Differences between revisions 34 and 302 (spanning 268 versions)
Revision 34 as of 2016-07-01 13:11:54
Size: 2400
Editor: MarkBarton
Comment:
Revision 302 as of 2018-07-06 14:12:21
Size: 3632
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian worked at Kamioka with Fujii-san:
   * We attempted to measure the tilt sensitivity of the accelerometers by adding shims under the legs but gave up when we discovered that picking up and putting down the accelerometer perturbs the zero point even without shims. We will probably need a special tilt stage to do this properly.
   * We took some frequency and Q measurements. The results were amplitude dependent. Joris thinks that this is due to not operating the accelerometers close enough to zero DC output.
   * We set up for a test of the geophone noise. One geophone is reading half the output of the others - one of the adapter cables is broken.
  * Hirata-san:
   * Received extra compensation masses and washed them.
   * Received PI guides, assembled them and shipped them to Kamioka.
   * Received backup set of pillar for security structure (with M10 instead of M12 holes at top).
   * Removed adhesive from base of BS flags in preparation for regluing.
   * Did assembly drawings for cable clamps and other add-on parts for BF and SF.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Feedthrough Adapters
   * Connectors RECEIVED.
  * SR machining test ONGOING.
  * Installation stuff
   * "Ceiling" work in BS clean booth (removal of second floor section) scheduled for Fri 7/1.
   * Assembly frame construction scheduled for 7/4
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - ordered with assembly frame, will arrive next week.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 7/2 ====
 * We double-checked the bounce frequency and it was indeed around 0.5 Hz with the CuBe auxiliary spring installed.
 * We prepared (but did not yet install) 6 arc weights for tuning the IP.
 * We unlocked the security structure from the assembly frame, and raised the whole system on the top jacks. We then unlocked the IP and adjusted the leveling so the IP was centered. We then had to loosen two of the poles at the top level of the security structure to make it vertical again, because it turns out that the jack receptacles (which also serve as the IP leg bases) are welded at very uneven depths in the bottom surface of the PI, so the IP and the bottom surface can't be level at once.
 * We debugged an issue with the height of the payload. It turns out that due to a buildup of errors (especially an extra 3 mm between the SF and BF), the payload is some 5-6 mm low with the F0 keystone at CAD height. Since the frequency is roughly independent of height around 0.5 Hz, we decided to go with a higher F0 keystone.
 * Enzo and Eleonora routed all the SF/... cables up to the PI.
 * We found we needed 4.7 kg of extra mass to get the desired keystone height, so we decided to put the third Cu segment (3.3 kg) back on, purely as ballast.
 * We put some extra small masses on the SF cap to level it. The suspension is now fully ballasted and trimmed except for 1 Promec mass (455 g) standing in for the new PI yaw stepper motor assembly (estimated 330 g) which is yet to arrive.
 * We took all the SR sat amps back to Mozumi to get new capacitors installed, and grabbed three spares for use while that is being done.
 * We investigated and documented Tanaka-san's watchdog for the BS, to see if the BIO Converter chassis that it uses could also drive reset lines for stepper motor driver boxes.
 * Hirata-san and Terrence characterized the last 4 F0 blades.
 * Hirata-san and Terrence installed blades in the top filter for SR2 and tuned it to 0.5 Hz (with the CuBe auxiliary spring) over three rounds of compression.


==== Plan for week of 7/9 ====
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
===== Main Sequence =====
 * Check/restore alignment of payload, especially optic pitch.
 * Install and cable geophones.
 * Install arc weights.
 * Tune IP.
 * Install, cable PI yaw stepper.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Calibrate PI LVDTs and FRs.
 * Cabling, testing, TFs.

===== F0/LBB Stuff =====
 * Finalize PI #1 for SR2; crane into SR2 cleanbooth.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
 * Set tank jacks to nominal height.
 * Clear space for PI #2 (SRM) work.

==== Plan for week of 7/16 ====
 * Monday 7/16 is Sea Day.
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.
===== Main Sequence =====
 * Lock suspension.
 * Crane into tank.
 * Unlock suspension.
 * Rearrange cables.
 * Test.
===== F0/LBB Stuff =====
 * Install correct IP in PI #2.
 * Crane PI #2 to second floor.
 * Rebuild top filter of PI #2.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/2

  • We double-checked the bounce frequency and it was indeed around 0.5 Hz with the CuBe auxiliary spring installed.

  • We prepared (but did not yet install) 6 arc weights for tuning the IP.
  • We unlocked the security structure from the assembly frame, and raised the whole system on the top jacks. We then unlocked the IP and adjusted the leveling so the IP was centered. We then had to loosen two of the poles at the top level of the security structure to make it vertical again, because it turns out that the jack receptacles (which also serve as the IP leg bases) are welded at very uneven depths in the bottom surface of the PI, so the IP and the bottom surface can't be level at once.
  • We debugged an issue with the height of the payload. It turns out that due to a buildup of errors (especially an extra 3 mm between the SF and BF), the payload is some 5-6 mm low with the F0 keystone at CAD height. Since the frequency is roughly independent of height around 0.5 Hz, we decided to go with a higher F0 keystone.
  • Enzo and Eleonora routed all the SF/... cables up to the PI.
  • We found we needed 4.7 kg of extra mass to get the desired keystone height, so we decided to put the third Cu segment (3.3 kg) back on, purely as ballast.
  • We put some extra small masses on the SF cap to level it. The suspension is now fully ballasted and trimmed except for 1 Promec mass (455 g) standing in for the new PI yaw stepper motor assembly (estimated 330 g) which is yet to arrive.
  • We took all the SR sat amps back to Mozumi to get new capacitors installed, and grabbed three spares for use while that is being done.
  • We investigated and documented Tanaka-san's watchdog for the BS, to see if the BIO Converter chassis that it uses could also drive reset lines for stepper motor driver boxes.
  • Hirata-san and Terrence characterized the last 4 F0 blades.
  • Hirata-san and Terrence installed blades in the top filter for SR2 and tuned it to 0.5 Hz (with the CuBe auxiliary spring) over three rounds of compression.

Plan for week of 7/9

  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.

Main Sequence
  • Check/restore alignment of payload, especially optic pitch.
  • Install and cable geophones.
  • Install arc weights.
  • Tune IP.
  • Install, cable PI yaw stepper.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Calibrate PI LVDTs and FRs.
  • Cabling, testing, TFs.

F0/LBB Stuff
  • Finalize PI #1 for SR2; crane into SR2 cleanbooth.
  • Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
  • Set tank jacks to nominal height.
  • Clear space for PI #2 (SRM) work.

Plan for week of 7/16

  • Monday 7/16 is Sea Day.
  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.

Main Sequence
  • Lock suspension.
  • Crane into tank.
  • Unlock suspension.
  • Rearrange cables.
  • Test.

F0/LBB Stuff
  • Install correct IP in PI #2.
  • Crane PI #2 to second floor.
  • Rebuild top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)