, so the buoyancy correction for it will have to be done at F0, and F0 will end up quite close to nominal.
 * Fabian also offloaded the IM pico yaw adjustment done by Enomoto-kun-tachi to the F0 yaw stepper. This left the OSEMs well-centered, so we will not need to adjust them and the LBB can be released.
 * SRM
  * Enzo fixed the broken triple in-air pico adapter cable and we plugged it back in.
  * Fabian calibrated the F0 FR.
  * Enzo and Terrence installed the arc weights and geophones, tuned and centered the IP, and centered and calibrated the FRs.
  * Mirapro helped us with the camera viewport issue by giving us a gasket of the same type but a different brand from their stock, which snapped easily into place. We then installed the viewport on the tank. Kokeyama-san will help us add the camera and camera LAN cable next week.
  * Simon gave us all the remaining items for the SRM OL except the 3D stage for the LEN QPD.
Line 23: Line 37:
==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
===== SR2 =====
 * Set up OL.
 * Possibly do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
 * Possibly add more arc weights, to get below 0.1 Hz.
===== SRM =====
 * Continue assembly.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
==== Plan for week of 2/4 ====
 * Mark, Enzo, Fabian, Terrence at Kamioka Mon-Fri.
 * Hirata-san at Kamioka Mon+TBD.
 * Etc
  * Split SR2, SR3 and SRM RT models.
  * Get rid of the power reel behind SRM and plug stuff into the new power point instead.
 * BS
  * Run BNC cables for stepper remote enable, plug into BIO, debug.
 * SR2
  * Do buoyancy correction.
  * Install camera viewport.
  * Install camera.
  * Run BNC cables for stepper remote enable, plug into BIO, debug.
 * SR3
  * Release LBB.
  * Ballast LBB.
  * Install camera viewport.
  * Install camera.
  * Debug stepper remote enable.
 * SRM
  * Install camera.
  * Ballast LBB.
  * Do buoyancy correction.
  * Set up OL.
  * Debug stepper remote enable.
Line 36: Line 63:
==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri (except Hirata-san to take compensation day Friday or Monday (TBD)).
===== SRM =====
 * Continue assembly.

==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.
==== Vacation/Travel Info ====
 * Constitution Day, 2/11.
 * Mark and Enzo at KIW in Perugia, 2/12-18.
 * Enzo vacation, 3/5.
 * Enzo et al. Farewell Party, 3/7.
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 2/12 (February 12th)

  • On Saturday we moved the vertical IM OSEMs in order to compensate for a large pitch in the IM introduced when the IR laser as aligned.
    • I took transfer functions over the weekend and the system looks healthy.
    • Although moving the OSEMs was done successfully, I accidentally pulled the cables and moved the flying saucer cable clamp set. I rotated it back judging the position by visual inspection, but an IM yaw drift appeared since then. It's moving with a speed of 0.2 urad/min.
    • On Tuesday we moved the Im back to zero but the drift continued. At the time of writing these lines it is at -833 urad, with H2 and H3 at 93 um and 47 um and still drifting.
  • On Saturday we connected the SRM geophones in-air cables and confirmed we had a signal.
    • However, on Wednesday morning the geophones are not giving any signal. We cheked the master model channel and realized the problem was not the slave model. We suspect a hardware fault.
    • I checked the in-air cables were connected.
  • We released the SRM optical bench and wiped the places where sticky tape was used to fix support blocks.
  • We wiped the SR2 optical bench and security structure. SR3 and SRM had been wiped by Hirose-san, Hirata-san and Fujii-kun.
  • Terrence worked on splitting the real-time models for all the SR suspensions.
  • Today the pumping down of the central area will begin around noon. We will monitor the four inverted pendulums.

Report for week of 1/28

  • Etc
    • Mark inventoried lots of items and updated the Status page.

  • SR2
    • Hirata-san helped with installing the obelisk on the LBB, and added counterweights to get the LBB level and at the right height for the first rough alignment. However the springs were still at or near the top stops, so he later pulled down the LBB with excess mass, locked the blades at the bottom of their range and reset the LBB rods and damping magnet ring, aiming off by 10 mm so that it would be correct when the LBB was allowed to rise to midrange on the blades. He left it pressed down for now so that Hirose-san could apply FC. Early next week he will release it and do the final ballasting.
    • Hirose-san applied and removed FC on both sides of the optic for cleanliness.
    • Mirapro hooked the LBB.
  • SR3
    • Enzo installed IM damping filters.
    • Mark installed a BIO Converter for the stepper remote enable (which will eventually also be used for the WD).
    • Fabian researched buoyancy compensation and pre-applied as much as possible to SR3. The total compensation needed is 0.19 mm for F0, 0.48 mm for SF and 0.46 mm for BF, total 1.23 mm. 1.0 mm had been applied with the jacks. The initial plan was to apply the calculated amounts at each level but then offset F0 1.0 mm lower to undo the jack adjustment. However SF was stuck approximately 1 mm lower than it needed to end up, so the buoyancy correction for it will have to be done at F0, and F0 will end up quite close to nominal.
  • Fabian also offloaded the IM pico yaw adjustment done by Enomoto-kun-tachi to the F0 yaw stepper. This left the OSEMs well-centered, so we will not need to adjust them and the LBB can be released.
  • SRM
    • Enzo fixed the broken triple in-air pico adapter cable and we plugged it back in.
    • Fabian calibrated the F0 FR.
    • Enzo and Terrence installed the arc weights and geophones, tuned and centered the IP, and centered and calibrated the FRs.
    • Mirapro helped us with the camera viewport issue by giving us a gasket of the same type but a different brand from their stock, which snapped easily into place. We then installed the viewport on the tank. Kokeyama-san will help us add the camera and camera LAN cable next week.
    • Simon gave us all the remaining items for the SRM OL except the 3D stage for the LEN QPD.

Plan for week of 2/4

  • Mark, Enzo, Fabian, Terrence at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Mon+TBD.
  • Etc
    • Split SR2, SR3 and SRM RT models.
    • Get rid of the power reel behind SRM and plug stuff into the new power point instead.
  • BS
    • Run BNC cables for stepper remote enable, plug into BIO, debug.
  • SR2
    • Do buoyancy correction.
    • Install camera viewport.
    • Install camera.
    • Run BNC cables for stepper remote enable, plug into BIO, debug.
  • SR3
    • Release LBB.
    • Ballast LBB.
    • Install camera viewport.
    • Install camera.
    • Debug stepper remote enable.
  • SRM
    • Install camera.
    • Ballast LBB.
    • Do buoyancy correction.
    • Set up OL.
    • Debug stepper remote enable.

Vacation/Travel Info

  • Constitution Day, 2/11.
  • Mark and Enzo at KIW in Perugia, 2/12-18.
  • Enzo vacation, 3/5.
  • Enzo et al. Farewell Party, 3/7.
  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.