Differences between revisions 34 and 209 (spanning 175 versions)
Revision 34 as of 2016-07-01 13:11:54
Size: 2400
Editor: MarkBarton
Comment:
Revision 209 as of 2017-12-01 13:33:12
Size: 1857
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian worked at Kamioka with Fujii-san:
   * We attempted to measure the tilt sensitivity of the accelerometers by adding shims under the legs but gave up when we discovered that picking up and putting down the accelerometer perturbs the zero point even without shims. We will probably need a special tilt stage to do this properly.
   * We took some frequency and Q measurements. The results were amplitude dependent. Joris thinks that this is due to not operating the accelerometers close enough to zero DC output.
   * We set up for a test of the geophone noise. One geophone is reading half the output of the others - one of the adapter cables is broken.
  * Hirata-san:
   * Received extra compensation masses and washed them.
   * Received PI guides, assembled them and shipped them to Kamioka.
   * Received backup set of pillar for security structure (with M10 instead of M12 holes at top).
   * Removed adhesive from base of BS flags in preparation for regluing.
   * Did assembly drawings for cable clamps and other add-on parts for BF and SF.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Feedthrough Adapters
   * Connectors RECEIVED.
  * SR machining test ONGOING.
  * Installation stuff
   * "Ceiling" work in BS clean booth (removal of second floor section) scheduled for Fri 7/1.
   * Assembly frame construction scheduled for 7/4
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - ordered with assembly frame, will arrive next week.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====

 * We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
 * Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
 * Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
 * Enzo found nearly all in-vacuum cables.
 * Enzo and Shoda-san got several more loops closed on the BS.
 * Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
 * Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
 * Hirata-san worked on SR procurement.
 * Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.
 
==== Plan for week of 12/4 ====
 * Mark at Kamioka.
 * Fabian at f2f satellite meeting Mon, then Kamioka.
 * Enzo at f2f then Mitaka.
 * Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
 * Kozu-kun Thu only.
 * Mirror gluing.
 * IM assembly and pico test.

==== Plan for week of 12/11
 * Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
 * Kozu-kun Mon-Thu only.
 * Assembly frame alignment and optical table centering.
 * Move trolley system from SR3.
 * OL setup.

==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo TBD, probably 12/22-1/3
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
  • Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
  • Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
  • Enzo found nearly all in-vacuum cables.
  • Enzo and Shoda-san got several more loops closed on the BS.
  • Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
  • Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
  • Hirata-san worked on SR procurement.
  • Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.

Plan for week of 12/4

  • Mark at Kamioka.
  • Fabian at f2f satellite meeting Mon, then Kamioka.
  • Enzo at f2f then Mitaka.
  • Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
  • Kozu-kun Thu only.
  • Mirror gluing.
  • IM assembly and pico test.

==== Plan for week of 12/11

  • Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
  • Kozu-kun Mon-Thu only.
  • Assembly frame alignment and optical table centering.
  • Move trolley system from SR3.
  • OL setup.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

Vacation Info

  • Mark 12/22-1/3
  • Enzo TBD, probably 12/22-1/3
  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21