Differences between revisions 339 and 415 (spanning 76 versions)
Revision 339 as of 2018-10-28 19:16:53
Size: 4354
Editor: MarkBarton
Comment:
Revision 415 as of 2019-05-16 16:03:54
Size: 2401
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
Line 6: Line 5:
==== Report for week of 10/22 ====
===== SRM =====
 * We borrowed the TM HPCDs from SR2 and SR3 so that SRM had HPCDs for IM-H, IM-V and GAS.
 * Fabian adjusted the last two OSEMs (IM-H2 and H3).
 * We closed the BF and weighed the BF/... section.
 * Fabian and Hirata-san routed all the BF/... cables via the BF cap (except for the four TM OSEM cables, where we're still waiting for extensions).
 * We built up the assembly frame and security structure to the SF level and craned in the SF.
 * We installed the SF-BF rod and flying saucer, and suspended the BF/... section. We will need about 600 g on the BF cap for balance and SF keystone height, which is as expected and not a problem.
 * Hirata-san collected a suitable CuBe spring and bracket parts from Type A. He ultrasonically cleaned the bracket and then installed the bracket and spring on the F0. The frequency increased from 0.5 Hz to 0.625 Hz, so he did another round of compression, from 30 mm to 31.3 mm.
 * Enzo soldered some short and/or broken cables to make longer cables that we need urgently. He got in touch with Yamamoto-san to arrange bringing them to Toyama University and ultrasonically cleaning them.
 * We pulled out cables running to the OMMT area that were used for the old OSEM/geophone testing setup and started a new geophone testing setup in the SR3 area using the optical table from the SR2 assembly frame.
 * Hirose-san reported results from his astigmatism test on the second SRM small optic and metal mass. With the tight shims (1.0 mm thickness, as used for the installed SRM) there was substantial astigmatism, but with the next looser available size (1.5 mm) there was no astigmatism but the optic is held very poorly and rattles. Hirose-san is ordering some intermediate thicknesses and will make a recommendation. However he will almost certainly suggest that we change the shims on the hanging SRM, so we need to think about whether that is feasible.
==== Report for Golden Week ====
 * Mark monitored vent and pumpdown, and worked on vistools.py.
Line 19: Line 8:
===== SR2 =====
 * Akutsu-san gathered the parts we will need for the SR2 OL so that Terrence can install it next week.
 * Hirata-san supervised the disassembly of the assembly frame. The pieces are now in the IMMT area, although we may need to move them again because they're a bit in the way.
==== Report for the week of 5/6 ====
 * Lucia and Terrence got the blending working for the IP LVDTs and geophones.
 * Terrence and Mark modified the models and MEDM screens to add a new IP block, IDAMP, for damping using the blended signal with inertial information, and a new DAMPMODE block for ramping smoothly between IDAMP and the old DAMP.
 * Mark worked on vistools.py, improving the support for cdsMuxMatrix blocks (e.g., OSEM2EUL) and adding support for cdsRampMuxMatrix blocks (e.g., the newly introduced DAMPMODE). He also created two sets of unit tests, unittest.py and unittest.sh, for the two modes of use (as a Python module in other Python programs, and as a command-line utility in bash).
Line 23: Line 13:
==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
===== SR2 =====
 * Set up OL.
 * Possibly do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
 * Possibly add more arc weights, to get below 0.1 Hz.
===== SRM =====
 * Electronics
  * More cable soldering?
  * Get soldered cables ultrasonically cleaned.
  * Collect unused cables for return to AEL.
 * PI
  * Finalize tuning.
  * Add more cable clamps.
  * Prepare SF magnet ring.
 * Main sequence
  * Cable/test SF LVDT and FR.
  * Decide and install SF internal ballast mass (probably 1 Promec).
  * Reinstall SF cap.
  * Weigh SF/... section.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
==== Report for week of 5/13 ====
 * Terrence and Mark looked at the velocity and angular velocity noise of the SR2 as reported by the LEN OL. The Y signal was fairly clean and the Y RMS angular velocity requirement was met. However the L signal was quite noisy, and was also contaminating the P signal due to the large cross terms in the diagonalization matrix. The RMS L from 5 Hz down with damping on was around 10 µm/s, which is 10 times the requirement. However little of this was due to pendulum resonances - most of the noise was featureless and broadband. In displacement units the noise was flat up to about 1 Hz and then smoothly rolled off to f^-2. The noise in the raw P and Y signals (not yet divided by the sum) was about 10 times the noise in the SUM
 * We tried improving the noise with different whitening settings. Increasing the overall gain, increasing it at the QPD but reducing it at the whitening filter, and switching off the 1-10Hz boost whitening filter (and compensating software filter) had no effect. Blocking the beam reduced the noise by about 2 orders and brought the raw P and Y in line with the SUM, suggesting that the problem was before the QPD.
 * Mark swapped in an improved version of `vistools.py`, debugged a few small issues, and simplified the `TYPEB.py` Guardian.
Line 51: Line 18:
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri (except Hirata-san to take compensation day Friday or Monday (TBD)).
===== SRM =====
 * Main sequence
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
  * Unlock IP and center roughly.
  * Calibrate IP LVDTs.
  * Check/adjust alignment of SS.
  * Add arc weights and geophones (or extra mass equivalent to geophones).
  * Cable/test geophones.
  * Improve centering/tuning of IP and SS alignment.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.

==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.
==== Vacation/Travel Info ====
 * Terrence's next visit from 4/18 to 7/27.
 * Mark's US vacation from 5/22 to 6/11.
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for Golden Week

  • Mark monitored vent and pumpdown, and worked on vistools.py.

Report for the week of 5/6

  • Lucia and Terrence got the blending working for the IP LVDTs and geophones.
  • Terrence and Mark modified the models and MEDM screens to add a new IP block, IDAMP, for damping using the blended signal with inertial information, and a new DAMPMODE block for ramping smoothly between IDAMP and the old DAMP.
  • Mark worked on vistools.py, improving the support for cdsMuxMatrix blocks (e.g., OSEM2EUL) and adding support for cdsRampMuxMatrix blocks (e.g., the newly introduced DAMPMODE). He also created two sets of unit tests, unittest.py and unittest.sh, for the two modes of use (as a Python module in other Python programs, and as a command-line utility in bash).

Report for week of 5/13

  • Terrence and Mark looked at the velocity and angular velocity noise of the SR2 as reported by the LEN OL. The Y signal was fairly clean and the Y RMS angular velocity requirement was met. However the L signal was quite noisy, and was also contaminating the P signal due to the large cross terms in the diagonalization matrix. The RMS L from 5 Hz down with damping on was around 10 µm/s, which is 10 times the requirement. However little of this was due to pendulum resonances - most of the noise was featureless and broadband. In displacement units the noise was flat up to about 1 Hz and then smoothly rolled off to f^-2. The noise in the raw P and Y signals (not yet divided by the sum) was about 10 times the noise in the SUM
  • We tried improving the noise with different whitening settings. Increasing the overall gain, increasing it at the QPD but reducing it at the whitening filter, and switching off the 1-10Hz boost whitening filter (and compensating software filter) had no effect. Blocking the beam reduced the noise by about 2 orders and brought the raw P and Y in line with the SUM, suggesting that the problem was before the QPD.
  • Mark swapped in an improved version of vistools.py, debugged a few small issues, and simplified the TYPEB.py Guardian.

Vacation/Travel Info

  • Terrence's next visit from 4/18 to 7/27.
  • Mark's US vacation from 5/22 to 6/11.
  • Mark's final day 6/28.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)