Differences between revisions 34 and 304 (spanning 270 versions)
Revision 34 as of 2016-07-01 13:11:54
Size: 2400
Editor: MarkBarton
Comment:
Revision 304 as of 2018-07-20 13:48:01
Size: 1648
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian worked at Kamioka with Fujii-san:
   * We attempted to measure the tilt sensitivity of the accelerometers by adding shims under the legs but gave up when we discovered that picking up and putting down the accelerometer perturbs the zero point even without shims. We will probably need a special tilt stage to do this properly.
   * We took some frequency and Q measurements. The results were amplitude dependent. Joris thinks that this is due to not operating the accelerometers close enough to zero DC output.
   * We set up for a test of the geophone noise. One geophone is reading half the output of the others - one of the adapter cables is broken.
  * Hirata-san:
   * Received extra compensation masses and washed them.
   * Received PI guides, assembled them and shipped them to Kamioka.
   * Received backup set of pillar for security structure (with M10 instead of M12 holes at top).
   * Removed adhesive from base of BS flags in preparation for regluing.
   * Did assembly drawings for cable clamps and other add-on parts for BF and SF.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Feedthrough Adapters
   * Connectors RECEIVED.
  * SR machining test ONGOING.
  * Installation stuff
   * "Ceiling" work in BS clean booth (removal of second floor section) scheduled for Fri 7/1.
   * Assembly frame construction scheduled for 7/4
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - ordered with assembly frame, will arrive next week.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 7/17 ====
 * We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement.
 * We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force.
 * We calibrated all the PI LVDTs.
 * We set the SF damper ring gap.
 * We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods.
 * Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank).
 * We installed more cable clamps on the SR2 PI.

==== Plan for week of 7/23 ====
 * Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Hirata-san at Kamioka Mon-Thu.
 * Mirapro moves assembly frame ≈7/25 (Wed).

===== SR3 =====
 * Unlock suspension.
 * Rearrange cables.
 * Test.
===== SR2 =====
 * Finish PI prep.
 * Crane into AF, suspend.
 * Start cable routing.
===== SRM =====
 * Prepare to assemble SRM metal mass (most parts due Wed 7/25).
 * Help Mirapro with AF move.
 * Start rebuild of top filter of PI #2.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Hirata-san at Mitaka 7/27.
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/17

  • We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement.
  • We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force.
  • We calibrated all the PI LVDTs.
  • We set the SF damper ring gap.
  • We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods.
  • Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank).
  • We installed more cable clamps on the SR2 PI.

Plan for week of 7/23

  • Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Mon-Thu.
  • Mirapro moves assembly frame ≈7/25 (Wed).

SR3
  • Unlock suspension.
  • Rearrange cables.
  • Test.

SR2
  • Finish PI prep.
  • Crane into AF, suspend.
  • Start cable routing.

SRM
  • Prepare to assemble SRM metal mass (most parts due Wed 7/25).
  • Help Mirapro with AF move.
  • Start rebuild of top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Hirata-san at Mitaka 7/27.
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.